Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: myex65

Home > PMI > PMI Professional in Business Analysis > PMI-PBA

PMI-PBA PMI Professional in Business Analysis Question and Answers

Question # 4

After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides

enough information to check if the requirement has been met.

Which of the following would work best in this case?

A.

User stories

B.

Functional specifications

C.

Flow chart

D.

Prototyping

Full Access
Question # 5

A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation

process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume

reporting required by the company's financial department. The business analyst for the project determines that the selection criteria

needed was not specified in the system requirements or design specifications.

Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement

was missed?

A.

Root cause analysis, fishbone diagram, and/or the Five Whys

B.

Root cause analysis, problem tracking, and/or benchmarking

C.

Scope modeling, Ishikawa diagram, and/or the Five Whys

D.

Cause and effect diagram, brainstorming, and/or the Five Whys

Full Access
Question # 6

A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.

What can be used to analyze this information and determine project scope?

A.

Capability table

B.

As-is process

C.

Requirements traceability matrix

D.

Root cause analysis

Full Access
Question # 7

A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?

A.

How requirement changes will impact the requirements baseline

B.

How requirement changes will be implemented

C.

How requirement changes will impact the validation plan

D.

How requirement changes will be communicated

Full Access
Question # 8

The business analyst is in the process of implementing a solution for a customer. The team is having difficulty confirming if certain requirements have been met.

What could have caused this issue?

A.

The test engineer has not properly communicated requirements to the team.

B.

Not all stakeholders were involved during requirements elicitation.

C.

Acceptance criteria for the requirements were not measurable.

D.

Requirements were not adequately reviewed with the project sponsor.

Full Access
Question # 9

A project was in the design phase when the team received news of a new regulatory mandate that affects the project. The requirements have already been approved and baselined. If the new requirements are not included, the company will be out of compliance and may

face monetary penalties.

What should the business analyst do next?

A.

Obtain approval from the project manager.

B.

Define the project scope.

C.

Follow the change control process.

D.

Update the requirements.

Full Access
Question # 10

A company is developing a new e-commerce platform to enter a new market segment. Development is well under way when the government issues a new set of regulations.

Which course of action should the business analyst take?

A.

Evaluate if the new set of regulations is aligned with the business case.

B.

Evaluate the impact of the change on the project schedule.

C.

Obtain management sign-off on the new set of regulations.

D.

Check the traceability matrix to identify affected use cases.

Full Access
Question # 11

A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?

A.

Request that the project manager identify all affected project stakeholders.

B.

Provide all signed-off project documentation to the stakeholders for information purposes only.

C.

Engage all stakeholders early in the requirements gathering phase to define acceptance criteria.

D.

Solicit feedback and add requirements to the project backlog.

Full Access
Question # 12

During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:

A.

interviewed to understand how the user's work would be impacted.

B.

involved in the development and sign-off of the business requirements.

C.

identified as a stakeholder as part of the stakeholder analysis.

D.

given the opportunity to review the user acceptance test scripts.

Full Access
Question # 13

The business analyst has been assigned to a project involving a low number of stakeholders. Which technique should be used to elicit requirements?

A.

Survey

B.

Interview

C.

Document analysis

D.

Interface analysis

Full Access
Question # 14

A national company with offices in every state in the country has deployed a solution to allow employees to view their health benefits online. The business analyst on the project team is validating solution results to assess whether or not the solution has achieved the desired business result.

Which is the best technique to gather information from employees regarding their satisfaction with the solution?

A.

Survey

B.

Focus groups

C.

Interface analysis

D.

Organization modeling

Full Access
Question # 15

A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

A.

Questionnaires

B.

Group decision making

C.

Stakeholder analysis

D.

Prototyping

Full Access
Question # 16

A business analyst is planning the business analysis activities for a new payroll project. Due to a tight timeline, the analyst advises stakeholders that the requirements sessions should begin as soon as possible.

Which key factor drives the selection of business analyst activities to be included in the project?

A.

Communication plan

B.

Project life cycle

C.

Return on investment (ROI)

D.

Payback period

Full Access
Question # 17

The business analyst is conducting a feasibility study to understand how well a potential solution fits into the organization. What kind of feasibility assessment is the business analyst undertaking?

A.

Operational

B.

Technical

C.

Cost-effectiveness

D.

Time

Full Access
Question # 18

A company is developing a new risk management system. The company expects the system to evolve in the near future due to changing government regulations.

Which approach will better cope with the requirements’ volatility?

A.

Storyboarding

B.

Multivoting

C.

Phased baselining

D.

Comparative analysis

Full Access
Question # 19

A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.

How can the business analyst determine how well the solution meets the business case?

A.

Conduct a user survey.

B.

Ask the sponsor for feedback.

C.

Survey the project.

D.

Compare the results of day-in-the-life (DITL) testing and integration testing.

Full Access
Question # 20

A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new

functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create

project plans, schedule meetings, and provide meeting minutes.

In the scenario above, what is the role of the technical staff and testing team from Company A?

A.

Accountable

B.

Consult

C.

Responsible

D.

Inform

Full Access
Question # 21

A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?

A.

Multivoting

B.

MoSCoW

C.

Time-boxing

D.

Budget analysis

Full Access
Question # 22

An organization is in the process of replacing its current system. The business analyst is charged with ensuring that all current connections to other systems remain functional after the upgrade.

What analysis should the business analyst conduct to facilitate a successful migration?

A.

Document

B.

User interface

C.

Interface

D.

Systems

Full Access
Question # 23

A business analyst has captured all of the requirements from the various stakeholders within the organization and has compiled them into a complete list. After reviewing the list of requirements with the stakeholders, it is determined that the list of requirements is too large and will exceed the allotted budget.

Which tool or technique should the business analyst use with the stakeholders to prioritize the requirements to determine which requirements are approved, deferred, or rejected?

A.

SMART Goals

B.

Moscow Analysis

C.

SWOT Analysis

D.

Timeboxing Analysis

Full Access
Question # 24

Once a new project has been identified, the business analyst works with project team members to define what will be included in and excluded from the new system. Which of the following has the business analyst defined?

A.

Solution design

B.

Business requirements

C.

Solution scope

D.

Business case

Full Access
Question # 25

To reduce the amount of time and effort needed to create a product specification for a project, the business analyst plans to reuse:

A.

quantitative analysis.

B.

risk assessments.

C.

qualitative analysis.

D.

requirements.

Full Access
Question # 26

Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s)

versioning?

A.

Statement of work

B.

Project plan

C.

Problem or opportunity statement

D.

Traceability matrix

Full Access
Question # 27

The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change?

A.

Requirements management plan

B.

Impact analysis

C.

Scope statement

D.

Pareto analysis

Full Access
Question # 28

A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.

From the business analysis perspective, the main reason for this business failure was a failure to:

A.

set the product positioning.

B.

review and evaluate market expectations.

C.

gather the appropriate usability requirements.

D.

establish measurable success criteria in the business case.

Full Access
Question # 29

A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.

Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?

A.

The requirements verification process is documented.

B.

The requirements elicitation process is documented.

C.

The requirements validation process is documented.

D.

The requirements approval process is documented.

Full Access
Question # 30

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

A.

Manage solution scope.

B.

Manage requirements traceability.

C.

Manage requirements prioritization.

D.

Manage assumptions and constraints.

Full Access
Question # 31

A type of requirements document that would be the most valuable to a database administrator would be:

A.

a data flow diagram.

B.

a business process diagram.

C.

an entity relationship diagram.

D.

an object diagram.

Full Access
Question # 32

What are some of the components of a requirements management plan?

A.

Requirements definition, functional and non-functional requirements, and decision-making process

B.

Requirements work plan, requirements definition, and traceability matrix template

C.

Requirements work plan, prioritization process, and traceability matrix template

D.

Requirements definition, requirements attribute template, and traceability matrix template

Full Access
Question # 33

A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.

Which type of requirements are these?

A.

In-scope

B.

Tested

C.

Implemented

D.

Out-of-scope

Full Access
Question # 34

A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.

What document should the business analyst use to determine the relationship of the requirement to the business need?

A.

Traceability matrix

B.

Requirements management plan

C.

Requirements package

D.

Reliability matrix

Full Access
Question # 35

Which statement accurately depicts what changes can be made to requirements after they are baselined?

A.

Requirements can be changed only with sponsor approval.

B.

Requirements can be changed through a defined process.

C.

Requirements cannot be changed once development begins.

D.

Requirements cannot be changed once user acceptance testing begins.

Full Access
Question # 36

Which tool should be used to improve the communication of product needs with the stakeholders and to improve their understanding?

A.

Requirements management tool that documents requirements and their properties and relationships

B.

Document management system and a relationship matrix that groups all related documents

C.

Modeling tool integrated into a version control feature that ensures that team knowledge is captured

D.

Workflow management tool that documents the flow of information

Full Access
Question # 37

A business analyst is working on a project's acceptance criteria. In an early collaboration with the company's stakeholders, the business analyst identified several user groups within the company: "Purchaser," "Shipper," "Customer," and "Agent." These user groups

categorize stakeholders with similar needs and create a detailed narrative.

Which technique did the business analyst use for evaluating the solution's acceptance criteria?

A.

Stakeholder analysis

B.

Job analysis

C.

Persona analysis

D.

Risk analysis

Full Access
Question # 38

A company is in the final phases of implementing a project for a client. Which tool or technique could the business analyst use to iteratively validate the solution?

A.

Expected vs. actual results

B.

Expected vs. actual costs

C.

Schedule variance

D.

Quality variance

Full Access
Question # 39

How should a business analyst determine whether a solution satisfies business requirements?

A.

By reviewing the results of user acceptance testing

B.

By evaluating the solution against the project charter

C.

By conducting a brainstorming session with end users

D.

By reviewing the traceability matrix

Full Access
Question # 40

The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release. A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.

Which decision role was used?

A.

Majority

B.

Plurality

C.

Consensus

D.

Unanimity

Full Access
Question # 41

A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?

A.

Project schedule and cost baseline

B.

Requirements traceability matrix

C.

Requirements attributes table

D.

Sequence diagram

Full Access
Question # 42

A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.

Which of the following techniques would the business analyst use to identify stakeholders?

A.

Brainstorming

B.

State diagram

C.

Estimation

D.

Prototyping

Full Access
Question # 43

A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.

What would be the most viable technique to use in this scenario?

A.

A review of the solution prototype

B.

A brainstorming session

C.

A use-case development session

D.

A review of the previous version

Full Access
Question # 44

Which technique or tool is used to obtain acceptance of the delivered product?

A.

Expert judgment

B.

Facilitated workshops

C.

Inspection

D.

Contextual inquiry

Full Access
Question # 45

A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning.

What technique could the business analyst use to help alleviate this concern?

A.

Decomposition model

B.

Context diagram

C.

Swimlane diagram

D.

Business analysis work plan

Full Access
Question # 46

Testing on a project has been completed. In order to proceed with deployment, a decision is needed.

Who should the business analyst contact to review the testing results and get approval to proceed with deployment?

A.

The tester identified in the testing strategy

B.

The person identified in the RACI matrix

C.

The project manager identified in the project charter

D.

The project sponsor identified in the scope document

Full Access
Question # 47

Through user acceptance testing, a software flaw was identified. What should the business analyst do next as part of the root cause analysis in order to analyze and resolve the discrepancy?

A.

Create a fishbone diagram.

B.

Create an interface analysis.

C.

Create a Delphi estimation.

D.

Create a functional decomposition.

Full Access
Question # 48

The project team is working on test scripts to test a solution. Which source can be used for building tests of end-to-end business processes across business functions and systems?

A.

Prototype model

B.

Feature model

C.

Context diagram

D.

Use case

Full Access
Question # 49

A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.

How can the business analyst determine the impact on existing requirements?

A.

Perform a stakeholder analysis.

B.

Review the requirements traceability matrix.

C.

Use time-boxing to defer the new requirement.

D.

Update the use case documentation.

Full Access
Question # 50

Which of the following actions will contribute most to the success of the initial stage of the project?

A.

Interview stakeholders to clearly define the problem.

B.

Document the requirements and obtain sign-off.

C.

Establish the change control process of the project.

D.

Define the acceptance criteria required during the acceptance phase.

Full Access
Question # 51

An organization is evaluating the possibility of conducting business internationally. Which factors should be investigated at the onset of the initiative?

A.

Deliverables to be produced

B.

Impacts on requirements baseline

C.

External dependencies

D.

Change control processes

Full Access
Question # 52

The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.

What should the business analyst do?

A.

Develop a change control process.

B.

Obtain approval from the project sponsor.

C.

Document changes as they occur.

D.

Hold firm on scope and reject changes.

Full Access
Question # 53

Once the requirements are compared to internal and external quality standards, what should the business analyst do next?

A.

Set the priority of the requirements.

B.

Communicate the requirements to stakeholders.

C.

Ensure that the requirements are validated.

D.

Baseline the requirements.

Full Access
Question # 54

A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.

Which next step should the business analyst take?

A.

Start documenting requirements.

B.

Obtain approval on the plan.

C.

Store the document for safe keeping.

D.

Start implementing the project.

Full Access
Question # 55

A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:

A.

requirements gathering workshops with the stakeholders.

B.

requirements acceptance with the customer.

C.

requirements validation with the testers.

D.

requirements sign-off with the customer.

Full Access
Question # 56

The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown schedule (WBS) and schedule. However, a key requirement was not implemented in the release.

Which is a possible reason why the requirement was not implemented?

A.

The requirements management plan was not updated with the change.

B.

The scope management plan was not updated with the change.

C.

The requirements traceability matrix was not updated with the change.

D.

The schedule management plan was not updated with the change.

Full Access
Question # 57

The customer and the business analyst are collaborating in the development of a solution scope. It is important for the customer to:

A.

communicate changes to requirements only when they are completely defined.

B.

spend the time required to provide, clarify, and elaborate requirements.

C.

challenge assessments of the cost and feasibility of requirements.

D.

perform an alternatives analysis for requirements implementation.

Full Access
Question # 58

A startup company sells organic vegetable and fruit smoothies. Management is tracking a rapid decrease in sales of their best-selling juice, so they contract a business analyst to identify solutions in order to increase sales by comparing similar products offered by competitors.

Which technique or tool should be used?

A.

Competitive analysis

B.

Benchmarking

C.

Trend analysis

D.

Focus group

Full Access
Question # 59

Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:

A.

prepare a test procedure for the product to discuss at the requirements review.

B.

start designing the product to impress the customer with the amount of progress achieved early in the project.

C.

evaluate the requirements and highlight those that cannot be met or need to be deferred.

D.

request a contract amendment to delete any requirements from the contract that will be difficult to meet.

Full Access
Question # 60

Which of the following is a properly written requirement statement?

A.

The pot shall be lightweight and heat up quickly.

B.

The pot shall be usable in the oven or on the stove.

C.

The pot shall be manufactured in the following colors: yellow, red, brown, blue.

D.

The pot shall prominently display the company brand.

Full Access