A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.
What is the best approach to resolve this issue?
The document that defines the process for managing requirements revisions is the:
The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.
What should the business analyst do?
Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:
A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?
Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.
What should the business analyst recommend to the project manager?
A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.
How can the business analyst determine the impact on existing requirements?
What should a business analyst do after discovering that two solution requirements conflict?
A new business analyst has taken over on a project that is in the development phase. The project manager is looking for an update on requirements status.
What should the business analyst use to help communicate the status?
The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.
Which project artifact could the test team review to help identify acceptance criteria?
A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.
Which of the following is the best strategy to define the appropriate acceptance criteria?
After analyzing a set of requirements documents, it is determined that the requirements are not yet ready for peer review. This was most likely caused by:
A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.
The business analyst tells the stakeholder that the requirement status was changed to "deferred â€
What could have prevented the stakeholder from being surprised about the status change?
A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.
What can be used to analyze this information and determine project scope?
Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?
In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.
What task should the business analyst perform in order to identify these impacts?
Company A has set aside capital to invest in an upgrade to their scheduling system. Documentation of the current structure was presented to the business analyst. However, the description of certain steps is not documented clearly, and the business analyst has not been allowed to inspect the existing system. During elicitation, the business analyst asked questions of the schedulers as they performed functions in order to gain an understanding of the process.
Which type of elicitation technique did the business analyst use in this instance?
Last year, a company registered a high number of complaints about its customer service. Which of the following tools or techniques can help to identify the high-priority changes needed to improve that service?
The customer and the business analyst are collaborating in the development of a solution scope. It is important for the customer to:
After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?
After conducting a brainstorming session with a group of project participants, the business analyst feels that the elicited requirements are biased. Which tool or technique could be used to gain an objective, first-hand insight into tasks and activities that are difficult to describe?
Through user acceptance testing, a software flaw was identified. What should the business analyst do next as part of the root cause analysis in order to analyze and resolve the discrepancy?
When modeling processes or analyzing tasks, business rules can be uncovered by asking about:
Which of the following actions will contribute most to the success of the initial stage of the project?
The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.
What could have caused this?
The business analyst wishes to clarify the project's key business drivers and ensure that requirements can be prioritized to provide maximum business value. Which question should the business analyst ask of stakeholders to help obtain this clarification?
A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database. A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.
What should the business analyst do to ensure that the business need can be validated?
A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.
Which activity should the business analyst initiate before beginning requirements elicitation?
A company is in the final phases of implementing a project for a client. Which tool or technique could the business analyst use to iteratively validate the solution?
A company wants to improve the service to its customers by reducing complaint response time by 40%. To achieve this goal, it is necessary to redesign and optimize their internal processes and support it with a new product. The client thinks that disruption and short-term loss of productivity is inevitable.
Where can the business analyst best reflect the intangible costs associated with this change?
What should be done to ensure that the product design meets the stated requirements?
A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.
Which next step should the business analyst take?
A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?
A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning.
What technique could the business analyst use to help alleviate this concern?
A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.
Which of the following techniques would the business analyst use to identify stakeholders?
The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change?
The human resources, engineering, and marketing departments have provided feedback on the business needs for a new product. After analyzing the feedback from the three departments, it would be best to:
During the initial phase of a project, which technique could assist in identifying and categorizing the stakeholders?
A business analyst is working on a highly complex project and has elicited a large number of requirements from stakeholders in several departments. Due to the large number of requirements, the stakeholders have determined that they would like to prioritize them to minimize a potentially large scope.
Which technique could the business analyst use to manage requirements?
A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.
What document should the business analyst use to determine the relationship of the requirement to the business need?
A type of requirements document that would be the most valuable to a database administrator would be:
The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release. A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.
Which decision role was used?
Company A has initiated a project to update their online ordering system. The business analyst has noticed that the purchasing department, a primary stakeholder, is excluded from the list of stakeholders.
In which reference material can the business analyst find information about the missing project stakeholders?
The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget.
What should the team do to reduce the risk of rework?
A business analyst is working on a project's acceptance criteria. In an early collaboration with the company's stakeholders, the business analyst identified several user groups within the company: "Purchaser," "Shipper," "Customer," and "Agent." These user groups
categorize stakeholders with similar needs and create a detailed narrative.
Which technique did the business analyst use for evaluating the solution's acceptance criteria?
Which of the following best describes the function of the requirements baseline?
A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?
A document is being created that will detail the customer's needs for a product and will include a functional model, a data model, and a glossary of terms. This document is called a:
When eliciting requirements, a good time to consider using the interviewing method is when:
A business analyst is working on a project to implement a new call management system for a help desk. They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.
Which technique should the business analyst use to investigate the problem?
How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?
The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?
One of the main purposes for creating a requirements traceability matrix is to:
A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.
How would the business analyst define the scope of this project?
Which technique or tool is used to obtain acceptance of the delivered product?