Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: myex65

Home > PMI > PMI Professional in Business Analysis > PMI-PBA

PMI-PBA PMI Professional in Business Analysis Question and Answers

Question # 4

A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.

What is the best approach to resolve this issue?

A.

Meet with the customer and apologize for misunderstanding the business's need.

B.

Suggest re-estimating the requirement and following the change control process.

C.

Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.

D.

Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.

Full Access
Question # 5

The document that defines the process for managing requirements revisions is the:

A.

project management plan.

B.

change management plan.

C.

communications management plan.

D.

scope management plan.

Full Access
Question # 6

The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.

What should the business analyst do?

A.

Develop a change control process.

B.

Obtain approval from the project sponsor.

C.

Document changes as they occur.

D.

Hold firm on scope and reject changes.

Full Access
Question # 7

Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:

A.

prepare a test procedure for the product to discuss at the requirements review.

B.

start designing the product to impress the customer with the amount of progress achieved early in the project.

C.

evaluate the requirements and highlight those that cannot be met or need to be deferred.

D.

request a contract amendment to delete any requirements from the contract that will be difficult to meet.

Full Access
Question # 8

A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?

A.

The industry is unregulated.

B.

The project impact is contained within a small department of the company.

C.

Errors in the product could result in financial solvency.

D.

The organization follows an iterative project life cycle.

Full Access
Question # 9

Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.

What should the business analyst recommend to the project manager?

A.

Ask the developer's team manager for more resources.

B.

Review the business case to reconsider the project.

C.

Hire external subject matter experts for the core project team.

D.

Ask the sponsor for more resources.

Full Access
Question # 10

A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.

How can the business analyst determine the impact on existing requirements?

A.

Perform a stakeholder analysis.

B.

Review the requirements traceability matrix.

C.

Use time-boxing to defer the new requirement.

D.

Update the use case documentation.

Full Access
Question # 11

What should a business analyst do after discovering that two solution requirements conflict?

A.

Consult the sponsor(s) and log the constraint.

B.

Perform an impact analysis and propose a lower-cost alternative.

C.

Update the requirements baseline and upload it to the project repository.

D.

Communicate the conflict to stakeholders and facilitate a resolution.

Full Access
Question # 12

What can a business analyst use to track requirements documentation?

A.

Affinity diagram

B.

Data dictionary

C.

Business rules matrix

D.

Version control system

Full Access
Question # 13

A new business analyst has taken over on a project that is in the development phase. The project manager is looking for an update on requirements status.

What should the business analyst use to help communicate the status?

A.

Project charter

B.

Communication plan

C.

Business analysis plan

D.

Traceability matrix

Full Access
Question # 14

The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.

Which project artifact could the test team review to help identify acceptance criteria?

A.

Project scope

B.

Use cases

C.

RACI chart

D.

Delphi outcome

Full Access
Question # 15

A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.

Which of the following is the best strategy to define the appropriate acceptance criteria?

A.

Quantify the risks associated with the measurement errors and update the risk register.

B.

Ask the operations manager to formally accept the requirements documents.

C.

Plan a training session for the new system before it is handed over to the operations manager.

D.

Clearly define the maximum acceptable error rate for the new system.

Full Access
Question # 16

After analyzing a set of requirements documents, it is determined that the requirements are not yet ready for peer review. This was most likely caused by:

A.

some requirements having not yet been discussed in a work group session.

B.

the requirements’ reference codes not tracing to the attribute numbers in the work breakdown structure.

C.

the requirements documents having not yet received sign-off from the sponsor.

D.

the requirements not providing all of the information needed to define the work.

Full Access
Question # 17

A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.

The business analyst tells the stakeholder that the requirement status was changed to "deferred ”

What could have prevented the stakeholder from being surprised about the status change?

A.

The status should have been communicated to the requirement’s source.

B.

The status should have been reviewed prior to project launch.

C.

The status should have been communicated to all project stakeholders.

D.

The status should have been updated in the traceability matrix.

Full Access
Question # 18

A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.

What can be used to analyze this information and determine project scope?

A.

Capability table

B.

As-is process

C.

Requirements traceability matrix

D.

Root cause analysis

Full Access
Question # 19

Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?

A.

Deliver the existing product and then begin work on the requested changes.

B.

Trace the requirements and measure the impact of the requested changes on the existing delivery date.

C.

Schedule a review by the change control board (CCB) to determine next steps.

D.

Ask the developers to implement the changes.

Full Access
Question # 20

Which of the following is an example of a functional requirement?

A.

The system is able to require passwords.

B.

The system can be accessed from multiple locations.

C.

The system provides an user-friendly interface.

D.

The system can handle 3,000 user requests concurrently.

Full Access
Question # 21

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

A.

Manage solution scope.

B.

Manage requirements traceability.

C.

Manage requirements prioritization.

D.

Manage assumptions and constraints.

Full Access
Question # 22

Company A has set aside capital to invest in an upgrade to their scheduling system. Documentation of the current structure was presented to the business analyst. However, the description of certain steps is not documented clearly, and the business analyst has not been allowed to inspect the existing system. During elicitation, the business analyst asked questions of the schedulers as they performed functions in order to gain an understanding of the process.

Which type of elicitation technique did the business analyst use in this instance?

A.

Active observation

B.

Participatory observation

C.

Interview

D.

Simulation

Full Access
Question # 23

Last year, a company registered a high number of complaints about its customer service. Which of the following tools or techniques can help to identify the high-priority changes needed to improve that service?

A.

A work breakdown structure analysis of the service

B.

A Pareto analysis

C.

A flowchart of the service

D.

A cause-and-effect diagram

Full Access
Question # 24

The customer and the business analyst are collaborating in the development of a solution scope. It is important for the customer to:

A.

communicate changes to requirements only when they are completely defined.

B.

spend the time required to provide, clarify, and elaborate requirements.

C.

challenge assessments of the cost and feasibility of requirements.

D.

perform an alternatives analysis for requirements implementation.

Full Access
Question # 25

After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?

A.

Plan-driven approach

B.

Waterfall approach

C.

Analytical approach

D.

Change-driven approach

Full Access
Question # 26

After conducting a brainstorming session with a group of project participants, the business analyst feels that the elicited requirements are biased. Which tool or technique could be used to gain an objective, first-hand insight into tasks and activities that are difficult to describe?

A.

Questionnaires and surveys

B.

Document analysis

C.

Observation

D.

Traceability matrix

Full Access
Question # 27

Through user acceptance testing, a software flaw was identified. What should the business analyst do next as part of the root cause analysis in order to analyze and resolve the discrepancy?

A.

Create a fishbone diagram.

B.

Create an interface analysis.

C.

Create a Delphi estimation.

D.

Create a functional decomposition.

Full Access
Question # 28

When modeling processes or analyzing tasks, business rules can be uncovered by asking about:

A.

tasks that overlap with each other.

B.

work that may be performed out of sequence.

C.

reasons for choosing a particular course of action.

D.

task transitions that hinder organizational performance.

Full Access
Question # 29

Which of the following actions will contribute most to the success of the initial stage of the project?

A.

Interview stakeholders to clearly define the problem.

B.

Document the requirements and obtain sign-off.

C.

Establish the change control process of the project.

D.

Define the acceptance criteria required during the acceptance phase.

Full Access
Question # 30

The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.

What could have caused this?

A.

The product was not adequately tested in accordance with the test plan.

B.

The requirements matrix did not adequately track back to client requirements.

C.

Requirement changes were not properly identified in the project charter.

D.

The product design was not properly reviewed by the quality department.

Full Access
Question # 31

The business analyst wishes to clarify the project's key business drivers and ensure that requirements can be prioritized to provide maximum business value. Which question should the business analyst ask of stakeholders to help obtain this clarification?

A.

Which stakeholders have the most influence?

B.

Which functional areas are impacted?

C.

How is the organizational chart structured?

D.

What is the business need?

Full Access
Question # 32

A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database. A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.

What should the business analyst do to ensure that the business need can be validated?

A.

Document an assumption.

B.

Document a constraint.

C.

Document a defect.

D.

Document a business rule.

Full Access
Question # 33

A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.

Which activity should the business analyst initiate before beginning requirements elicitation?

A.

Prepare the requirements traceability matrix.

B.

Define how the solution will be evaluated.

C.

Draft a high-level data model.

D.

Document how the relevant systems interact.

Full Access
Question # 34

A company is in the final phases of implementing a project for a client. Which tool or technique could the business analyst use to iteratively validate the solution?

A.

Expected vs. actual results

B.

Expected vs. actual costs

C.

Schedule variance

D.

Quality variance

Full Access
Question # 35

A company wants to improve the service to its customers by reducing complaint response time by 40%. To achieve this goal, it is necessary to redesign and optimize their internal processes and support it with a new product. The client thinks that disruption and short-term loss of productivity is inevitable.

Where can the business analyst best reflect the intangible costs associated with this change?

A.

In the requirements specification document

B.

In the business case

C.

In the pay-back analysis

D.

In the balanced score card chart

Full Access
Question # 36

What should be done to ensure that the product design meets the stated requirements?

A.

Conduct multiple internal design reviews.

B.

Use a traceability matrix.

C.

Review lessons learned results.

D.

Engage an experienced development team.

Full Access
Question # 37

A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.

Which next step should the business analyst take?

A.

Start documenting requirements.

B.

Obtain approval on the plan.

C.

Store the document for safe keeping.

D.

Start implementing the project.

Full Access
Question # 38

A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?

A.

Project schedule and cost baseline

B.

Requirements traceability matrix

C.

Requirements attributes table

D.

Sequence diagram

Full Access
Question # 39

A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning.

What technique could the business analyst use to help alleviate this concern?

A.

Decomposition model

B.

Context diagram

C.

Swimlane diagram

D.

Business analysis work plan

Full Access
Question # 40

A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.

Which of the following techniques would the business analyst use to identify stakeholders?

A.

Brainstorming

B.

State diagram

C.

Estimation

D.

Prototyping

Full Access
Question # 41

The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change?

A.

Requirements management plan

B.

Impact analysis

C.

Scope statement

D.

Pareto analysis

Full Access
Question # 42

The human resources, engineering, and marketing departments have provided feedback on the business needs for a new product. After analyzing the feedback from the three departments, it would be best to:

A.

vote on the product's highest-value business needs.

B.

negotiate to best meet each department's objectives.

C.

collaborate on a product scope that aligns with the company’s objectives.

D.

delegate the decision to be made by the product sponsor.

Full Access
Question # 43

During the initial phase of a project, which technique could assist in identifying and categorizing the stakeholders?

A.

Business activity model

B.

RAC! matrix

C.

Power/interest grid

D.

Organization modeling

Full Access
Question # 44

A business analyst is working on a highly complex project and has elicited a large number of requirements from stakeholders in several departments. Due to the large number of requirements, the stakeholders have determined that they would like to prioritize them to minimize a potentially large scope.

Which technique could the business analyst use to manage requirements?

A.

MoSCoW

B.

SMART goals

C.

RACI models

D.

Storyboarding

Full Access
Question # 45

A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.

What document should the business analyst use to determine the relationship of the requirement to the business need?

A.

Traceability matrix

B.

Requirements management plan

C.

Requirements package

D.

Reliability matrix

Full Access
Question # 46

A type of requirements document that would be the most valuable to a database administrator would be:

A.

a data flow diagram.

B.

a business process diagram.

C.

an entity relationship diagram.

D.

an object diagram.

Full Access
Question # 47

The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release. A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.

Which decision role was used?

A.

Majority

B.

Plurality

C.

Consensus

D.

Unanimity

Full Access
Question # 48

Company A has initiated a project to update their online ordering system. The business analyst has noticed that the purchasing department, a primary stakeholder, is excluded from the list of stakeholders.

In which reference material can the business analyst find information about the missing project stakeholders?

A.

Organizational chart

B.

Business case

C.

Business analysis plan

D.

Business analyst communication plan

Full Access
Question # 49

The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget.

What should the team do to reduce the risk of rework?

A.

Ask the project sponsor to prioritize the requirements.

B.

Organize a new elicitation workshop.

C.

Perform a Pareto analysis on the requirements.

D.

Validate the requirements before continuing with development.

Full Access
Question # 50

A business analyst is working on a project's acceptance criteria. In an early collaboration with the company's stakeholders, the business analyst identified several user groups within the company: "Purchaser," "Shipper," "Customer," and "Agent." These user groups

categorize stakeholders with similar needs and create a detailed narrative.

Which technique did the business analyst use for evaluating the solution's acceptance criteria?

A.

Stakeholder analysis

B.

Job analysis

C.

Persona analysis

D.

Risk analysis

Full Access
Question # 51

Which of the following best describes the function of the requirements baseline?

A.

Controls the product development and evolution.

B.

Provides the basis for the development scope.

C.

Tracks the progress of requirements documentation.

D.

Defines how the project will be scheduled.

Full Access
Question # 52

A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

A.

Questionnaires

B.

Group decision making

C.

Stakeholder analysis

D.

Prototyping

Full Access
Question # 53

A document is being created that will detail the customer's needs for a product and will include a functional model, a data model, and a glossary of terms. This document is called a:

A.

standard operating manual.

B.

business case.

C.

project charter.

D.

requirements specification.

Full Access
Question # 54

When eliciting requirements, a good time to consider using the interviewing method is when:

A.

attempting to obtain sign-off on requirements from stakeholders.

B.

there is not enough time to gather requirements from many different sources.

C.

there are communication challenges among stakeholders.

D.

assembling a requirements traceability matrix.

Full Access
Question # 55

A business analyst is working on a project to implement a new call management system for a help desk. They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.

Which technique should the business analyst use to investigate the problem?

A.

Interviews

B.

Root cause analysis

C.

Observation

D.

Process modeling

Full Access
Question # 56

How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?

A.

Create prototype proof-of-concept models.

B.

Conduct requirement walkthrough sessions.

C.

Review performance data with the project sponsor.

D.

Talk to distinct testing groups to check testing status.

Full Access
Question # 57

The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?

A.

Create a requirements traceability matrix for review and approval by the customer.

B.

Create a requirements baseline approval form for the customer to review and approve.

C.

Request that the customer create a baseline of the requirements in the contract specification.

D.

Perform a variance analysis on the design specification and report the results to the customer.

Full Access
Question # 58

One of the main purposes for creating a requirements traceability matrix is to:

A.

track how requirements can be connected to the solution.

B.

provide test cases to validate solution deliverables.

C.

document stakeholder approval of project requirements.

D.

track the project solution scope.

Full Access
Question # 59

A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.

How would the business analyst define the scope of this project?

A.

Perform a work breakdown structure.

B.

Perform a feasibility study.

C.

Perform process modelling.

D.

Perform a structured walkthrough.

Full Access
Question # 60

Which technique or tool is used to obtain acceptance of the delivered product?

A.

Expert judgment

B.

Facilitated workshops

C.

Inspection

D.

Contextual inquiry

Full Access