SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?
Determine the correct formula and date for the late finish for Activity 9004.
The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.
If all other work proceeds according to the Baseline plan, how many times will the critical path change?
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?
Which of the following is NOT a tool or technique used to perform scope planning?
Project schedules help control all of the following EXCEPT for_____________________.
Which of the following will always describe the critical path? The path with
Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?
Using the normal schedule, what is the early finish date and total float of Activity 10002?
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?
The addition of which of the following relationships would cause a logic loop?
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?
Which is NOT an industry-recognized methodology for quantifying critical delay?
Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?
The amount of time that an activity can be delayed from its early start date without delaying project completion is called:
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
Which of the following is NOT required when performing weekly or monthly schedule updates?