Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
What product is used to maintain a record of those who have an interest in the project and their information requirements?
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.
Identify the missing word in the following sentence relating to one of the principles:
A PRINCE2 project should have [?] defined for each project objective.
Which process provides information for the project board to review an updated project plan?
According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?
Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.
When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.
Which statement about applying the 'tailor to suit the project' principle is CORRECT?
Which are reasons for a benefits management approach?
1. To state how improvements will be measured
2. To confirm that the benefits are realized
3. To estimate the costs of improvement
4. To define the reason for delivering the improvement
Which statement describes the context of the 'initiating a project" process?
Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?
How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?
Which term is defined-as the amount and type or risk that the business is willing to take in pursuit of is objectives?
In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?
Which statement about the length of management stages in a project is CORRECT?
Which process is used by the project board to respond to on exception report?
According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?
The project board Wants to consider whether td continue to operate in the same way, of Whether to change operations by means. of a project.
In which step of ‘business case management technique should this be considered?
Which report must be used to inform the project board of a predicted deviation from agreed stage limits?
Who should act as the communication channel between a project and corporate or programme management?
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
Which is one of the six aspects of project performance that needs to be managed?
What process aims to ensure accurate progress information is provided to the Project Manager?
Which product documents the information needed to demonstrate continued business justification?
Which of the following statements about quality assurance and Project Assurance is true?
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual
products being worked on.
Which part of effective issue management is the project manager applying?
Identify the missing word in the following sentence:
[ ?] is a prediction made by studying historical data and past patterns.
The project manager needs to monitor the progress of the stage.
Which combination of management products should the project manager review?
According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
Which statement about capability and competency within a project is CORRECT?
As part of the ‘closing a project’ process, the project manager needs to assess whether the outcomes are likely to deliver the expected performance improvements post-project.
In which step of 'business case management' technique should the project manager assess this?
Identify the missing ward in the following sentence.
PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.
The senior user needs to understand how user assurance will support the senior user on the project.
Which management product should the senior user review?
Which term is defined as the means by which an organization transitions to a desired future state?
Which member of the project management team should secure funding for the project before the project stars?
The project board is reviewing the project initiation documentation (PID) to decide whether the project should continue or close. What should the project board ensure the PID is aligned with?
Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?
Which is a description of a purpose of the communication management approach?
Which action should the project manager take when reviewing progress to assess the 'health' of a stage?
What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?
The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.
Which element of effective business case management is the senior user applying?
Which should define how tools will be used to support the information needs of the project team?
The project manager reviews the project product description to identify the detailed requirement for each product.
In which step of the quality management technique should the project manager do this review?
Which term is defined as a product that will not meet is quality specifications?
Which action contributes to achieving the ‘ensure continued business justification’ principle?
Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?
The project manager needs to document how risk management will be undertaken during the project.
In which step of the 'risk management’ technique should the project manager document this?
Which TWO are objectives of the closing a project: process?
1. To ensure the benefit reviews enable the project benefits to the confirmed
2. To update the business case so that the project hoard can decide whether to continue with the project
3. To ensure that the project team deliver the products to quality expectations
4. To hand over any open threats to operations
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project
If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?
Which is a step in the recommended approach to 'defining and analyzing the products'?
According to PRINCE2, which characteristic is necessary for an effective project board?
Which are advantages of a clear end to a project?
1. No further costs will be incurred by the project
2. Project products will be transferred to operations and support
3. All benefits will have been achieved
4. The project brief will be re-baselined
Which document should record the agreed amount of risk budget for a project?
What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products
What is described as an organization's unique attitude towards risk taking
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
To meet the minimum requirements for applying the progress theme, what must be considered?
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
What must be produced to meet the minimum requirements for applying the change theme?
Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.
Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
As a minimum requirement for applying the risk theme, what must specifically be assessed?
How does the use of product descriptions support the 'focus on products' principle?
The application of which principle helps to define what should be included in a project?
How does PRINCE2 ensure that the specific management needs of an organization are met?
Identify the missing words in the following sentence.
The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.
The project manager reviews whether there has been a Change in the way team members relate to each other.
Which principle is the project manager applying as part of the 'people' element?
What is the result of the change derived from using the project’s product?
Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:
Which role should be accountable for approving these proposals?
What does the communication management approach define?
1. How versions of products will be described on information sent to interested parties
2. How information should be sent to interested parties
3. How often information should be sent to interested parties
4. How the PRINCE2 roles will be combined during the project
The project board needs to confirm that there is enough information to initiate the project.
What should the project board review?
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?