Weekend Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > PRINCE2 > PRINCE2 Agile > PRINCE2-Agile-Foundation

PRINCE2-Agile-Foundation PRINCE2 Agile Foundation (Version 2) Exam Question and Answers

Question # 4

For which process is the agreement on the requirements for delivery of specialist products necessary?

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Full Access
Question # 5

Which statement describes the focus of “being Agile” and not “doing Agile”?

A.

Task completion within strict timelines

B.

Adaptability and collaboration

C.

Document-driven processes

D.

Agile techniques for efficiency

Full Access
Question # 6

In which process should the requirements for delivery of specialist products be agreed?

A.

Initiating a project

B.

Managing product delivery

C.

Starting up a project

D.

Managing a stage boundary

Full Access
Question # 7

Which of the following is a prioritized list of the requirements for a product?

A.

Project canvas

B.

Release map

C.

Project log

D.

Backlog

Full Access
Question # 8

How is the ‘tailor to suit the project’ principle applied in an agile context?

A.

By flexing what is produced to stay in control and deliver value

B.

By emphasizing tolerances on what is being delivered

C.

By using the Agilometer to assess the project environment

D.

By fitting releases into planned management stages

Full Access
Question # 9

What is typically displayed on a board to show progress to people working on a project?

A.

Agilometer assessment

B.

Product backlog

C.

Information radiator

D.

User story

Full Access
Question # 10

Why are team working agreement produced?

A.

To create structure so that the team manager can assess individual performance

B.

To evolve the effectiveness and behaviors of the self-organizing team by agreeing values

C.

To make the team rules visible to the project manager for monitoring purposes

D.

To ensure that the delivery team members comply with company policy

Full Access
Question # 11

What role does AI play in addressing project complexity within PRINCE2 Agile?

A.

It helps reduce all sources of project complexity

B.

It adds layers of complexity through excessive automation

C.

It helps reduce uncertainty and ambiguity associated with change initiatives

D.

It ensures stakeholder involvement in all decision-making

Full Access
Question # 12

Which of the following integrated elements defines who is working on the project and who is affected by the project?

A.

The project context

B.

The PRINCE2 practices

C.

The PRINCE2 processes

D.

The “people” element

Full Access
Question # 13

Which two statements are key responsibilities of supplier representative?

1. They highlight areas that the project may impact from a technical perspective.

2. They are partially assigned to the delivery team.

3. They create the project's specialist products.

4. They prioritize requirements.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 14

Which of the following is a common challenge when merging project management and Agile?

A.

Lack of clear processes

B.

The use of different terminology

C.

Lack of guidance at project level

D.

The use of a flexible framework

Full Access
Question # 15

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 16

Which statement about the ‘protect the level of quality’ target is CORRECT?

A.

It is achieved by allowing enough time for testing

B.

It is achieved by using the same team members

C.

It gives confidence on the progress of the project

D.

It delivers the early realization of benefits

Full Access
Question # 17

Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?

1) It should be replaced by the project manager attending a daily stand-up.

2) It should be displayed in the form of an information radiator in a team room.

3) It should be produced when the amount to be delivered will result in tolerance being exceeded.

4) It should be produced in a product backlog in the form of prioritized user stories.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 18

How is the “closing a project” process used?

A.

By controlling the link between the project manager and the delivery team

B.

By ensuring that the project is viable

C.

By accepting the project product

D.

By ensuring the focus remains on delivering the stage’s products

Full Access
Question # 19

Which statement about the ‘initiating a project’ process is CORRECT?

A.

The initiation stage plan should form part of the project plan

B.

The impact of frequent releases on quality management should be assessed

C.

The process should take more time than usual for disruptive projects

D.

The project solution should be documented in detail in the project product description

Full Access
Question # 20

What term is used to describe boards that display what work needs to be completed for people working on a project?

A.

Work in progress limit

B.

Information radiator

C.

Highlight report

D.

Glad! Sad! Mad!

Full Access
Question # 21

Which is an advantage of using the PRINCE2 Agile behavior ‘collaboration’?

A.

It ensures that there are no surprises

B.

It allows people to provide cover for one another

C.

It uses experimentation to expand requirements

D.

It uses learning to help improve products

Full Access
Question # 22

What is essential to secure leadership buy-in for scaling up agile?

A.

Speaking the language of leadership

B.

Ensuring that all decisions are made by leadership

C.

Ensuring emphasis on doing agile

D.

Empowering teams to self-manage

Full Access
Question # 23

Which of the following levels of psychological safety encourages sharing ideas and skills openly?

A.

Challenger safety

B.

Contributor safety

C.

Inclusion safety

D.

Learner safety

Full Access
Question # 24

What does velocity typically measure?

A.

Work packages completed by the team

B.

The rate of progress the team is making

C.

The number of timeboxes completed

D.

The speed that a minimum viable product is created

Full Access
Question # 25

Which well-known agile method uses visualization, and controls work in progress?

A.

Scrum

B.

Lean Startup

C.

Lean

D.

Kanban

Full Access
Question # 26

How does the change theme regard change in PRINCE2 Agile?

A.

As disruptive

B.

As something to be avoided

C.

As a necessity

D.

As inevitable

Full Access
Question # 27

What is a responsibility of the team coach?

A.

To liaise with the agile coach

B.

To liaise with the project manager

C.

To liaise with the chief product owner

D.

To liaise with project assurance

Full Access
Question # 28

Which workshop is used to assess the project’s status and address any challenges?

A.

Team planning workshop

B.

Project retrospective workshop

C.

Team retrospective workshop

D.

Progress review workshop

Full Access
Question # 29

Which artifact is used to describe the project's major products in the form of epic user stories?

A.

Project dashboard

B.

Release map

C.

Product backlog

D.

Project backlog

Full Access
Question # 30

What should the business case state about the minimum viable product (MVP)?

A.

When the MVP will be defined

B.

That the MVP must go into operational use

C.

What the MVP is

D.

That the MVP is the same as project viability

Full Access
Question # 31

Which statement defines a PRINCE2 principle?

A.

A PRINCE2 project defines its quality management approach

B.

A PRINCE2 project is monitored and controlled on a stage-by-stage basis

C.

A PRINCE2 project ensures a consistent approach to risk management

D.

A PRINCE2 project is tailored to suit the competitor’s environment

Full Access
Question # 32

Which is a reason for releasing a product into a staging area?

A.

It enables the faster delivery of changes

B.

It supports regulatory compliance checking

C.

It enables a phased Waterfall approach

D.

It supports management by exception

Full Access
Question # 33

Whose interests are specifically represented by the senior supplier?

1. Those ensuring the project is value for money.

2. Those who will use the project’s products.

3. Those who will be developing the project’s products.

4. Those responsible for the project’s technical integrity.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 34

Which statement explains the target ‘be on time and hit deadlines’ for flexible delivery?

A.

It reduces testing in order to meet deadlines

B.

It sets the project baseline at the correct level

C.

It enables team dynamics to remain the same

D.

It improves the supplier's reputation with the customer

Full Access
Question # 35

Which TWO statements about the supplier subject matter expert are CORRECT?

1) They provide a wider picture of the customer view.

2) They prioritize requirements at the detailed level.

3) They should be focused on the customer.

4) They ensure that the work is compliant with project standards.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 36

Which of the following is used to support the “progress” practice?

A.

Agilometer

B.

Burn charts

C.

Trading/swapping

D.

Team skills matrix

Full Access
Question # 37

Which of the following defines agility?

A.

The set of activities that define the sequence of actions

B.

The ability to embrace and respond to change

C.

The ability to protect from uncontrolled changes

D.

The core belief that anyone is capable of learning

Full Access
Question # 38

Which statement BEST describes the PRINCE2 Agile guidance for change?

A.

The delivery team should be authorized to make changes at the detailed level

B.

The delivery team should quickly approve changes to the project baseline

C.

The executive should manage changes dynamically at the detailed level

D.

The executive should approve delivery level changes to harness the benefits of positive change

Full Access
Question # 39

Which practice has the purpose of defining the products to be delivered, and who will deliver them?

A.

Plans

B.

Business case

C.

Organization

D.

Risk

Full Access
Question # 40

Which statement about the ‘be on time and hit deadlines’ target is CORRECT?

A.

It allows change to be handled dynamically

B.

It is achieved by keeping the delivery teams stable

C.

It helps with planning dependencies within a project

D.

It ensures that the level of quality is protected

Full Access
Question # 41

During which process should release planning be done for the FIRST time?

A.

Initiating a project

B.

Managing a stage boundary

C.

Managing product delivery

D.

Controlling a stage

Full Access
Question # 42

Which workshop extracts actionable insights for future iterations?

A.

Progress review workshop

B.

Project initiation workshop

C.

Project retrospective workshop

D.

Team planning workshop

Full Access
Question # 43

In which area is Agile strongest when blending with PRINCE2?

A.

Product delivery

B.

Project management

C.

Project direction

D.

Product management

Full Access
Question # 44

Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

A.

To use empiricism, based on knowledge that comes from experience

B.

To build, measure, learn from your experiences

C.

To create a minimum viable product to manage uncertainty

D.

To fail fast, if you are going to fail

Full Access
Question # 45

Which is a purpose of the ‘managing product delivery’ process?

A.

To plan the delivery of the products before committing to significant expenditure

B.

To agree on what is required for accepting, executing and delivering project work.

C.

To establish and deliver the project communications to the wider organization

D.

To delegate day-to-day management of the project to the project manager

Full Access
Question # 46

Which is a collaborative technique for defining decision-making within teams?

A.

Delegation poker

B.

Team skills matrix

C.

Personas

D.

Magic estimation

Full Access
Question # 47

Which statement explains the PRINCE2 Agile behavior of ‘exploration’?

A.

It empowers the project management team at the delivery level

B.

It uses the most effective channel to communicate information

C.

It displays the progress rate to everyone using burn-down charts

D.

It seeks out feedback collaboratively from project stakeholders

Full Access
Question # 48

What challenge does PRINCE2 Agile address in Agile adoption?

A.

Agile frameworks are too rigid for product delivery

B.

Agile frameworks struggle to scale for large, complex initiatives

C.

Agile frameworks struggle with role definitions

D.

Agile frameworks cannot be combined with other methods

Full Access