11.11 Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > PMI > Project-Management-Professional > PMP

PMP Project Management Professional (2025 Version) Question and Answers

Question # 4

A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that

some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)

A.

Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.

B.

Escalate the issue to the functional manager and ask for support.

C.

Involve all stakeholders in the project by distributing status reports.

D.

Focus on the supportive stakeholders and minimize involvement of unsupportive stakeholders.

E.

Engage all stakeholders in the project including the unsupportive stakeholders.

Full Access
Question # 5

A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.

What should the project manager do first?

A.

Formalize the product owner assignment.

B.

Review similar projects in the company.

C.

Set the project's purpose, mission, and vision.

D.

Carry out the product backlog creation.

Full Access
Question # 6

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

A.

Adopt the same timeframe as the closed project for the current project.

B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.

Create a draft schedule based on the activity list and the historical data from the closed project.

D.

Evaluate each activity duration and build a new project schedule.

Full Access
Question # 7

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

A.

Prioritize other items for the team and deal with the conflicting requirements later.

B.

Allow the project team to decide what is the most appropriate requirement to follow.

C.

Escalate to the project management office (PMO) and request a solution for the requirements.

D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

Full Access
Question # 8

An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile

practices, which are relevant to the project.

What should the project manager do in order to gain buy-in from the different stakeholders?

A.

Organize a meeting with relevant stakeholders explaining the benefits of agile and the practices relevant for the project.

B.

Send the project management plan, which includes the suggested agile practices, to the stakeholders.

C.

Ask the project management office (PMO) to get buy-in from the stakeholders, because agile is an approach that differs from their previousways of working.

D.

Organize a meeting with a consultant to provide training to the stakeholders on agile practices.

Full Access
Question # 9

During the execution phase of a project, a project manager notices that the project team is not motivated and performance is decreasing. The decision is made to invest in financial rewards for all of the Key team members. After the rewards are distributed, the team is still underperforming.

What should the project manager have done to avoid this situation?

A.

Determined the appropriate type of incentive for key team members

B.

Conducted frequent monitoring on key team members’ performance during project execution

C.

Distributed the monetary incentive according to the team members’ individual performance

D.

identified the underperforming team members and asked the human resources (HR) department to replace them

Full Access
Question # 10

A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment

What should the project manager do?

A.

invite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team

B.

invite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment

C.

invite the product owner and the team to a discussion about the concept and expected performance of the equipment

D.

invite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting

Full Access
Question # 11

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience

performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

A.

Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work,

B.

Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product

C.

Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.

D.

Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.

Full Access
Question # 12

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

A.

Finish to start

B.

Start to start

C.

Start to finish

Full Access
Question # 13

A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.

What should the project manager do?

A.

Plan a training session for the new team members not familiar with the system.

B.

Communicate the rules and criteria to the team members through email.

C.

Work only with the team members familiar with the system

D.

Document which rules and criteria the new team members are not familiar wit

Full Access
Question # 14

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

A.

Add the new requirements to the project scope immediately since they are mandatory changes.

B.

Review the new requirements with the compliance department to determine if a change request is needed.

C.

Ignore the new requirements as the current budget and schedule do not allow for any changes.

D.

Proceed with the defined project requirements and delay implementing the new requirements.

Full Access
Question # 15

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

What should the project manager do next?

A.

Incorporate the changes in the last sprint before the first release.

B.

Call for an internal meeting to discuss the changes and their value.

C.

Ask the product owner to prioritize the backlog with the project team.

D.

Request the scrum team to prioritize the product backlog.

Full Access
Question # 16

When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a

result, the team ground rules favor these two team members.

What should the project manager have done to avoid this situation?

A.

Come to the meeting with suggested ground rules

B.

Ask all team members to send new ideas prior to the meeting

C.

Extend the meeting to allow everyone to speak

D.

Set expectations for contributions ahead of the meeting

Full Access
Question # 17

A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.

What should the project manager do to ensure value is delivered quickly?

A.

Plan the project to deliver value incrementally with regular releases.

B.

Request a budget increase to pay the subject matter experts (SMEs) more overtime

C.

Identify tasks that can run in parallel to deliver the project faster.

D.

Ask the project sponsor to provide additional resources to fast track the project.

Full Access
Question # 18

A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with

incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

A.

Forward the client's request to management as a change request to get formal approval.

B.

Document the information in the meeting minutes and share it with the project stakeholders.

C.

Draft a contract change with the desired scope changes and send it to the client for approval.

D.

Finish the current monthly release as it was planned and replan for the future months.

Full Access
Question # 19

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

A.

Validate if the project charter changed from the original one.

B.

Meet with these stakeholders to review the project charter.

C.

Check if these stakeholders attend regular project meetings.

D.

Review the project charter to validate this claim.

Full Access
Question # 20

A team member has very strong technical skills and is interested in a leadership role. A leadership position opens up outside of the team in the organization. The project manager has observed that the team member has a major gap in communicating in a professional manner.

What should the project manager do?

A.

Suggest the team member focus on positions with technical aspects and possible technical career opportunities.

B.

Recommend the team member for effective communication training and support their career development interests.

C.

Encourage the team member to stay in their current role as they are important to the project.

D.

Ask the team member to refrain from pursuing new opportunities as they are not a suitable fit for a leadership position.

Full Access
Question # 21

A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.

What should the project manager do?

A.

Use an agile approach and engage a vendor that delivered well in a previous organization.

B.

Consult the product owner and engage a vendor that is recommended by them.

C.

Consult the development team and engage a vendor that is recommended by them.

D.

Use a formal approach using procurement policies, procedures, forms, and work instructions.

Full Access
Question # 22

A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.

What should the project manager do in this situation as a servant leader?

A.

Request an exception to allow the team to return to work on-site

B.

Allow the team to address the problem as a self-organized team

C.

Coach team members to increase their engagement and collaboration

D.

Force the team to attend the daily standups to gather the project status

Full Access
Question # 23

A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist

from the team was average.

What should the project manager do to help the new compliance specialist improve?

A.

Escalate this situation to the manager of the area for a possible solution.

B.

Provide time for the specialist to adjust to the pace of the project.

C.

Coordinate a one-to-one meeting with the specialist to assess the situation.

D.

Contact the human resources (HR) manager about the team's feedback.

Full Access
Question # 24

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

A.

Ask the team to collect the knowledge locally and share it at the end of the project.

B.

Utilize the cloud wiki to collect the necessary knowledge.

C.

Coordinate with the team and the project stakeholders to collect the knowledge.

D.

Provide just-in-time knowledge to the client, upon request.

Full Access
Question # 25

A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.

What should the project manager do?

A.

Send out daily emails with the project status and task lists to all team members.

B.

Meet daily with the project team and include a monthly report on the risks and issues.

C.

Distribute a project newsletter that includes any project changes and required project information.

D.

Encourage collaboration on a daily basis, facilitating different communication channels.

Full Access
Question # 26

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

A.

Fast track this dependency to avoid delaying the project.

B.

Perform Integrated Change Control.

C.

Include the dependency in the project schedule.

D.

Ask IT to prioritize the needed system to meet the schedule.

Full Access
Question # 27

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

A.

Require the team to have daily mandatory meetings with the project management office (PMO).

B.

Recommend the use of formal written documentation in all project communications.

C.

Review the communications strategy with the team regularly with a view for continuous improvement.

D.

Send out a survey to review the preferred method, time frequency for communications.

E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

Full Access
Question # 28

A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead's decisions. The team lead asks the project manager for help.

What should the project manager do?

A.

Suggest to the team lead how to deal with this team member and discuss the situation with the engineer.

B.

Organize a meeting with all of the project stakeholders and inform them about the new risk and its impact on the project.

C.

Organize a meeting with the project team and discuss the situation and its impact on project delivery.

D.

Suggest to the engineer how to work efficiently with the lead and discuss the situation with the lead's functional manager.

Full Access
Question # 29

After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?

A.

Ask management to replace the new sponsor with the previous sponsor.

B.

Request the previous sponsor to discuss changes with the project team.

C.

Explore ways to share the project vision and outcome with the new sponsor.

D.

Find ways to bypass the new sponsor and reach management for support.

Full Access
Question # 30

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.

What should the project manager do?

A.

Ask the project management office (PMO) to support and review all deliverables.

B.

Log the issue in the risk register and the issue log.

C.

Assign a technical writer to the project.

D.

Develop a standard for document quality control.

Full Access
Question # 31

A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.

What should be me project manager's response?

A.

Sprint plan and product roadmap

B.

Product roadmap and sprint backlog

C.

Product backlog and scrum board

D.

Sprint backlog and scrum board

Full Access
Question # 32

A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.

What should the project manager do first to verify alignment?

A.

Ask the project team to delay the kick-off while resolving the concern.

B.

Request a copy of the project assumptions log for more insight.

C.

Meet with the project sponsor to obtain more information.

D.

Consult with the project team members to gain their opinions.

Full Access
Question # 33

The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?

A.

Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.

B.

Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.

C.

Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.

D.

Ask the sponsor to start a new project to support the existing project and help it meet the original time line.

Full Access
Question # 34

A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team

members who are confused about the next steps and the final outcome of the project.

What should the new project manager do?

A.

Avoid conflict and let the team self-organize on how they want to work on the project tasks.

B.

Ask the project sponsor to provide team members with a project direction regarding outcomes.

C.

Set short-term goals in order to create a winning culture internally and praise team members for achieving them.

D.

Escalate the situation to the steering committee and request that more time be allotted to the project.

Full Access
Question # 35

A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?

A.

Ask another team member to redo the proof of concept using the current technology to ensure It is truly not an option.

B.

Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.

C.

Add this item to the issue log and explore possible resolution options with the team.

D.

Update the risk register indicating that a new technology must be chosen by the team lead.

Full Access
Question # 36

Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the

company’s competitive advantage. What should the project manager do?

A.

Reject all requested changes and bypass the company's change control process.

B.

Encourage the project team to add premium features to impress the client.

C.

Start the process to include the new features of the product on the next iteration.

D.

Allow all requested changes and bypass the company's change control process.

Full Access
Question # 37

One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.

What should the project manager do?

A.

Coordinate design document preparation

B.

Perform a qualitative risk analysis

C.

Request further clarification of the requirement

D.

Manage the engagement of this stakeholder.

Full Access
Question # 38

A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager

has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management

competencies. The project manager explains that the exiting team members were lazy.

What should the project manager do to prevent this high turnover rate from continuing?

A.

Be more involved in the team member recruitment process to ensure qualified team members are chosen.

B.

Develop relationship skills as a leader and also develop the teams’ emotional intelligence skills.

C.

Avoid micromanaging the team, enforce stricter rules, and monitor employees.

D.

Explain to the recruiting manager that a project is temporary in nature, making it different than an operational environment.

Full Access
Question # 39

A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.

What should the project manager do In this scenario?

A.

Add temporary members with the specialized skill set to the team to accomplish the work with a high level of confidence.

B.

Assess the impact of a possible delay to the project and encourage the team to take the work if the impact is tolerable.

C.

Accept the work and outsource it to another team that has the specialized skill set; then integrate the solution,

D.

Reject the work from this team's backlog and ask the product owner to add It to another team's backlog.

Full Access
Question # 40

A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.

Full Access
Question # 41

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.

What should the project manager have done to prevent this situation?

A.

Performed a stakeholder analysis when the sponsor joined the project

B.

Held a governance meeting to review the project increment

C.

Conducted a product iteration review with the new project sponsor

D.

Escalated the issue to ensure the increment would be approved

Full Access
Question # 42

A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly

requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes

of a request. Both of them are equal in seniority and both report to the same functional manager.

How should the project manager proceed?

A.

Update the communications management plan and the stakeholder engagement plan.

B.

Escalate the issue to the functional manager and explain the situation to them.

C.

Negotiate a mutually agreeable feedback cycle with acceptable timelines.

D.

Refer the lead project manager to the communications management plan.

Full Access
Question # 43

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional

managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

A.

Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software.

B.

Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained.

C.

Request a meeting with the sponsor to change the scope to allow the development team to conduct testing.

D.

Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software.

Full Access
Question # 44

A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.

Full Access
Question # 45

A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master's program will coincide with the last phase of the project.

What should the project manager do?

A.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

B.

Suggest the team member postpone their enrollment in the master's program until the project is completed.

C.

Ask the team member to inform human resources (HR) about their enrollment in the master's program.

D.

Assess the team member's commitment to the master's program and its impact on project performance.

Full Access
Question # 46

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the

quality standards required by regulations.

What should the project manager have done to avoid this?

A.

Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog

B.

Ensured that the project sponsor understood the scope of the project to avoid any future complaints

C.

Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration

D.

Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks

Full Access
Question # 47

An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.

Who should the project manager contact to help the team accelerate the delivery?

A.

The human resources (HR) department—to ask for more resources to add to the project team.

B.

The product owner and the stakeholders—to prioritize the requirements in the product backlog.

C.

The team—to have them increase their velocity to accomplish the stakeholders requirements.

D.

The stakeholders—to have them prioritize the requirements in the product backlog.

Full Access
Question # 48

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

A.

Risk register information

B.

Higher-level activities completed

C.

Milestones status report

D.

Resource breakdown structure (RBS)

Full Access
Question # 49

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

A.

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

B.

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.

C.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.

D.

Create a record in the issue register and escalate the issue to the project steering committee.

Full Access
Question # 50

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control

B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.

C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.

D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.

Full Access
Question # 51

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.

Propose an approach based on value measurement, such as the use of objectives and key results.

C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

Full Access
Question # 52

A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.

What strategy should the project manager use?

A.

Focus on the implementation of a software as a service (SaaS) solution for the customer.

B.

Specify the scope and features to be deployed in the contract clearly.

C.

Work very closely with the customer and third parties to meet their needs.

D.

Change the marketing and product management definitions to meet stakeholder needs.

Full Access
Question # 53

At a meeting, the project manager for an agile project indicates that the sprint goals were not met. The product owner leaves the meeting early. and the team discusses how the meeting went. Team members are confused as there were no defects for the new user stories and no new requirements were discussed.

What should the project manager do in the future to avoid this situation?

A.

Create better plans to test the functionality in more detail.

B.

Review the definition of done (DoD) with the product owner.

C.

Include previous sprint defects and close them in the actual sprint.

D.

Get approval from the product owner on the user stories.

Full Access
Question # 54

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to

ensure the community members are up to date on project progress?

A.

Share project updates when requested by the stakeholders.

B.

Share project updates through regular community meetings.

C.

Share the annual reports virtually and in the local newspapers.

D.

Share the project reports with the sponsor to inform community members.

Full Access
Question # 55

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?

A.

Use a burndown chart to provide transparency.

B.

Use a kanban board to increase accountability.

C.

Use a product backlog to manage changes.

D.

Use a burnup chart to provide transparency.

Full Access
Question # 56

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member's concern?

A.

Ask the team member to resolve the issue independently to minimize further delays.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Implement fast tracking to reduce the impact of the delay on the sprint.

D.

Update the communications management plan to prevent future reoccurrence.

Full Access
Question # 57

At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?

A.

Defer all actions until the next workshop to keep the team focused on other higher priorities

B.

Follow up on each item as soon as possible to ensure timely completion and report the status to management.

C.

Review the critical path and update the project schedule with the newly identified tasks.

D.

Prioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress.

Full Access
Question # 58

A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk

materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two)

A.

Ask the team member to work overtime to make up the time lost so that the project schedule is not impacted.

B.

Analyze the impact of the issue and submit a change request to update the project schedule.

C.

Inform the project sponsor that the risk has materialized and request that the project budget be increased.

D.

Extend the project deadline and update the project schedule to reflect the delay.

E.

Log it in the risk register and work with the relevant owner to implement the mitigation action plan.

Full Access
Question # 59

A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures

What should the project manager do?

A.

Follow the Perform integrated Change Control process and submit a change request

B.

Ask the team members to draft a justification before processing the reimbursements

C.

Update the project management plan with the incurred costs

D.

Review the budget and allocate funds for the reimbursements

Full Access
Question # 60

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

A.

Meet with the project team to develop a proper resolution to the issue.

B.

Update the project artifacts to reflect the new deadlines reported.

C.

Request approval from the project sponsor to add more resources,

D.

Prepare documentation to explain the issue and communicate accordingly.

Full Access
Question # 61

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

Full Access
Question # 62

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because

of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?

A.

Escalate the issue to the project sponsor.

B.

Address the issue during the next sprint planning meeting.

C.

Initiate a change request to extend the project end date.

D.

Extend the dates for future project milestones.

Full Access
Question # 63

A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.

What immediate corrective action should the project manager take?

A.

Discuss the issue with the virtual team members and revise the communications management plan.

B.

Escalate this issue to the virtual team members' supervisors.

C.

Add this issue to the risk management plan and take action if it persists.

D.

Discuss the issue with the project sponsors and add this as an issue in the issue log.

Full Access
Question # 64

In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market

while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.

What should the project manager do to avoid a reoccurrence of this scenario?

A.

Ensure the content of the project report is clearly understood and request any necessary feedback.

B.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.

C.

Send a detailed report to each steering committee member ahead of the meeting.

D.

Ensure that all product features are completed as per the communicated specifications before releasing to market.

Full Access
Question # 65

A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one

member reported an impediment that requires collaboration from an expert who is assigned to another project.

What should the project manager do first in this situation?

A.

Review the project's key performance indicators (KPIs) to determine the impact of this assignment.

B.

Check the expert's availability within the organization on an as-needed basis.

C.

Develop the team member's capacities through mentoring and training.

D.

Ask the project sponsor to assign a new resource with the necessary expertise to the team.

Full Access
Question # 66

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?

A.

Review the adaptive tools' impact and obtain agreement from the functional manager.

B.

Follow the functional manager's recommendation to implement only predictive tools in the project.

C.

Make the decision on which project approach to use that would best fit the project.

D.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

Full Access
Question # 67

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?

A.

Use the team's connections with international colleagues to get early warnings on future changes.

B.

Keep the focus on the priority items while the change goes through the change control process.

C.

Reject the change request since it may negatively impact the project's performance.

D.

Implement the change request as soon as possible to avoid accumulating new scope.

Full Access
Question # 68

A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The

project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.

What should the project manager do?

A.

Ask the experienced members to lead the junior members to facilitate skill transfer.

B.

Encourage team members to focus on delivering results with their specialized skills.

C.

Organize networking sessions to allow the team members to get to know one another.

D.

Ask the team to self-organize and escalate any issues to the project manager.

Full Access
Question # 69

A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.

What should the project manager do?

A.

Escalate the team member's disruptive behavior to their functional manager.

B.

Collaborate with the team to arrive at team ground rules and publish the rules to the team.

C.

Observe to ensure this typical forming stage behavior does not escalate beyond what is acceptable.

D.

Request team members document their decisions independently and share with each other.

Full Access
Question # 70

An experienced project team member always points out the issues of other team members during meetings. The other team members feel that

the experienced team member is deflecting their own issues in meetings.

What should the project manager do?

A.

Arrange separated group meetings to allow everyone to express their opinions.

B.

Review the communications management plan with the team and enforce its implementation.

C.

Prepare an agenda for all future team meetings and facilitate the discussion.

D.

Speak with the experienced team member to discuss the issues in a supportive way.

Full Access
Question # 71

A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically

last 45 minutes with many misunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?

A.

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.

B.

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.

C.

Instruct the meeting participants to speak only about blockers during the meeting.

D.

Train the three team leads to conduct a local meeting, then run an overall status meeting.

Full Access
Question # 72

A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.

How should the project manager ensure the acceptance criteria are ret?

A.

Perform tests and routinely track results as per the quality management plan.

B.

Make sure the stakeholders are aware of the acceptance criteria.

C.

Negotiate to obtain approval if most of the tests have passed.

D.

Modify the acceptance criteria before the official delivery.

Full Access
Question # 73

A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.

How should the project manager approach this situation?

A.

Understand the customer's perspective and provide mentoring on agile mindsets.

B.

Call for an internal team retrospective and create an improvement action plan.

C.

Ask the customer to work with the product owner to prioritize all requests.

D.

Work with the team to receive customer directions and improve the process.

Full Access
Question # 74

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

A.

Hold an emergency project team meeting to discuss the situation.

B.

Ask the human resources (HR) manager for an external replacement.

C.

Log the situation in the issue log.

D.

Update the key stakeholders on the issue.

Full Access
Question # 75

A project manager who is experienced in predictive and adaptive approaches has been assigned to a new project. Most of the project

stakeholders have only worked on predictive projects, and only a few have been exposed to adaptive projects.

What should the project manager do?

A.

Propose a hybrid approach and determine which stakeholders will be engaged in each phase of the project.

B.

Follow a predictive approach to reduce the training effort, even though there are incremental deliveries in the project.

C.

Use an adaptive approach, engage the stakeholders who have been exposed to adaptive projects, and train those who have not.

D.

Understand the scope complexity and project magnitude prior to determining which approach to use.

Full Access
Question # 76

A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the

processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager

reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager

confirms that the team is following the processes exactly.

What should the project manager do?

A.

Update the schedule to account for the unexpected delays in the project tasks.

B.

Review the resources allocated to the project and change accordingly.

C.

Review and amend the processes to ensure only value-adding activities are present.

D.

Update the variation register to account for the extended project time.

Full Access
Question # 77

A project manager is working with several junior engineers on a project. The project manager noticed that when the junior engineers are asked questions, they defer te more senior team members on the team for answers. Having worked with the junior engineers on another project, the project manager knows they are capable of making these minor decisions correctly.

This uncertainty from the junior engineers is now slowing progress.

‘What should the project manager do?

A.

Update the risk register to reflect the possible impact of the projects slower progress,

B.

Ensure the junior engineers make decisions within a certain responsibility level and commit to it,

C.

Remove the junior engineers from any decision-making activity until further trained.

D.

Pair senior engineers to shadow the junior engineers and correct them throughout.

Full Access
Question # 78

A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?

A.

Convene an impact analysis meeting.

B.

Escalate the issue to the product owner.

C.

Consult the communications management plan.

D.

Review the stakeholder register.

Full Access
Question # 79

In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other's work. What would have

most likely caused this communication breakdown?

A.

The sprint review meetings were not held regularly.

B.

The daily standup meetings were not consistently attended.

C.

The project manager failed to develop a communications management plan.

D.

The weekly project status reports were not published regularly.

Full Access
Question # 80

During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager

react to ensure the project remains successful?

A.

Focus the discussion on recovery and ways to get back on track.

B.

Act in a way to highlight the criticality of the situation.

C.

Punish the team member for providing negative data that will affect the team's morale.

D.

Thank the team member for raising this issue, log it, and move on to the next topic.

Full Access
Question # 81

Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to

ensure the project is delivered successfully?

A.

Ask the vendor to communicate via the established channels.

B.

Invite the vendor to a meeting to discuss the concerns.

C.

Escalate the vendor's lack of responsiveness to the project sponsor.

D.

Proceed with other tasks while awaiting a response from the vendor.

Full Access
Question # 82

An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.

What should the project manager do to manage business concerns and expectations before starting the project?

A.

Meet with the project finance team to measure market variations and product impact.

B.

Direct the project team to estimate user stories in greater detail.

C.

Ask the product owner to prioritize the backlog items based on the return on investment (ROI).

D.

Request that the project team develop a release plan and roadmap for the project.

Full Access
Question # 83

A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget

What should the project manager do?

A.

Request to use the management reserve to keep the schedule

B.

Mitigate risks associated with the workaround to avoid project delays

C.

Proceed with the approved risk response plan.

D.

Discuss the options with the client as part of the change control process

Full Access
Question # 84

A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.

What should the project manager do to create a positive environment?

A.

Establish the team ground rules and share them with the team for strict adherence.

B.

Copy the ground rules established by another project and provide them to the teams.

C.

Extract the organization's policies and processes, customize them, and give them to the teams to adhere to.

D.

Help the teams in establishing and adhering to their ground rules and revisit after regular intervals.

Full Access
Question # 85

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

A.

Add developers to remove the backlog.

B.

Escalate the issue with the product owner.

C.

Reduce the testing scope of the backlog.

D.

Enroll team members in training on the tool.

Full Access
Question # 86

One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate

What interpersonal skill did the project manager use?

A.

Networking

B.

Emotional intelligence

C.

Conflict management

D.

Influencing

Full Access
Question # 87

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?

A.

Revisit the communications management plan and make necessary adjustments

B.

Revisit the scope management plan and note this as a risk

C.

Schedule a meeting with the product owner and finance team to agree on course corrections

D.

Continue developing based on the project management plan and address the issue post delivery

Full Access
Question # 88

A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel

How should the project manager handle this situation?

A.

Allocate and use part of the project's contingency reserves for training purposes.

B.

Negotiate a contract and form a partnership with a local authority for medical and security support services.

C.

Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training

D.

Hire only local resources who are aware of the terntory's hazards, providing employment to the local community

Full Access
Question # 89

Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings

What should the project manager do?

A.

Schedule a meeting for the project team to review the communications management plan.

B.

Tell the rest of the project team to continue discussions with the new team member

C.

Send an email to the project team outlining the communications strategy.

D.

Mentor the new team member on the methodology the project team is using

Full Access
Question # 90

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.

What should the new project manager do to address the process improvements?

A.

Understand the context and interdependencies of the process from the team members and then define improvements

B.

Continue with the process as is. and wait until the next phase to suggest any improvements

C.

Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework

D.

Define a ground rule to comply with the quality standard and ask the team members to apply it.

Full Access
Question # 91

An organization has historically executed most projects using a predictive approach The organization now wants to change over to an agile approach

Which strategy will be useful to effectively help prepare the organization for this change?

A.

Create a task force of executives who will monitor agile projects on a daily basis

B.

Add multiple layers of managers who will be accountable for the agile execution

C.

Improve organizational readiness by addressing impediments to agile in the organization.

D.

Take a big bang approach of moving the whole organization to agile at once

Full Access
Question # 92

A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.

What should the project manager do first?

A.

Develop the resource management plan and ensure adequate training

B.

Replace the current project team members

C.

Outsource the task to be completed by a specialized vendor.

D.

Update the issue log to account for the lack of team member qualifications

Full Access
Question # 93

A company just started managing a project using an agile approach Due to this change the general manager is worried about the scope definition process for upcoming projects

What should the project manager do to ensure the project scope is completely defined?

A.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk.

B.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

C.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

D.

Ask the general manager to review every requirement to ensure all projects will deliver the requested products

Full Access
Question # 94

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

A.

Increased bum rate

B.

Increased cost

C.

Increased technical debt

D.

Decreased efficiency

Full Access
Question # 95

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?

A.

Reduce the priority of project risks as all remaining risks are low-level

B.

Notify stakeholders that all high-level risks have been resolved

C.

Reevaluate identified risks and update the risk register

D.

Reclassify low-level risks as high-level risks

Full Access
Question # 96

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?

A.

The project charter and scope statement

B.

The requirements traceability matrix

C.

The business requirement documents (BRD)

D.

The WBS dictionary

Full Access
Question # 97

A project manager for a large multiyear industrial project has a project with diversified stakeholders from various geographical areas. Recently, the project manager encountered an issue with stakeholder engagement

Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two)

A.

Five whys

B.

Communications management plan

C.

Ishikawa diagrams

D.

Issue log

E.

Open-space meetings

Full Access
Question # 98

A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.

What should the project manager do?

A.

Proceed with the project without allowing scope creep to occur

B.

Use the contingency funds to provide support for the requested projects

C.

Cancel the project since the stakeholder's request is out of scope

D.

Inform the sponsor and document the request in the stakeholder engagement plan

Full Access
Question # 99

A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.

How should the project manager prepare for the next steps of the project?

A.

Escalate to the management team to increase the timeline based on the complexity of the project

B.

Wait for the other project estimates before planning the schedule

C.

Prioritize and estimate the milestones for the high-level requirements based on historical data

D.

Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan

Full Access
Question # 100

A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind schedule

What can the project manager do to move the team to the norming phase?

A.

Plan social activities to help foster stronger interpersonal relationships and identify shared goals.

B.

Speak with the project sponsor about changing the team composition

C.

Figure out who is behind the issues and apply progressive disciplinary techniques.

D.

Show the team the schedule impact of their communication issues and encourage them to put their differences aside

Full Access
Question # 101

The CEO has authorized the development of a complex financial product for a company to provide greater future benefits. The budget has been acquired through financing with global investors who expect all risks to be identified as soon as possible

What should the project manager use to identify the risks?

A.

An analysis of shared risks between parties

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Expert judgment

D.

A risk value assessment

Full Access
Question # 102

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs

B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team

C.

The project manager should allow the resources to periodically choose on which team they would like to work.

D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization

Full Access
Question # 103

The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project

How should the project manager alert the new project sponsor about these concerns?

A.

Send an email invitation to the project sponsor to attend all of the project team's weekly meetings, and hope the sponsor will find time to attend

B.

Send an email to the project sponsor summarizing the project status and key concerns, and request an immediate face-to-face meeting to discuss them

C.

Continue emailing updated project status reports highlighting the key risks andissues, and wait for the project sponsor to request a meeting

D.

Complete a risk analysis outlining the delays and impacts, and email a copy of the risk register, urging the project sponsor to respond

Full Access
Question # 104

A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule

What should the project manager do to keep the project on schedule while still meeting project objectives'?

A.

Collaborate with the change control board (CCB) to review the scope and submit any change requests

B.

Submit a change request to the CCB and update the schedule

C.

Update the scope and add more resources to the project

D.

Update the scope and move on to the next project milestone

Full Access
Question # 105

The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable

What personality indicators should the project manager consider when determining what communication style to use with this team member?

Full Access
Question # 106

Drag the organizational characteristics on the left to the correct scenario on the right

Full Access
Question # 107

A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?

A.

Sort conflicts into two groups: positive and negative

B.

Place conflicts into categories: structural and interpersonal.

C.

Place conflicts on a shared conflict list and ensure it is visible

D.

Review conflicts during daily Scrum so they are handled in a timely manner

Full Access
Question # 108

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches What does the project manager need to do first in order to have good project performance?

A.

Coach those team members lacking hybrid knowledge to learn on the job.

B.

Change the team to include hybrid experts

C.

Assess the required training per team member.

D.

Deliver hybrid training to all team members

Full Access
Question # 109

A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?

A.

Add the new stakeholder to the communications management plan

B.

Share the project status reports with the new stakeholder.

C.

Update the stakeholder engagement plan

D.

Schedule a meeting with the new stakeholder

Full Access
Question # 110

A few months into a project, several schedule issues have emerged Drag the schedule problems on the left to the specific tools on the right that if implemented during schedule development could have prevented the issues.

Full Access
Question # 111

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change

What should the scrum master do?

A.

Create a stakeholder engagement plan

B.

Design a communications management plan

C.

Update the team charter accordingly.

D.

Set up a meeting to discuss accommodations the team will have to make

Full Access
Question # 112

A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required

How should the project manager assist the product owner?

A.

Coach the product owner on how to create a product backlog

B.

Encourage the team to subdivide the project tasks

C.

Create a work breakdown structure (WBS) and explain the deliverables to the product owner

D.

Discuss the product owner's responsibilities within the project team

Full Access
Question # 113

During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?

A.

Include stakeholders during daily standup meetings to monitor progress.

B.

Validate acceptance criteria with stakeholders prior to backlog refinement

C.

Avoid including stakeholders in iteration reviews.

D.

Create a requirements traceability matrix and distribute it accordingly

Full Access
Question # 114

A transportation company is transforming its operational processes and the mam system this company uses to move freight The scope statement is in place An iterative delivery approach has been agreed by all stakeholders. What does the project manager need to do next to help the team understand the work that needs to be done?

A.

Work with the team to decompose the scope into a WBS and work packages in order to create required deliverables and timelines.

B.

Work directly with stakeholders on the work breakdown structure (WBS) and assign tasks with a required timeline for each team member to start the work.

C.

Create the requirements management plan to outline how project requirements will be collected analyzed and documented and then assign requirements to team members

D.

Start working on the project management plan with work packages, a detailed schedule, and work assignments for team members

Full Access
Question # 115

A food company is developing a new product using a predictive approach, and the product is currently in the testing phase Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach At the end of one of the iterations, a new regulation related to the product is enacted.

What should the project manager do next?

A.

Make a change request regarding the project's scope to ensure compliance.

B.

Include an assessment to verfy compliance in the next iteration

C.

Conduct an iteration review to address the new regulation

D.

Start the tests over, adapting the trials to the new regulation

Full Access
Question # 116

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?

A.

Guide the team to revert back to the forming and storming stages

B.

Escalate the issue to the project sponsor.

C.

Convene a team building event to address key performance indicators (KPIs).

D.

Discuss the decrease in productivity with human resources

Full Access
Question # 117

In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing The software update will be accomplished using an agile approach in order to minimize risk The machine procurement, installation, and integration will be accomplished using predictive approaches

What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule'’

A.

Weekly colocated meetings with the relevant stakeholders

B.

Biweekly conference calls with the relevant stakeholders

C.

Weekly one-on-one meetings with each of the relevant stakeholders

D.

Biweekly written status reports from the relevant stakeholders

Full Access
Question # 118

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.

Encourage and assign the team to perform demos of their products or software with the customers

C.

Give the team autonomy to make their own decisions on how to perform the tasks.

D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Full Access
Question # 119

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?

A.

Schedule a meeting with all stakeholders to extend the project deadline

B.

Replace the vendor with a new vendor who can offer the component on time

C.

Add an item to the next status review to make stakeholders aware of the vendor issue.

D.

Review and update the issue log and determine if any alternative components can be offered

Full Access
Question # 120

A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year

Which project approach suits the scenario?

A.

Execute it as a Scrum project

B.

Execute it as a predictive project

C.

Execute it using the same approach as the reference project

D.

Execute it as a project with stage gates

Full Access
Question # 121

The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project

What should the project manager do to reduce negative impacts to the project?

A.

Modify the communications management plan to account for regional differences

B.

Conduct cultural awareness seminars

C.

Hold a virtual meeting to discuss the political environment.

D.

Conduct a multigenerational management training session

Full Access
Question # 122

Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?

A.

The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate

B.

Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator

C.

The team facilitator uses historical data and arrives at an estimate based on the nature of the project.

D.

The product owner obtains all project details and based on the team's experience and velocity provides a budget estimate

Full Access
Question # 123

Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable

What should the project manager do next?

A.

Check the project budget to verify if there is enough contingency reserve

B.

Review the cost management plan to determine how to address this issue

C.

Tell the team members that more equipment is not part of the project's scope.

D.

Submit a change request to increase the budget and buy new equipment

Full Access
Question # 124

A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?

A.

Autocratic decision making

B.

Expert judgment

C.

Context diagram

D.

Change control tools

Full Access
Question # 125

During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice One of the client representatives, who is not a key decision maker, is extremely opinionated This client representative could become a roadblock to progress due to their perceived level of authority during meetings

How should the project manager handle this moving forward?

A.

Ask that only key decision makers attend the project meetings.

B.

Update the project schedule to cater to this particular stakeholder

C.

Allocate time to gain buy-in from the stakeholder prior to key decision meetings.

D.

Update the risk register to consider the possible project impacts

Full Access
Question # 126

While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?

A.

Ask the product designer why the deviation was not considered in the design phase

B.

Report to the project sponsor that the product is working and the project is struggling with the budget.

C.

Evaluate and initiate the change request process with the stakeholders

D.

Ask the quality team to discard the sample and test again with a new sample

Full Access
Question # 127

The following table shows the business value created and the development effort required to implement various features in a product

Which feature should the team prioritize first? Enter the feature name in the box below

Full Access
Question # 128

From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?

A.

Inform the client that extra resources will be added to give the client more time for reviews.

B.

Update the project risk register with the potential for delays

C.

• Work with the client on an acceptable amount of time for document approval

D.

Inform the client of their responsibility in relation to document approval

Full Access
Question # 129

During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings

How should the project manager handle this?

A.

Communicate directly with the director and inform them of the communications management plan

B.

Communicate directly with the client stating that any scope changes must go through the project manager

C.

Review the stakeholder engagement plan and put in place any existing actionsaccordingly

D.

Discuss the issues with the project team and let them know that the project manager will handle scope changes

Full Access
Question # 130

During a documentation audit of an international company it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated How should the project manager have handled documentation for the project?

A.

Updated the project management plan regularly and had it securely shared with all stakeholders

B.

Assigned a project team member to ensure all project documentation was updated

C.

Reviewed the risk register to identify a response plan for the audit

D.

Kept documentation in the project management information system (PMIS), and shared it with appropriate stakeholders

Full Access
Question # 131

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

A.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables

B.

Request more funding from the project sponsor to hire additional skilled resourcesand to incorporate additional quality in the project delivery approach and outcome

C.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions

D.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives

Full Access
Question # 132

The customer's project manager changes during the final stage of a project How can the project manager avoid a project closure delay’

A.

Update the stakeholder engagement plan

B.

Review the latest project status report and update the stakeholders

C.

Escalate the case to the customer's management team

D.

Issue the project payment invoice to the customer in advance

Full Access
Question # 133

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Review the lessons learned from the previous project

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Create a lessons learned document for the initiation phase

Full Access
Question # 134

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

A.

Escalate the matter to the executive board so they can decide on next steps

B.

Prioritize the project backlog and ask the development team to fix the issues

C.

Review the project's benefits management plan with the product owner.

D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits

Full Access
Question # 135

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

A.

Probability assessments

B.

Collaborative discussions

C.

Workshops for risk avoidance

D.

Interview with the project champion

Full Access
Question # 136

A project has a very tight delivery schedule The project is approaching the delivery date and the project sponsor often sends the project manager alerts to avoid any schedule slippage The project team has performed at an acceptable level until now but the project manager wants to ensure the team's performance level is maintained until the end

What action should the project manager take to motivate the project team’s performance?

A.

Send a formal notice to team members instructing them to maintain performance

B.

Hire a few temporary team members to help with the additional work

C.

Award certificates of appreciation to encourage the team

D.

Inform the team about the delivery pressure from the project sponsor

Full Access
Question # 137

The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action

What two actions should the project manager take'? (Choose two)

A.

Discuss with the construction team alternatives on moving the new train station to another location.

B.

Publish information on the city’s website about the benefits that the new tram station will bring

C.

Have a meeting with the mayor and explain the importance of the new train station to the city.

D.

Conduct regular meetings with the neighbors to get their buy-in for the project

E.

Register this situation as a risk and develop a mitigation plan

Full Access
Question # 138

A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email

What should the project manager do?

A.

Contact the sponsor to request direction regarding the communication tool to be used by the project team

B.

Update the communications management plan based on the product owner’spreferences and distribute to the team

C.

Suggest to the team to start using the communication tool suggested by the product owner

D.

Request the product owner to use email because using another tool will increase the workload

Full Access
Question # 139

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?

A.

Check the approved list of requirements to see if there are any missing items.

B.

Work with the stakeholder to improve the requirements' acceptance criteria

C.

Review the requirements traceability matrix with the concerned stakeholder

D.

Discuss with the stakeholder which additional requirements should be added

Full Access
Question # 140

To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations

What should the project manager do?

A.

Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate

B.

Review the historical information and lessons learned from last year’s project to justify the new budget estimate

C.

Change the budgeting technique to a more accurate, bottom-up cost estimation.

D.

Use soft skills to convince the project sponsor to approve the new budget estimate

Full Access
Question # 141

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.

How should the project manager respond’

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced

B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework

C.

Record the issue in the issue log and escalate the conflict to the project sponsor forassistance

D.

Explain to the stakeholder that the stakelrolder engagement plan requires their attendance at all reviews

Full Access
Question # 142

A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes

What should the project manager have done at the start of the project to prevent this resistance?

A.

Created a communications management plan that outlined the method of communicating to stakeholders.

B.

Ensured that the company culture encourages changes before accepting the project

C.

Encouraged leadership to discuss the change with departments that are typically resistant to change

D.

Involved stakeholders from all levels of the company so everyone understands the change

Full Access
Question # 143

A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next

Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)

A.

Sprint charter

B.

Burndown chart

C.

Company mission and vision

D.

Product backlog

E.

Sprint goal

Full Access
Question # 144

A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped

What should the project manager do?

A.

Analyze both projects to determine the most effective use of common resources

B.

Use resource optimization to justify requesting more resources for the critical project

C.

Provide schedule optimization training to the project teams to improve their skills.

D.

Apply fast-tracking techniques to compress the schedule of the critical project

Full Access
Question # 145

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?

A.

Sent the meeting minutes to the stakeholders after the kick-off meeting

B.

Reviewed all the approvals immediately after the kick-off meeting was over

C.

Ran separate kick-off meetings for each culture and time zone

D.

Validated each stakeholder's understanding during the kick-off meeting

Full Access
Question # 146

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?

A.

Assign the tasks to another resource, and ask the resource to work double shifts

B.

Update the schedule to reflect the project's changes in duration

C.

Ask human resources (HR) for a replacement, and update the nsk register

D.

Update the resource management plan and resource allocation chart accordingly

Full Access
Question # 147

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status

What should the project manager do?

A.

Update the stakeholder engagement assessment matrix

B.

Update the communications management plan to include informal requests

C.

Ask the team member to develop a dashboard to fulfill the request.

D.

Tell the team member to route the request through the project manager

Full Access
Question # 148

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?

A.

Ask the team to work overtime to complete the deliverable on time

B.

Evaluate the situation and identify ways to compress the schedule without impacting baselines

C.

Check the scope to verify if there is scope creep and get the project on schedule

D.

Submit a change request to the project sponsor to change the schedule

Full Access
Question # 149

The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director’s support as the marketing director is a key stakeholder.

What should the project manager do to obtain the support?

A.

Ask the marketing director to participate in daily meetings

B.

Mentor the marketing director on hybrid approaches

C.

Ask the marketing team members to coach the director

D.

Tram the marketing team and keep the director informed

Full Access
Question # 150

A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project

What should the project manager have the project team update to ensure proper communications to stakeholders?

A.

Project management plan

B.

Stakeholder engagement plan

C.

Stakeholder register

D.

Communications management plan

Full Access
Question # 151

A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?

A.

Conduct a stakeholder analysis to identify how regional policies may influence needs

B.

Request relevant stakeholders to conduct an analysis and reach consensus independently

C.

Conduct a project scope review workshop with relevant stakeholders.

D.

Conduct project planning meetings in one location with relevant stakeholders

Full Access
Question # 152

A client is structured as a matrix organization for an agile project The project manager is working on-site with key stakeholders from different parts of the organization

How should the project manager handle the different stakeholders?

A.

All stakeholders are important, so the project manager should follow directions provided by management and key stakeholders

B.

Because there are different perspectives perform a stakeholder analysis and act based on the outcome.

C.

The project manager is working on the client's premises, so follow the directions of all the key stakeholders

D.

This is an agile project, so listen only to the directions of the project manager's supervisor and the functional managers of the organization

Full Access
Question # 153

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase

What item(s) should the project manager develop first?

A.

A product backlog and identification of the features to be delivered

B.

A business case and scope document

C.

A communications management plan that addresses the team's needs

D.

A risk management plan to incorporate known risks

Full Access
Question # 154

In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.

What should the project manager do next1?

A.

Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder

B.

Inform the project sponsor that there are stakeholders who are not included in the communications management plan

C.

Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan

D.

Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.

Full Access
Question # 155

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

A.

Ensure the sprint size is appropriate for the iteration duration.

B.

Promote changing the iteration duration in order to commit as planned.

C.

Engage in recruiting a highly skilled resource to reinforce the skills.

D.

Consider using a reward system to encourage timely delivery

Full Access
Question # 156

During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.

What should the project manager do next?

A.

Discuss approval of the change request in the next project meeting

B.

Perform a risk assessment on the required change request.

C.

Evaluate the change request against the project scope statement

D.

Ask the sponsor for more funds to cover the change request

Full Access
Question # 157

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.

What training should the project manager choose for their team to help with this situation?

A.

Communication training

B.

Negotiation training

C.

Emotional intelligence training

D.

Agile training.

Full Access
Question # 158

A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork

What should the project manager do to improve morale?

A.

Identify the wants and aspirations of the team

B.

Build team connections and emotional bonds

C.

Forge consensus through team participation.

D.

Set goals and push the team to achieve the goals

Full Access
Question # 159

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

A.

Perform a risk assessment and define a risk response action plan.

B.

Proceed with the project using management reserves to cover any delays or losses.

C.

Propose a pause in this phase to save labor costs and asset depreciation.

D.

Establish new partnerships with other suppliers in anticipation of any delays.

Full Access
Question # 160

A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams

What should the project manager do?

A.

Emphasize to the teams the importance of meeting the agreed deadlines

B.

Provide appropriate training to compensate for the mismatch.

C.

Update the project schedule to reflect the delay

D.

Accept the risk of the project missing deadlines due to the mismatch.

Full Access
Question # 161

In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict

How should the project manager resolve the problem?

A.

Talk to the supervisor to tone down their approach and attitude.

B.

Provide a just-in-time training to the technician to improve their skill set.

C.

Use a direct, collaborative approach with the technician and supervisor.

D.

Replace the technician with a high performing resource as time is critical

Full Access
Question # 162

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

Full Access
Question # 163

Drag the communication event on the left to the mam subject discussed during the event on the right.

Full Access
Question # 164

A project manager of a large company needs to categorize the stakeholders' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.

Drag each stakeholder scenario on the left to the correct engagement level on the right.

Full Access
Question # 165

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

Full Access
Question # 166

A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?

A.

Ask the product owner, who is the key stakeholder, to choose among the different ideas.

B.

Propose ideas to the group, ask everyone to vote, and then choose the most popular idea

C.

Schedule a session to give everyone the chance to express their opinions about each idea, then vote and decide.

D.

Offer an opinion about the pros and cons of each idea and try to reach a consensus in a facilitated meeting

Full Access
Question # 167

During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?

A.

Ask the new team member to follow the team ground rules.

B.

Ask an experienced team member to identify a replacement

C.

Ask the new team member to reassess their own capabilities

D.

Ask an experienced team member to coach the new team member

Full Access
Question # 168

The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress What should the project lead do?

A.

Provide a link to the project's shared drive for the executive to search through for any artifacts that are of interest.

B.

Invite the executive to the project's meeting space to determine if the project information radiators meet their needs

C.

Reach out to the project management office (PMO) for status report templates and provide project updates in that format

D.

Ask the project sponsor or product owner to provide an update since the project lead should be trying to keep the team free from impediments

Full Access
Question # 169

An organization is transitioning to agile and a project has been chosen as a pilot The assigned project manager only has experience using predictive approaches but the project manager is now required to use agile approaches with the help of an agile coach During the retrospective of the fifth sprint, the project team complains that many obstacles exist with the organization that are creating project delays and rework

What should the project manager do in this situation?

A.

Include impediment resolutions during daily standup meetings

B.

Perform a root cause analysis during the standup meetings

C.

Create a dedicated sprint to solve the obstacles with the team

D.

Promote collaboration to help remove the obstacles for the team

Full Access
Question # 170

A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time

How should the project manager address this situation?

A.

Address the lack of performance by coaching the new team member

B.

Discuss options to improve performance with the resource manager

C.

Provide performance feedback as part of the retrospective ceremony.

D.

Request a more efficient replacement resource from the project sponsor

Full Access
Question # 171

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session

What should the project manager do first?

A.

Share the project documents and invite the key stakeholder to discuss any concerns

B.

Ask the project sponsor to exert authority on the key stakeholder in order to maintain the approved timeline

C.

Proceed with a working session for teams that do not belong to that key stakeholder

D.

Invite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy

Full Access
Question # 172

A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.

What should the project manager do?

A.

Create a roles and responsibilities matrix based on the project charter and ask the sponsor to share it with all stakeholders to provide credible authority

B.

Conduct scoping workshops with the project team to create a work breakdown structure (WBS), assign tasks to various entities share this with all stakeholders, and ask the team to complete their tasks as scheduled

C.

Conduct a general meeting with all stakeholders and review and address a list of activities for each of them

D.

Breakdown the situation to identify the root causes for the disagreement and then work with each stakeholder and participating entity on their exact roles and responsibilities

Full Access
Question # 173

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.

How should the project manager improve this situation with the project team?

A.

Engage the project team In implementing and Improving key aspects of the standup meetings.

B.

Ask the product owner to remove team members who do not comply with standup meeting rules.

C.

Send a daily retrospective report to all team members instead of holding standup meetings.

D.

Include a daily brainstorming session In the standup meetings to resolve pending Issues.

Full Access
Question # 174

The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?

A.

Advise the marketing director to receive formal training.

B.

Ask the marketing team members to coach their director.

C.

Train the marketing team and keep their director informed.

D.

Mentor the marketing director on the approaches.

Full Access
Question # 175

A team Is experiencing difficulties and has decided to use a spike. Please click on the portion of the burndown chart that corresponds to the spike.

Full Access
Question # 176

A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?

A.

Have the product owner create product documentation

B.

Have the team create a minimum viable product (MVP).

C.

Have the marketing department create a survey

D.

Have the team create a prototype with all features

Full Access
Question # 177

Vendor A submitted a bid for US$500,000. There is a 65% probability that the

vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come

in ahead of schedule for a savings of US$50,000.

What should the project manager determine as the value of the vendor's bid?

A.

US$650,000

B.

US$452,500

C.

US$547,500

D.

US$582,500

Full Access
Question # 178

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?

A.

Perform a qualitative risk analysis and update the risk register.

B.

Submit a change request through the Integrated change control process.

C.

Update the issue log and discuss It in the next steering committee meeting.

D.

Estimate the associated costs and increase the project budget accordingly.

Full Access
Question # 179

A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9

A.

Provide team-building activities so that the team can learn how to overcome disruptive behavior

B.

Inform the disruptive team member's functional manager that the disruptive behavior should be stopped immediately

C.

Request a meeting with the disruptive team member and help to resolve the issue

D.

Encourage self-governance and ask the concerned team member to speak to the disruptive team member directly

Full Access
Question # 180

A project team that is very experienced in enterprise resource planning (ERP)

systems implementation is currently planning the delivery of a new ERP project. There is a

requirement to reuse the client's security subsystem developed by a third party. The client

states that integration with the security subsystem must be done by the client's team. The

project manager does not want to have such an external dependency.

What should the project manager do first?

A.

Plan the implementation of this integration in the first iteration to help reduce risks.

B.

Record the issue in the issue log and closely manage this dependency.

C.

Inform the client that the project team will take care of the integration.

D.

Document the client's responsibility for the integration with the security subsystem.

Full Access
Question # 181

One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.

What should the project manager do?

A.

Assign this member to facilitate the next meeting to ensure project team collaboration.

B.

Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.

C.

Review and update the project ground rules to make meeting attendance mandatory.

D.

Understand the reason for the team member's absence and encourage them to attend future meetings.

Full Access
Question # 182

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?

A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach

B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using

C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use

D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project

Full Access
Question # 183

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer

B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports

C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop

D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server

Full Access
Question # 184

During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements

Which technique should the project manager use to resolve this issue?

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Force/direct

D.

Collaborate/problem solve

Full Access
Question # 185

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?

A.

Functional managers, team members, and external consultants with experience in the field

B.

Team members, engineers, and weather experts

C.

Team members, consultants from outside the project with experience in the field, and the customer

D.

Weather experts, functional managers, and team members

Full Access
Question # 186

A customer asks the project manager about opportunities to create business value.

What should the project manager do first in order to provide the customer with an appropriate

response?

A.

Examine the business value throughout the project.

B.

Ask the team to organize a spike to identify more value.

C.

Meet with the product owner to review the backlog.

D.

Meet with the sponsor to review the business case.

Full Access
Question # 187

A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?

A.

Modeling directive leadership

B.

Modeling commanding leadership

C.

Modeling adaptive leadership

D.

Modeling servant leadership

Full Access
Question # 188

In an ongoing project, stakeholders have been approaching team members for status

reports and changes without consulting the project manager. What should the project

manager do to ensure a successful project?

A.

Send the project charter to all stakeholders for information.

B.

Send an email to all stakeholders directing them to approach the project managerdirectly.

C.

Review the stakeholder engagement plan and inform the stakeholders.

D.

Review the change management plan and ask the change control board (CCB) to beinvolved.

Full Access
Question # 189

During a project gate review meeting, it is identified that one of the project

deliverables will require corrective actions to meet the project quality requirements. What

should the project manager do first?

A.

Update the risk register and implement the approved risk response plan for qualitydeviations.

B.

Identify the resources that were responsible for the deliverable and request a teamdevelopment plan.

C.

Update the issue log, identify the involved stakeholders, and assign resources to thecorrective actions.

D.

Submit a change request to update the project quality requirements for the involvedproject deliverable.

Full Access
Question # 190

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

A.

Develop requirements and designs to support a faster product release.

B.

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Outsource development of the product to a third party with more experience.

Full Access
Question # 191

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Full Access
Question # 192

A protect manager has just finished planning for a project when the client adds a new project team member The project manager Knows that the new team member only works remotely and is not in the main office. In addition, the new team member engages with decisions quickly in a face-to-face environment, but is slow to respond otherwise.

How should the project manager reflect this in their planning?

A.

Send out recurring onsite project meeting invites to ensure the team member's presence.

B.

Update the project charter to include the new team member for this project.

C.

Monitor the new team member's input to gauge their value to the project.

D.

Include the team member in the stakeholder register and update the communications management plan.

Full Access
Question # 193

When a project manager is trying to determine a leadership style to use on a project what should they consider?

A.

Number of tasks on the protect

B.

Culture of the organization

C.

Project timeline

D.

Experience of the project manager

Full Access
Question # 194

In an agile product development environment, work is distributed to Cities A, B, and

C, which are geographically dispersed. The small teams work and collaborate to deliver the

sprints.

• City A's team focuses on the features of data capture.

• City B's team focuses on the user experience and development pieces.

• City C's team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?

A.

Ensure all three teams deliver independently without interactions so that they remainfocused and meet customer requirements.

B.

Implement communication techniques and ensure the teams follow a relay pattern ofhanding off work from one team to the other.

C.

Use a fishbone analysis to resolve problems and iron out communication issuesbetween the teams.

D.

Maintain localized teams to circumvent the challenges of delay or any otherunforeseen risks that might prevent progress.

Full Access
Question # 195

A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.

What should the project manager do in this situation?

A.

Explain to the management team that reporting and management dashboards are not effective agile practices

B.

Ask the management team to review the endorsed agile concepts to prove that the old information s not relevant

C.

Help the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPls)

D.

Remind the management team that an agile approach empowers teams to be self-directed and therefore there is no need for reporting

Full Access
Question # 196

A project, which has its execution phase planned m an iterative way has the following metrics for the first three iterations

One of the requirements for the project states that m order to get payment authorized fcx the project neither the SPI nor the CPl can be less than 0 95 What should the project manager do in iteration 4 to ensure the project is in compliance with the requirement?

A.

Schedule crashing

B.

Fast tracking

C.

Earned schedule

D.

Earned value

Full Access
Question # 197

A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?

A.

Replan the remaining iterations according to the new installation dates

B.

Update the product backlog m order to address the delays

C.

Review the procurement agreements to address the situation

D.

Find another vendor who can fulfill the delivery dates

Full Access
Question # 198

A team is given an agile project to build a conceptual product for a new customer.

While planning, the project manager is trying to determine the best way to show value to the

customer, as the technical requirements are not very detailed.

What should the project manager do to help the client understand the value delivered during

project execution?

A.

Include a planned value (PV) calculation in the sprint report for each build cycle.

B.

Conduct a customer demonstration at the end of each build cycle.

C.

Provide the customer with the refined specification during each build cycle.

D.

Show the customer a sprint burndown chart for each build cycle.

Full Access
Question # 199

A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.

What should the project manager do?

A.

Update the issue log and review the lessons learned register for options

B.

Implement conflict resolution to accommodate the team's needs

C.

Implement decision-making techniques to advance the stones

D.

Empower the team to self-organize and make their own decisions

Full Access
Question # 200

An agile team has started a new project. When should the project manager organize their first team retrospective?

A.

When the team completes a release of a monumental increment

B.

When the team reaches a major milestone

C.

When more than a few weeks have passed

D.

When the work is progressing well through the team

Full Access
Question # 201

A new sales software development project is underway The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.

Which project approach should the project manager take?

A.

Incremental

B.

Predictive

C.

Hybrid

D.

iterative

Full Access
Question # 202

A project manager who works for a company involved in several industries is asked

to lead a software development project for a government agency. The company attempted to

execute similar projects for other industries before but was unsuccessful.

What should the project manager do to ensure project success?

A.

Document this information in the risk management plan.

B.

Develop a contingency plan to prepare for possible risks.

C.

Continue executing the project using expert judgment.

D.

Review the lessons learned registers from the previous projects.

Full Access
Question # 203

A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

A.

Report the issue during the next status meeting at the end of the week

B.

Escalate the issue to the project sponsor and upper management

C.

Close out the project and tell the manager to open a service desk ticket

D.

Log the issue and assign it to the project team member(s).

Full Access
Question # 204

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

A.

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution

B.

Call a team meeting to discuss team members' strengths and weaknesses

C.

Establish rules and regulations for team members with consequences if the goals are not reached

D.

Establish team behavior and develop an understating of how to work together

Full Access
Question # 205

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

A.

Recognize the stakeholder's skills are important for the project and evaluate thepossibility of the stakeholder supporting the project team.

B.

Request the functional manager to assign the team from the lessons learned project tothe current project to avoid a learning curve.

C.

Ask the project team to review the lessons learned and have the team contact thestakeholder directly if there are any questions.

D.

Send a request to the project sponsor to hire the stakeholder and have them becomepart of the project team.

Full Access
Question # 206

The change control board (CCB) has approved a change request to add a new

component within a product. The operations manager discovers the change after its approval

and complains that the implementation of the change will cause significant disruption to the

production line.

What should the project manager do first?

A.

Escalate the issue to the project sponsor, as the decision to add the component bringsmany benefits even though it will be disruptive to the production line.

B.

Lead a root cause analysis workshop with the design team to identify the failures thatled to the decision to add a component that was not compatible with the productionline.

C.

Meet with the operations manager to explain the background for the change andunderstand the operation manager's concerns about the change.

D.

Formally acknowledge the operation manager's concerns and raise a new risk that theproject may deliver late and over budget due to manufacturing difficulties.

Full Access
Question # 207

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

A.

Meet with the stakeholder to discuss the impact of the deliverable

B.

Consider the stakeholder as a risk and evaluate possible solutions with the project team

C.

Improve communication with the stakeholder to obtain their assistance in the future

D.

Escalate to the project sponsor due to the political nature of the issue

Full Access
Question # 208

A project manager is leading a project that is implementing an assembly line.

During the quality review meeting, a team member reports an issue stating that the product

being developed has discrepancies with the one requested by the customer.

What should the project manager do?

A.

Ensure the current solution is in place to enable future usability.

B.

Run a root cause analysis to identify the quality breach and update the qualitymanagement plan.

C.

Check that the product meets the requirements established by the customer.

D.

Make a proposal of new specifications and submit it to the customer for approval.

Full Access
Question # 209

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

A.

Increase the overall project duration to account for the inexperienced team memberson the project.

B.

Ensure planning has accounted for replacing team members in new project roles whodo not deliver on project goals.

C.

Assess the training requirements and ensure time for professional developmenttraining by senior members.

D.

Revisit the project resource allocation to remove the inexperienced team membersassigned to the project.

Full Access
Question # 210

A project manager has experience working with a specific provider that has been

requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.

What should the project manager do during the planning phase?

A.

A. Hire resources to obtain knowledge about the provider's specific capabilities.

B.

B. Add penalty clauses to the contract and update the risk register.

C.

C. Encourage the provider to work overtime with no additional costs to the project.

D.

D. Contract another provider with less experience and give them a chance to provide the deliverables.

Full Access
Question # 211

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items

What should the project manager do as a servant leader?

A.

Ask the sponsor to submit a change request to the change control board (CCB)

B.

Support the product owners decision to change the priority of the product backlog items

C.

Accept the request and include the product backlog items in the next sprint

D.

Review the impact of the change on the schedule management plan baseline

Full Access
Question # 212

A project manager has been assigned to a project that is in progress. The project

manager is looking for information regarding why the project is being completed.

What should the project manager do first?

A.

Evaluate the project exit criteria in the project charter.

B.

Reach out to the senior executive sponsor for the project.

C.

Understand the project success criteria and objectives.

D.

Review the project status reporting for the latest information.

Full Access
Question # 213

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?

A.

Discuss the issue with the project sponsor and request extra time and budget to obtainthe component from a different supplier.

B.

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response

C.

Submit a change request to the change control board (CCB) for changes to theperformance measurement baseline to obtain the component from a different supplier.

D.

Raise a new issue in the issue log and convene subject matter experts (SMEs) andrelevant stakeholders to identify alternatives to address the problem.

Full Access
Question # 214

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Full Access
Question # 215

A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.

What should the project manager do next?

A.

Refer to the previous protect they worked on and base the estimate on that

B.

Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses

C.

Ask the project management office (PMO) by when the project can be completed and use that date as the project time line

D.

Break down the project into smaller tasks and estimate the durations of the activities

Full Access
Question # 216

An international client contacted a software development company to build out a

software product, and an agile project manager was assigned. At one of the review meetings,

the client complains that a feature mentioned at the initial debriefing was not implemented.

What should the project manager do?

A.

Include the mentioned feature in the prioritized requirements list.

B.

Assign a team member to immediately start working on that feature.

C.

Review the original project documentation to confirm.

D.

Treat it as a change request and assess the effect on the project's goals.

Full Access
Question # 217

A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided

details to the customer 2 weeks ago and set up a weekly conference call to effectively

communicate with them, but the customer has not been participating in the calls.

How should the project manager handle this situation?

A.

Request a change in the contract to include the shipment in the project managementplan.

B.

Find the root cause of the issue and discuss the customer's current engagement.

C.

Inform the customer that subsequent packages cannot be manufactured.

D.

Request a delivery date extension from the customer

Full Access
Question # 218

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

A.

Estimate user story points and forecast a budget for that deliverable

B.

Determine the control accounts and use a top bottom estimate

C.

Consider the cost performance index (CPl) based on earned value (EV) divided by costs

D.

Calculate the budget at completion (BAC) based on the completed and planned features

Full Access
Question # 219

During the forming phase of a project team a project manager implements several team-building initiatives and decides it would be fun to have improvisations theater activities. After the sessions the project manager received feedback from some key team members who felt that although the activity was fun it was not appropriate for the purpose of team building.

What should the project manager have done to avoid this negative feedback'?

A.

Assessed and analyzed personality indicators from the project team

B.

Sent the activity details to everyone involved prior to the session

C.

Communicated the decision to conduct this activity to the key team stakeholders

D.

Selected a vendor for the activity according to the procurement management plan

Full Access
Question # 220

A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?

A.

Follow the risk response plan

B.

Use the contingency fund

C.

Prepare a change request

D.

Update the risk register

Full Access
Question # 221

A project manager is assigned to lead a design for a new version of an existing

product with the technology and operations teams. The project manager organizes a joint

requirements session to determine the most practical ideas. The project manager was advised

that the session may become chaotic.

What should the project manager do to ensure the session is interactive, productive, and

efficient?

A.

Pick the senior and experienced staff members from both teams and arrange face-toface interviews.

B.

Organize a formal session led by a skilled facilitator with defined rules for howparticipants will interact with one another.

C.

Distribute a questionnaire on the key features of the product and encourage the teamsto respond with their design recommendations.

D.

Hold multiple sessions of manageable sizes with participants from both teams todiscuss their ideas.

Full Access
Question # 222

A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?

A.

Refer to the project charter

B.

Review the project resource matrix

C.

Assess the stakeholder register

D.

Update the communications management plan

Full Access
Question # 223

A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company's CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)

What should the project manager do to control this situation?

A.

Redefine the communications management plan

B.

Develop an integrated change management plan

C.

Document the risk in the project risk register

D.

Review the scope defined in the project charter

Full Access
Question # 224

A government agency is developing a new connectivity policy. The assigned project

manager is a famous economist with international recognition. The team is eager to work with

the project manager, but feels intimidated. The project manager realizes that a junior

economist, whose tasks are behind schedule, is especially intimidated by the situation.

What should the project manager do first?

A.

Evaluate the performance of the junior economist in the upcoming months.

B.

Reassign some of the junior economist's tasks to other economists.

C.

Request to replace the junior economist with a more experienced economist.

D.

Consider organizing paired work sessions for the junior and senior economists.

Full Access
Question # 225

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?

A.

Identify how the proposed changes will benefit the project in relation to the businesscase.

B.

Ask for a temporary budget increase to avoid cost overruns.

C.

Keep the team motivated and incentivized to avoid exhaustion from working on alengthy project.

D.

Assess the schedule delay and begin implementation to avoid additional lags

Full Access
Question # 226

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.

What should the project manager do first?

A.

Perform an impact analysis with subject matter experts (SMEs).

B.

Inform the government representative about the impact of the separate project.

C.

Implement a change request to increase the budget and schedule.

D.

Consult and update the risk register with the project stakeholders.

Full Access
Question # 227

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

A.

Organizational process assets (OPAs)

B.

Lesson learned registers from past projects

C.

Historical issue logs

D.

Project scope statement

E.

Project management plan

Full Access
Question # 228

During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project's completion date. It will Increase the likelihood of customer acceptance.

What should the project manager do to address the issue?

A.

Issue a change request to remove items from the scope of work and keep the project on schedule.

B.

Issue a change request to include the additional scope, and track the completion of the work items.

C.

Document the issue in the lessons learned document, and discuss this with the project sponsor.

D.

Arrange to pass the cost to the operational area since the customer will benefit.

Full Access
Question # 229

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

Full Access
Question # 230

A project manager is leading an electrical project that spans five towns. The project

manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.

What should the project manager do?

A.

Change the project scope and seek approval to exclude this town from the overallproject.

B.

Engage with the town's authorities to discuss the reason for the change in commitmentand agree on a solution.

C.

Instruct the team to move to the next town and continue the project to avoid further delays.

D.

Retrieve all minutes of stakeholder engagements and send to the town as a reminder of their commitment to the project.

Full Access
Question # 231

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

A.

Stakeholder analysis

B.

Resource needs analysis

C.

Accommodations assessment

D.

Team member assessment

Full Access
Question # 232

An agile project manager is evaluating the method that will be used to display the

value of the work performed to date. Which method will they select to display to the project stakeholder?

Full Access
Question # 233

A new project manager has been assigned to an environmental project. After

reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

A.

Injury or loss incidents could delay project deliverables.

B.

It is imperative that established performance metrics are met.

C.

The project manager is obligated to comply with the project location's regulatoryrequirements.

D.

The project manager must follow their employer's organizational process assets(OPAs).

Full Access
Question # 234

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

A.

Product backlog, budget, resource management plan

B.

Budget, minimum viable product (MVP), retrospective notes

C.

Resource management plan, retrospective notes, backlog grooming

D.

Backlog grooming, product backlog, minimum viable product (MVP)

Full Access
Question # 235

A project manager is appointed to manage an infrastructure project that spans

across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

A.

Discuss the concerns with the project sponsor and modify the project charter to includemore budget for interactions.

B.

Plan a communication method and allow the project team members to virtually interact.

C.

Create a social media group platform for the team to create a supportive environment.

D.

Set the ground rules and identify a contingency plan in the risk register.

Full Access
Question # 236

A project team is facing challenges understanding how to deliver a project's scope.

A senior subject matter expert (SME) from the organization's global office is in town for 1 week.

What should the project manager do to benefit from the SME's presence?

A.

Ask the SME to review the scope for alignment with the project charter.

B.

Organize a mentoring session with the team and the SME.

C.

Meet with the SME to discuss the current challenges the team is facing.

D.

Review the project scope statement with the SME.

Full Access
Question # 237

A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward

What should the project manager do first at this pomp

A.

Meet with the quality planning manager to identify the reason why the quality plan was not created yet

B.

Meet with the hardware design engineers to identify the minimum performance required to establish a market for the machine

C.

Meet with the sales and marketing teams to identify the requirements that were collected during the interview sessions with potential customers

D.

Meet with the key stakeholders to identify the proper product concept for the development team

Full Access
Question # 238

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Full Access
Question # 239

In a software project using an agile approach, there have recently been work

overruns. After assessing the situation, the project manager concluded that the overruns are

occurring because of insufficiently refined product backlog items.

What should the project manager do to correct this issue?

A.

Work with the sponsor to revise the product vision.

B.

Create a definition of ready (DoR) for the backlog items.

C.

Discuss the issue with the service request manager.

D.

Refine the product backlog items with the stakeholders.

Full Access
Question # 240

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

A.

Engage the services of an interpreter who understands the project domain.

B.

Check social media to determine if there are any common connections that use the new supplier.

C.

Request assistance from the procurement department on the next steps.

D.

Become aware of any cultural characteristics of the new supplier that could impactnegotiation.

Full Access
Question # 241

A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office's (PMO's) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO's status reports have sufficient enough information

How should the new project manager proceed*?

A.

Continue using the outgoing project manager's status reports as well as their approach for schedule reporting

B.

Explain to the PMO that the hybrid project team needs to keep an agile approach for reporting and will not be complying with the organizational standard

C.

Change the status reports according to the template supplied by the PMO and proceed with scheduled reporting

D.

Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

Full Access
Question # 242

A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.

What should the project manager do?

A.

Explain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule

B.

Document who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report

C.

Explain to the project sponsor that they are accountable for tracking benefits realization after project completion

D.

Discuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)

Full Access
Question # 243

A project stakeholder has expressed concern that the established success criteria for

the project are not being met. What should the project manager do next?

A.

Review the established project benefits tracking metrics.

B.

Update the project business case document.

C.

Document the agreed-upon ownership of benefits realization.

D.

Create a project benefits management plan.

Full Access
Question # 244

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

A.

Plan to execute the procurement tasks in a virtual environment.

B.

Review organizational process assets (OPAs) for similar projects.

C.

Create a change request to extend the duration of the project.

D.

Ask the project sponsor to put the project on hold.

Full Access
Question # 245

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

Full Access
Question # 246

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer

B.

Meet with both integration leads to understand the root cause and determine a resolution

C.

Escalate the issue to the program architect who developed the integration plan

D.

Assign the resolution of this issue to the integration lead who is a SME

Full Access
Question # 247

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

A.

Conduct a consensus-building session to decide how to approach the next set of work.

B.

Escalate the issue to the product owner for resolution.

C.

Add this conflict to the agenda for discussion at the next daily standup meeting.

D.

Conduct a planning session to decide how to approach the next set of work.

Full Access
Question # 248

A project manager is developing a project baseline schedule and has started to

assign team members to the project activities according to their function. What should the

project manager do in this phase?

A.

Develop project onboarding guidelines for the team members assigned to the project.

B.

Ensure that a kick-off meeting is planned and invite relevant stakeholders toparticipate.

C.

Ensure that lessons learned are considered as part of the project scheduledecomposition.

D.

Confirm that no conflicts exist in resource calendars with assigned activities on otherprojects.

Full Access
Question # 249

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

A.

Send an email update to existing team members about the addition of the new teammembers.

B.

Set up a weekly meeting with the new team members for a couple of months.

C.

Request the transfer of the new members to another project, citing a risk of confusion.

D.

Update and share the guideline document dealing with team communication.

Full Access
Question # 250

A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.

What should the project manager do to address this concern?

A.

Ask human resources (HR) to coordinate another activity.

B.

Reassess the team situation and provide a proper solution.

C.

Inform HR about the situation and ask for support.

D.

Meet with the team to explain that conflicts must be addressed and solved.

Full Access
Question # 251

A project team member has lost enthusiasm and is experiencing low morale for a

project they were once excited about. What should the project manager do?

A.

Escalate the issue to the team member's functional manager and request a responseas soon as possible.

B.

Meet with the team member to understand what the issues are and to provide support.

C.

Leverage other team members who are contributing and making the project a success.

D.

Have the team member transferred to another project and add other resources to theproject.

Full Access
Question # 252

An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?

A.

Updated the stakeholder engagement plan to reflect a change in the product owner

B.

Communicated the status of the project more frequently with the product owner

C.

Updated the communications management plan to reflect a change in the communication needs

D.

Reevaluated the new product owner's needs for better engagement

Full Access
Question # 253

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project's

performance?

A.

Results of the MoSCoW assessment

B.

Cost-benefit analysis

C.

Return on investment (ROI) analysis

D.

Earned value analysis (EVA)

Full Access
Question # 254

A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time

What kind of conflict resolution did the project manager apply in this situation?

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Collaborate/problem solve

D.

Force/direct

Full Access
Question # 255

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback

What should the project manager do to resolve the issue?

A.

Move one of the team members to a different protect team

B.

Review the ground rules for collaboration within the team

C.

Report the performance issue to both of the team members' supervisors

D.

Modify the communications management plan and resend it to the team

Full Access
Question # 256

A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?

A.

Mass communication

B.

Push communication

C.

Pull communication

D.

Interactive communication

Full Access
Question # 257

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

A.

Assessed the technical and organizational readiness for the project and identified risksat the beginning of the first iteration

B.

Requested the product owner's approval to add an external expert to define theacceptance criteria

C.

Defined a clear acceptance criteria at the initiation phase and continued with theproject

D.

Increased the communications between the team member and the product owner

Full Access
Question # 258

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?

A.

Avoid the conflict as the customer feels comfortable with using processes fromcompany A.

B.

Review the historical information and make the decision based on the return oninvestment (ROI).

C.

Ask the team to use company B's processes since they are more familiar with theseprocesses.

D.

Work with the team to analyze which processes are suitable to use and define them inthe ground rules.

Full Access
Question # 259

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

A.

Assess the impact of the features and refer it to the change control board (CCB).

B.

Implement the new features after assessing the impact.

C.

Reject the new features since it amounts to gold plating.

D.

Add the new features to avoid losing the sponsor's support for the project.

Full Access
Question # 260

A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person

What should the project manager do first?

A.

Request additional developers to join the project team through the change cannot process

B.

Break down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment

C.

Assign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers

D.

Include the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely

Full Access
Question # 261

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?

A.

Ask the team to focus on and deliver only the agreed-upon features.

B.

Request additional budget because additional features are being added.

C.

Encourage the team to continue, as this will eventually help the customer.

D.

Ask the product owner to add the additional features to the requirements.

Full Access
Question # 262

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?

A.

Explore the minimum requirements of the product and their feasibility.

B.

Explain the resource constraints of the project to management.

C.

Outsource the management of the product to an external team.

D.

Conduct a detailed risk analysis to highlight the risks in the project.

Full Access
Question # 263

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

A.

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken,

B.

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

D.

Encourage the whole team to be empowered and accountable for the decisions made according to their roles,

Full Access
Question # 264

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit

Which two rules are appropriate tor the project manager to instill in the team? (Choose two)

A.

Strive toward continuous improvement

B.

Work together daily as a team

C.

Only share suggestions at the end of the sprint

D.

Follow the sprint planning

E.

Send communications to the entire team

Full Access
Question # 265

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

A.

Escalate a schedule risk to the sponsor.

B.

Conduct team-building exercises.

C.

Stop the project and perform a team skill assessment.

D.

Make sure that the team has a full understanding of the scope.

Full Access
Question # 266

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

Full Access
Question # 267

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

A.

Move the solution designer to another team.

B.

Review the process that resulted in this situation.

C.

Stop work until the design document is completed.

D.

Ask the team to document the design.

Full Access
Question # 268

During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.

What should the project manager do?

A.

Review the procurement documentation and modify requirements as needed.

B.

Study the new regulations with the team and evaluate if there is any impact on theproject variables.

C.

Update the contingency plan to take this issue into account.

D.

Meet with the stakeholders to update the risk register and risk management plan.

Full Access
Question # 269

A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?

A.

Schedule training courses to enhance team performance

B.

Add new team members to help the project finalization

C.

Initiate rewards and incentives according to assessment results

D.

Schedule working lunch meetings until the project is complete

Full Access
Question # 270

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?

A.

Document the issues and extend the project delivery timeline.

B.

Convene the steering committee and inform them of the impact to the project.

C.

Prioritize the user stories with issues and have the team resolve them

D.

Update the project management plan and risk management plan.

Full Access
Question # 271

As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?

A.

Include this topic in the next iteration retrospective

B.

Review this topic with the product owner before the next iteration planning

C.

Discuss this topic with the team in the next daily meeting

D.

Ask the product owner to review this topic in the next iteration planning

Full Access
Question # 272

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

A.

Descope low-priority features that were not explicitly requested and add this feature as a high priority.

B.

Inform the senior manager that they will need a new project management plan for this feature,

C.

Complete the most current feature and release the resources for the new feature.

D.

Analyze the impact of this change and present the options to the senior manager.

Full Access
Question # 273

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

A.

Plan the project based on the available resources and submit a change request upon completion.

B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.

Identify the technical requirements and request that management hire external resources,

D.

Document the problem in the issue log and suggest a change request to decrease the scope.

Full Access
Question # 274

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

A.

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Full Access
Question # 275

In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?

A.

Reassign the task to another member of the team

B.

Support the team member by providing one more resource to complete the task immediately

C.

Ask the team member if there is an impediment and help to remove the blockers

D.

Keep the project sponsor informed about the delay

Full Access
Question # 276

A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.

What should the project manager do?

A.

Inform the stakeholder that they must level their knowledge with other stakeholders.

B.

Update the risk register with the potential impact and apprise the steering committee.

C.

Inform the project management office (PMO) that the team will use a predictive approach for this project.

D.

Allocate time to mentor the stakeholder in the selected project approach.

Full Access
Question # 277

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

A.

Create a change request to extend the project's duration and costs.

B.

Provide feedback to the team using project performance evaluations.

C.

Escalate the impact on the schedule to the project sponsor.

D.

Include buffer time in the schedule to absorb future delays.

Full Access
Question # 278

A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing

Which three corrective actions should the project manager perform? (Choose three)

A.

Confront the people causing the stress directly with the aim of finding amicable solutions

B.

Seek support from the project management office (PMO) on addressing issues affecting the project

C.

Discuss the possible actions with the project sponsor

D.

Avoid the people causing stress and request a transfer as soon as possible

E.

Talk to the human resources (HR) manager about these concerns

Full Access
Question # 279

A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload

What should the project manager do to optimize the time of the resource who produces the progress reports?

A.

Work more closely with the agile team to eliminate the need for progress reports

B.

Record this in the issue log and find a resource to produce the reports

C.

Produce the progress reports on their own

D.

Engage a new resource to produce the progress reports

Full Access
Question # 280

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing

Full Access
Question # 281

A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented

What should the project manager do?

A.

Ask the team member to learn the new system as on-the-job training

B.

Issue a change request to extend the project schedule

C.

Escalate the team members performance to the project sponsor

D.

Assign an experienced resource to support the team member

Full Access
Question # 282

As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved

How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

Full Access
Question # 283

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

A.

Support the team member by removing the blockers and impediments.

B.

Allocate the blockers and impediments to the product owner to resolve.

C.

Insist that the person who raised the blockers and impediments take ownership.

D.

Add any blockers or impediments to the risk register,

Full Access
Question # 284

A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline

B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change

C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline

D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline

Full Access
Question # 285

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

A.

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

Full Access
Question # 286

A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.

In order to help the team, what should the project leader do?

A.

Recommend that the product owner reviews the backlog refinement processes.

B.

Recommend that the team reviews the length of the iteration with the stakeholders.

C.

Recommend limiting the work in progress to improve the team’s focus.

D.

Recommend a review of the team members’ individual performances.

Full Access
Question # 287

A company has transitioned and is now delivering projects using a hybrid approach

instead of a predictive approach. The distributed project team's knowledge of agile is varied.

The project manager feels this new methodology will impact the timely delivery of the project.

What should the project manager do?

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk.

B.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.

C.

Plan for training on agile tools and techniques used in the defined hybrid methodologyfor consistent application by all team members.

D.

Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.

Full Access
Question # 288

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

A.

Consult preferred vendors from the company.

B.

Perform research on experienced vendors in the market.

C.

Source vendors with extensive experience.

D.

Follow the company's standard vendor selection criteria process,

Full Access
Question # 289

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs

How should the project manager ensure the work continues smoothly?

A.

Postpone the required work on the project until school holidays begin

B.

Advise the school to close (or the duration of the project work

C.

Continue the work as planned and inform the school when the project team arrives on-site

D.

Liaise with the school to include nonworking project hours during school start and finish times

Full Access
Question # 290

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

A.

Review organizational process assets (OPAs) for clarity.

B.

Document lessons learned before closing.

C.

Consult the project charter for next steps.

D.

Confirm the definition of done (DoD) has been met.

Full Access
Question # 291

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

A.

Ask the leadership team for help obtaining the needed staff.

B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.

C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

D.

Check with human resources (HR) regarding the availability of staff.

Full Access
Question # 292

A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in

one of the project teams.

What should the project manager do?

A.

Apply a root-cause analysis on the data breaches.

B.

Ensure that all team members complete the training.

C.

Redesign the training courseware to make it interesting.

D.

Retrain the team members responsible for the breaches.

Full Access
Question # 293

A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.

What should the project manager do first?

A.

Accept the feature.

B.

Determine if the feature is within the scope.

C.

Submit a change request! for the feature.

D.

Reject the feature.

Full Access
Question # 294

During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?

A.

Review and update the project schedule according to performance

B.

Review the schedule baseline and consider adopting a schedule performance indicator

C.

Develop a lime. cost, and scope tracking method exclusively for this project.

D.

Adopt a formal change management process for the project

Full Access
Question # 295

During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?

A.

Ask the team to solve the issue internally and review the underperforming resource's situation

B.

Meet with the team member privately to discuss the problem and work together to find a solution

C.

Contact the functional manager and request to replace the team member with a better resource

D.

Discuss various options to improve the team member's performance with their functional managers

Full Access
Question # 296

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

A.

Meet with the manager to set a high priority for printing the materials

B.

Create a change request to modify the print requirements

C.

Include a risk response in the resource management plan

D.

Purchase a high-volume printer specifically for this project.

Full Access
Question # 297

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

A.

Assess the business value impact and review the product roadmap to include any changes

B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

Full Access
Question # 298

A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix

What should the project manager do with regard to community engagement in this situation''

A.

Include the local union representative in the high-power, high-impact stakeholder group

B.

Focus on the sideward stakeholders only and let the organization manage the community.

C.

Build channels to extend communication efforts to the local community

D.

Use the city administration to address communication with the community

Full Access
Question # 299

After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?

A.

Consult the risk and issue logs.

B.

Initiate a project change request.

C.

Create a baseline impact assessment

D.

Discuss with the project sponsor.

Full Access
Question # 300

A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution

phase and will affect a few key workers’ licenses, which will become noncompliant.

What should the project manager do?

A.

Start scheduling the training for key workers now to ensure compliance.

B.

Maintain the current key workers since the project has already started.

C.

Update the project charter to ensure the new legislation is addressed,

D.

Start a recruitment drive for new workers with the licenses required.

Full Access
Question # 301

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

A.

Meet with each team member separately and apply an appropriate approach with each one.

B.

Approach the project sponsor and request help in discussing the project deliverables with team members.

C.

Explain to the team that the project manager is ultimately responsible for the delivery.

D.

Assign multiple managers to the various teams and delegate all of the tasks to them.

Full Access
Question # 302

A quality Issue that requires a change to the quality standard Is encountered In a project Currently, there Is no budget available for the required changes. What should the project manager do?

A.

Check the change management plan

B.

Document the issue in the scope management plan.

C.

Conduct a team brainstorming session to resolve the issue

D.

Check the quality management plan

Full Access
Question # 303

What should an agile lead do lo ensure their team is set up for success?

A.

Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level

B.

Schedule sprint meetings and coaching sessions to discuss project-related information

C.

Plan quarterly informal meetings or team bonding sessions to encourage the team to work together

D.

Document team tasks and challenges in order to understand when to step in and help a member of the team

Full Access
Question # 304

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Full Access
Question # 305

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.

Use a single communication medium such as video teleconferencing to limit confusion.

C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.

Send frequent updates via email to each stakeholder because this is an information technology project.

Full Access
Question # 306

A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.

The project team will be virtual and will include members from different countries around the world.

What should the project manager do to ensure effective team building occurs?

A.

Coordinate with team members to define and communicate ways of working, roles and responsibilities, scheduling, time zone, and culturalobservance information.

B.

Explain to the team that since they are all SMEs and know one another, they are expected to immediately collaborate and deliver effectively.

C.

Update the communications management plan and determine an issue resolution process for when furture conflicts arise.

D.

Colocate the team members at the beginning of the project to explain the expectations for team interaction, meeting schedules, and overallproject governance.

Full Access
Question # 307

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Full Access
Question # 308

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

A.

Appoint a dedicated product manager for the duration of the release

B.

Have the customer approve the product increment features.

C.

Ensure every user story has acceptance criteria.

D.

Track business outcomes for planned user stories.

Full Access
Question # 309

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint

B.

Ask the team to address this at the next sprint planning instead of at the retrospective

C.

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance

D.

Work with the product owner to remove the story from the sprint because the points cannot be splits

Full Access
Question # 310

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is

on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.

What should the project manager do?

A.

Contact the design team manager and ask to reconsider the priority list based on the latest situation,

B.

Meet with the designer to share the current status and develop a solution to complete the task.

C.

Meet with the design team manager to inform them of the current status and request an additional designer.

D.

Ask the software engineer to move forward without completing the important feature.

Full Access
Question # 311

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

A.

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

Full Access
Question # 312

A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?

A.

Ask the provider to seek options to solve the issue

B.

Add the issue to the issue log and report it at the next review meeting

C.

Review the current plan and consolidate if necessary

D.

Schedule a meeting with the provider to collaborate on the options

Full Access
Question # 313

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

A.

Keep the project focused and executed in silos for better outcomes.

B.

Report the concern to the agile project management office (PMO),

C.

Inform the product owner of the concern so that i can be addressed.

D.

Open up to the team to work collaboratively to achieve the outcomes.

Full Access
Question # 314

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity

issues joining team calls during the day.

What should the project manager do?

A.

Procure tools that consume less bandwidth for internet calls.

B.

Record the meeting to share with the team members who were unable to join.

C.

Ask the team members to use chat tools as an alternative to calls.

D.

Determine what the problem is and develop an action plan.

Full Access
Question # 315

A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.

Full Access
Question # 316

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

Full Access
Question # 317

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?

A.

Explain to the stakeholder that any modifications require additional budget

B.

Review the missed program deliverables with the project team

C.

Review the project charter for the project approval criteria

D.

Speak with the team's manager to get extra hours from the team

Full Access
Question # 318

During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?

A.

Provide the new member with access to the knowledge database so all of the project documentation Is available.

B.

Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.

C.

Ask the new member to document all of the requirements so a better understanding of the project objective is acquired,

D.

Provide the new member with the project documentation repository to allow the new member to review previous lessons learned, Owner

Full Access
Question # 319

One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.

What should the project manager do?

A.

Create a risk probability matrix to address the incompatibility.

B.

identify an alternative component in case of incompatibility.

C.

Use the contingency fund to redesign the interface if it is incompatible,

D.

Require the vendor to redesign the incompatible component to fit the system.

Full Access
Question # 320

In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?

A.

Submit a change request to leverage previous experience and manage the project using a predictive approach,

B.

Schedule a daily project definition meeting with the team to define the project scope before starting the execution.

C.

Start executing the project as the scope will be defined and redefined throughout the project.

D.

Obtain partial approval from the product owner to baseline the project scope plan before starting the execution.

Full Access
Question # 321

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

A.

Ask the accounting manager to delegate a team member who can support the project.

B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,

C.

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,

D.

Begin discussions with other functional managers and meet with the accounting manager later.

Full Access
Question # 322

A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water

What caused this situation to occur?

A.

The risk analysis was inadequate

B.

The project was completed behind schedule

C.

The requirements gathering was inadequate

D.

The project was delivered above budget

Full Access
Question # 323

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

A.

Review the deliverable carefully and determine the right status

B.

Assign one person to be responsible for the task

C.

Establish a clear definition of done (DoD) for each task

D.

Encourage team members to work together

Full Access
Question # 324

A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.

What should the project manager do?

A.

Ask senior management to communicate with these departments.

B.

Hire a project management consultant to help resolve the issue

C.

Convince senior management to introduce rewards to resisting departments.

D.

Understand the user concerns and revisit the stakeholder engagement plan

Full Access
Question # 325

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Full Access
Question # 326

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project

What should the project manager do?

A.

Start planning the project and then request that a PMO be implemented in the organization

B.

Request that the implementation of a PMO be executed in parallel with the project

C.

Provide project management training to only the internal team involved m the project

D.

Provide project management training to the stakeholders and explain their responsibilities

Full Access
Question # 327

A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,

yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?

A.

Ask the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.

B.

Direct the team to implement the benefits management plan and track achievements before the end of the project.

C.

Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.

D.

Update the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.

Full Access
Question # 328

A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)

A.

Require a written status report from all team members on a weekly basis

B.

Form a core group of team leads representing members from each country and encourage them to collaborate

C.

Ask team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the day

D.

Establish virtual one-on-one's with team members to address any issues and/or concerns privately

Full Access
Question # 329

A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?

A.

Remove the learn member from the team and hue a more skilled one

B.

Ask the technical lead to provide more training to the team member

C.

Ask the technical lead to discuss performance directly with the team member

D.

Meet with the team member to understand the situation and provide feedback.

Full Access
Question # 330

Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.

What should the project manager do to engage the stakeholders?

A.

Ask the team to work on the complaint raised by the clients.

B.

Escalate the issue raised by the clients to the project sponsor,

C.

Develop a solution with the team to identify the inventory level.

D.

Work with the team and the product owner to define the next steps.

Full Access
Question # 331

we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?

A.

Discuss the issue with the team to resolve the disagreement.

B.

Ensure that there is consensus among the project stakeholders.

C.

Discuss the issue during the next sprint planning meeting.

D.

Support the outcome of the architects’ agreement.

Full Access
Question # 332

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

A.

Maintain a central repository of artifacts with a version control system.

B.

Maintain separate document control via regions to avoid discrepancies.

C.

Develop a document management software for version control.

D.

Facilitate training on version control and project artifacts,

Full Access
Question # 333

A large and complex program in an agile environment has experienced an increase in

escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.

What should be done to resolve this issue?

A.

Invite the client and product owner to all planning, review, and retrospective meetings.

B.

Accept the escalations and manage them so the working relationship with the client isnot impacted.

C.

Review and clarify roles, responsibilities, and the governance model at the next sprintreview meeting.

D.

Invite the product owner to attend all Scrum meetings and define the governance modeland escalation path.

Full Access
Question # 334

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project's change control board (CCB),

Full Access
Question # 335

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

A.

Review the project scope to align the project teams

B.

Review the resource management plan to align the project teams

C.

Review the project integration plan to align the project teams

D.

Review the work breakdown structure (WBS) to align the project teams

Full Access
Question # 336

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget

B.

Engaged with the project sponsor to ensure support for the project manager's decision

C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped

D.

Convinced the functional manager to stop the activities that will run beyond the budget

Full Access
Question # 337

A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?

A.

Tell the owner that a rough order of magnitude will be provided.

B.

Contact a subject matter expert (SME) for advice and consultation.

C.

Call a meeting with the project team to identify the most appropriate approach.

D.

Tell the owner that the task requires more time and expertise

Full Access
Question # 338

During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables

How should the project manager mitigate this risk without compromising the completion date?

A.

Review the integrated change control process to restrict the number of changes

B.

Focus on delivering incremental value through multiple smaller deliveries

C.

Request sponsor support to get buy-in from the users and stakeholders

D.

Restart the stakeholder engagement process by collecting user requirements again

Full Access
Question # 339

A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time

What should the project manager do next?

A.

Record the issue then refocus the team's efforts on delivering the next set of deliverables

B.

Give the team member a formal warning for the negative impact due to failure to delrver and not meet deadlines

C.

Hold a team meeting to discuss team member commitments and communications

D.

Meet with the team member and work on a development plan for them to avoid missed deliverables in the future

Full Access
Question # 340

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

A.

Discuss the vacation plan and include scheduling changes in the change log database.

B.

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.

C.

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.

D.

Push out the project timeline according to the vacation plan in place based on the recent company policy.

Full Access
Question # 341

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

A.

Reviewed the project management plan

B.

Created a detailed operations manual

C.

Increased support hours for the hours of operation

D.

Involved operations stakeholders during planning

Full Access
Question # 342

A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.

What should the project manager have done*?

A.

Confirmed that the communication was understood and solicited feedback from the team

B.

Sent the roles and responsibilities matrix along with the project management plan

C.

Discussed the roles with the managers to help explain them to their team members

D.

Briefed each team member on their roles before sending the project management plan

Full Access
Question # 343

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?

A.

Schedule a training course for the new team member to fill in their gaps in experience.

B.

Log this as an issue in the project issue log and speak with the resource manager.

C.

Provide weekly feedback to all project team members, including the new member.

D.

Ensure that coaching meetings are in place for this team member within the project timeline.

Full Access
Question # 344

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned

Full Access
Question # 345

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

A.

Establish the project scope and set clear team objectives

B.

Set performance standards and direction

C.

Hold early kick-off meetings and regular weekly meetings

D.

Select members for their skill or potential

Full Access
Question # 346

After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?

A.

Develop the team members to work as a cross-functional team.

B.

Ask a functional manager to provide the right team members.

C.

Review the project charter to see if the scope can be modified.

D.

Ask the portfolio manager to reassign the project to another team.

Full Access
Question # 347

A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.

What should the project manager do next?

A.

Evaluate demonstrated task accountability

B.

Determine the appropriate approach

C.

Analyze team member influence

D.

Identify levels of decision-making authority

Full Access
Question # 348

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

A.

Update the scope management plan to track the new government requirements.

B.

Accept the cybersecurity team’s request as the security of the company is at risk ofbeing noncompliant.

C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.

Request a change through the change control process to manage the new cybersecurityrequirements.

Full Access
Question # 349

A government procurement team has been running a vendor selection process for more than 1 year, going beyond the originally planned 6 months due to a variety of factors. Two vendors have submitted proposals that were evaluated. The project manager asked for an estimated completion date 4 weeks ago, but it was not provided.

What should the project manager do?

A.

Work with the procurement team to build a high-level timeline.

B.

Explain to the steering committee that vendor negotiations are unpredictable.

C.

Ask the project sponsor to request an estimate from the procurement team.

D.

Escalate the delay issue to the project steering committee.

Full Access
Question # 350

After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company's newest offering. The project manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. The project manager fears that the competitor's offering is better in multiple ways compared to the project manager's project.

What should the project manager do?

A.

Perform a Kano analysis factoring in the competitor's offering and present it to the stakeholders.

B.

Meet with the development team to see what changes will improve the project compared to the competition's deliverable.

C.

Meet with the project team to discuss the concerns and determine how to ensure the project's deliverable can compete with the competitor's.

D.

Note this concern in the risk register and meet with the sales team to identify mitigation options factoring in the competitor's offerings.

Full Access
Question # 351

In the past year, a company paid US$60,000 to an external subcontractor for an ongoing project. The project manager has been asked to

evaluate if the project can be delivered more cost effectively this year by using internal labor. The project manager used an optimistic term of 4

months, a pessimistic term of 6 months, and a most expected term of 5 months, and has concluded that the service can be delivered with the

following resources:

* Two engineers (monthly salary of US$700 each)

* One project manager (monthly salary of US$1,600)

* Additional estimated monthly expenses of US$2,000

The project manager used the program evaluation and review technique (PERT) to calculate the savings if the project is delivered with in-house

resources.

How much money will the project manager estimate the company can save?

A.

US$35,000

B.

US$20,000

C.

US$40,000

D.

US$30,000

Full Access
Question # 352

A few developers have identified a list of impediments at the daily standup and are asking for the project lead's assistance in prioritizing them. There are a few complex backlog items, and a new junior tester has identified a few compliance defects. The product owner and a couple of developers will be leaving the project team, and the contract with the test and production support partner will not be renewed.

Which issue should the project lead focus on first?

A.

Developing a new contract for production support.

B.

Finding a new product owner to prioritize the product backlog.

C.

Regulatory compliance issues discussed in the meeting.

D.

Recruiting, onboarding, and training new developers.

Full Access
Question # 353

A project manager has expertise in the technical domain. The project manager frequently demonstrates unacceptable behavior toward other team

members; however, when confronted, the project manager denies this behavior.

What is the reason for the project manager's behavior?

A.

The project manager lacks necessary empathy.

B.

The project manager lacks emotional intelligence (El).

C.

The project manager was not properly trained.

D.

The project manager is in the wrong project role.

Full Access
Question # 354

A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.

What should the project manager do?

A.

Explain to the team that open discussions are needed but remind the team to follow the ground rules.

B.

Ask this member to only discuss the current topic to achieve team efficiency.

C.

Ask the team to accept the input from this particular member as their input may be useful.

D.

Allow the self-organized team to discuss the situation among themselves and come to a resolution.

Full Access
Question # 355

In a project, one team member has been asking for directions and what actions to take on many tasks. As a result, the team member has performed slowly in project delivery.

What should the project manager do to help this team member?

A.

Assign another senior team member to coach the team member.

B.

Empower the team member to make decisions.

C.

Mentor the team member on a regular basis.

D.

Address the team member's performance accordingly.

Full Access
Question # 356

An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project

execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.

What should the project manager have done to prevent this from happening?

A.

Ensured the stakeholder anticipated obstacles to achieving financial closure on the remaining funds.

B.

Ensured the risk was adequately assessed and mitigated by the appropriate stakeholders.

C.

Ensured the stakeholder who was providing additional funds remained interested in the project.

D.

Ensured the project team monitored and reviewed the project risk register periodically.

Full Access
Question # 357

An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and followup calls with key stakeholders. The team seems to be disengaged.

How should the project manager approach this situation?

A.

Give the team members a few days off to reduce stress.

B.

Reduce the number of internal and external meetings.

C.

Review team assignments and reduce the workload.

D.

Schedule one-to-one meetings and team-building meetings.

Full Access
Question # 358

A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.

What should the project manager do next?

A.

Perform stakeholder engagement.

B.

Perform integrated change control.

C.

Update the quality management plan.

D.

Update the risk management plan.

Full Access
Question # 359

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the

equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

A.

Defined the skill requirements more clearly in the scope statement.

B.

Asked the manager to follow the agreed-upon resource management plan.

C.

Conducted periodic reviews with the manager on resource availability.

D.

Consulted with the installation team on a regular basis to check for conflicts.

Full Access
Question # 360

A project manager is managing a mobile application development project when one of the experienced team members starts missing deadlines. The delays will impact

project implementation.

What should the project manager do next?

A.

Meet with the team member to understand their concerns and/or issues.

B.

Convene a team meeting to encourage and motivate the entire team.

C.

Assign an additional resource to help the team member with the tasks.

D.

Ask the team member's functional manager if there are any known issues.

Full Access
Question # 361

A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of

sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.

What should the project manager do?

A.

Introduce a float.

B.

Adjust the budget.

C.

Adjust the project time line.

D.

Fast track the project.

Full Access
Question # 362

A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the different requirements?

A.

Include only the common requirements of each stakeholder group in the project goals.

B.

Include only the key requirements and keep the stakeholders informed about scope decisions.

C.

Analyze the interests and influence of stakeholders and evaluate their requirements.

D.

Add only the opinions of the team, because they know the objectives of the project.

Full Access
Question # 363

A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?

A.

Follow the requirements management process.

B.

Follow the stakeholder engagement process.

C.

Follow the risk management process.

D.

Follow the change management process.

Full Access
Question # 364

A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress

(WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.

What should the project manager have done to avoid this situation?

A.

Stored project documentation in a shared folder.

B.

Organized monthly meetings with the external stakeholders.

C.

Invited all of the stakeholders to daily standup meetings.

D.

Sent weekly status update reports to all of the stakeholders.

Full Access
Question # 365

A project manager is leading a project that needs to be deployed quickly to the market. An influential stakeholder does not believe that the project management processes bring business value.

What can the project manager do to gain the support of the stakeholder?

A.

Ask the stakeholder for a meeting to review the project's charter and project management plan.

B.

Disregard the stakeholder's concerns and continue following the project management plan to execute the project.

C.

Hold a training workshop to educate the stakeholder about project management best practices.

D.

Clarify the project roles and responsibilities, and share the purpose to gain the stakeholder's buy-in.

Full Access
Question # 366

A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.

How should the project manager communicate with the local community?

A.

Social media

B.

Email

C.

Meetings

D.

Newspapers

Full Access
Question # 367

All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day.

What should the project manager do to prevent these delays?

A.

Review the Pareto diagram to identify the source of delays.

B.

Meet with the team in 2 weeks to respond to all of the open tasks.

C.

Consolidate the decision-making authority to remain with the project manager.

D.

Delegate the decision-making authority of some tasks to the team.

Full Access
Question # 368

A project manager is preparing a budget estimation for an international construction project. They decide to consult the project team members who are experienced in this type of project and are familiar with the local laws of the country.

Which budgeting approach would be the least risky for the project team to apply?

A.

Review historical data and provide parametric estimations for the activities, including local law restrictions.

B.

Use a top-down estimation and add contingencies to cover any future impacts regarding the legal context.

C.

Make a general estimation using a standard legal approach and then look to include early definitions.

D.

Discuss and compile the local information about laws to develop bottom-up estimations.

Full Access
Question # 369

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?

A.

Risk to delivery

B.

Technical complexity

C.

Business value

D.

Estimation accuracy

Full Access
Question # 370

A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?

A.

Gather a reduced number of approved requirements and add some extra features to fulfill the product specifications.

B.

Ask team members to research and collect data about the best features offered by similar products in the market.

C.

Stop all project activities until all requirements are set up front by the project sponsor and the key stakeholders.

D.

Gather enough requirements to produce a minimum viable product (MVP) with which to evaluate customer acceptance.

Full Access
Question # 371

The key stakeholders of a project would like to be actively involved in the review of product increments.

What should the project manager do?

A.

Analyze their interest and influence to manage expectations.

B.

Update the communications management plan for key stakeholders.

C.

Identify the needs and expectations of key stakeholders.

D.

Encourage their participation in release and sprint reviews.

Full Access
Question # 372

During execution of a complex project, the project manager encounters numerous change requests from various teams. These changes may result in the project not meeting its objectives.

How should the project manager ensure that these changes are managed effectively?

A.

Include the changes in the backlog and review priorities with the product owner.

B.

Record the changes using the risk register and continue monitoring.

C.

Deny the change requests and keep delivering the project as planned.

D.

Review the project and communications management plan with the main stakeholder.

Full Access
Question # 373

A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met.

What should the project manager do?

A.

Refer to the requirements traceability matrix and analyze the requirement.

B.

Analyze the benefits management plan and implement the needed change.

C.

Consult the scope management plan with the customer to understand the gap.

D.

Discuss and agree with the customer to implement the missing requirement.

Full Access
Question # 374

A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignments from multiple people and states they are not able to work effectively.

What should the project manager establish first in the project governance structure?

A.

Clear responsible, accountable, consult, and inform (RACI) matrix

B.

Risk management and issues resolution plan

C.

Resource management and conflict resolution plan

D.

Clear project work breakdown structure (WBS) and timeline

Full Access
Question # 375

A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is

identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact

on the project outcomes.

What should the project manager do next?

A.

Determine the impact of the risk and prioritize outcomes that do not affect the tax module.

B.

Delay developing the indirect tax module until the tax regulation comes into effect.

C.

Assess the impact of the risk with an expert and prioritize further outcomes with the client.

D.

Analyze the impact of the risk and discuss with the team to determine how to separate the tax module.

Full Access
Question # 376

A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What should the project manager review next?

A.

Quality process

B.

Quality management plan

C.

Organizational process assets (OPAs)

D.

Project charter

Full Access
Question # 377

A project manager is working on a unique project that is dissimilar to the project nature of the organization. The project manager is tailoring the artifacts for this new project.

Who should determine which artifacts should be used in the project?

A.

The project sponsor should select the project artifacts that the project manager and project management team should use in the project.

B.

The project manager and project management team should use the standard project artifacts from the database.

C.

The project stakeholders should meet and determine the project artifacts to be used by the project manager and the project management team.

D.

The project manager and the project management team should select the appropriate artifacts for use in the specific project.

Full Access
Question # 378

Eight highly qualified experts have been assembled to work for a 6-month period on an a specific aspect of an organization's product development process. How should the

project manager support this team to succeed?

A.

Hand over control of specific aspects of their roles as experts and let them agree on their own timelines and targets.

B.

Bring in a senior colleague who is also an expert to ensure the team is on track to achieve the goals and objectives.

C.

Define roles and targets for all team members and regularly follow up with one-to-one meetings to review progress.

D.

Work with the team members to define the overall objective and support them to engage around the goal.

Full Access
Question # 379

A company just started managing a project using an agile approach Due to this change, the general manager is worried about the scope definition process for upcoming projects What should the project manager do to ensure the project scope is completely defined?

A.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

B.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk

C.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

D.

Ask the general manager to review every requirement to ensure an projects will deliver the requested products

Full Access
Question # 380

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?

A.

Negotiate a contract change with the subcontractor.

B.

Meet with the client to discuss the issue with the subcontractor.

C.

Inform the subcontractor that they must send the schedule.

D.

Tell the subcontractor to submit a draft schedule.

Full Access
Question # 381

After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.

What should the project manager do?

A.

Make arrangements for the stakeholder to join the kick-off meeting virtually.

B.

Hold the kick-off meeting with the rest of the stakeholders to avoid a delay in the project.

C.

Change the kick-off meeting to a virtual meeting so all can attend at the same time.

D.

Reschedule the kick-off meeting for the following month so all can attend on-site.

Full Access
Question # 382

A project manager is leading a hybrid project and is collaborating with the client to develop the project contract.

Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.

What should the project manager do first?

A.

Study the contract terms and deadlines to ensure they are not under risk and confirm them with the stakeholder.

B.

Clarify the current work progress, causes for delays, existing risks, and planned corrective actions.

C.

Submit a request for extra time and budget related to the dependencies and technical difficulties.

D.

Ask the stakeholder to remain calm and confirm that they are participating in all team meetings.

Full Access
Question # 383

An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started

working at the company. In the first meeting with the project manager, the director demands a weekly project status report.

What should the project manager do?

A.

Invite the director to attend the daily standup meetings.

B.

Share this with the team and ask them to develop reports for the director.

C.

Introduce the agile aspect to the director and agree on a solution.

D.

Explain to the director that agile projects have live reports.

Full Access
Question # 384

A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more What should the project manager do next?

information to be shared.

A.

Inform the stakeholder to wait for the annual stakeholder review meeting

B.

Schedule a meeting with the stakeholder to better understand their request

C.

Update the project communications management plan immediately

D.

Consult the scope baseline document to track project updates

Full Access
Question # 385

A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in

innovative ways without any need for encouragement. However, the engineer declines the project manager's invitation to join the new project.

What is the most likely reason for the engineer's refusal to work on the project?

A.

The engineer did not feel welcome or enjoy working with the other project team members.

B.

The project manager did not follow the normal hiring process with the engineer's functional manager.

C.

The engineer has “project burnout" from working long hours and solving difficult problems.

D.

The project manager did not sufficiently support and recognize the engineer's professional growth.

Full Access
Question # 386

A project manager has been assigned to a project after the charter has been approved. While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.

What should the project manager do next?

A.

Reduce the quality and cost of other deliverables to allow additional budget for the items that were missed.

B.

Start the project and deal with these budget issues as they arise throughout the project life cycle.

C.

Add the missing budget items to the risk log and present them in the next project steering committee.

D.

Immediately discuss this with the project sponsor and request to revisit the budget to ensure its accuracy.

Full Access
Question # 387

A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule.

What should the project manager do next?

A.

Validate the information and update the risk management plan.

B.

Update the risk register and discuss it with the project stakeholders. b

C.

Source second-hand equipment in order to prepare for any delivery delays.

D.

Update the sponsor of the potential issue and ask for any suggestions.

Full Access
Question # 388

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

A.

Develop a more comprehensive template for the definition of done (DoD).

B.

Increase the percentage allocated for testing each backlog item.

C.

Organize more frequent sprint reviews with a broader audience.

D.

Establish a quality assurance (QA) team separate from the development team.

Full Access
Question # 389

A typically high-performing team member has started to demonstrate a performance drop as well as some aggressive behaviors toward other team members in meetings.

The project manager has worked with this individual for many months on this project and has not seen this type of behavior before.

What should the project manager do?

A.

Discuss the project manager's observations with the individual to determine why they are behaving this way.

B.

Discuss the individual's behavior with the other team members to determine if they have noticed and know what is going on.

C.

Attend more team meetings to observe the team more closely to determine the root cause.

D.

Discuss their performance with the team member's functional manager as well as human resources (HR) and discuss next steps.

Full Access
Question # 390

A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.

What should the project lead do?

A.

Invite the board member to the next daily standup.

B.

Invite the board member to the next sprint retrospective.

C.

Invite the board member to a separate demo.

D.

Invite the board member to the next sprint review.

Full Access
Question # 391

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.

What should the project manager have done to prevent this?

A.

Requested robust documentation for the component's build.

B.

Outsourced development of the specific component to another team.

C.

Acquired more than one resource skilled in each component.

D.

Facilitated cross-functional knowledge transfer during the project.

Full Access
Question # 392

A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility,

Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.

What should the project manager do next?

A.

Perform a cost-benefit analysis to evaluate using the Point B option.

B.

Add the issue to the change log and request additional budget through the change control board (CCB).

C.

Seek a decision from the construction team after explaining the project budget and schedule constraint.

D.

Use the Point B option because it will save the project cost and time.

Full Access
Question # 393

A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk.

The sponsor forwarded the email to the project manager asking for further details. After speaking with the sponsor, the project manager decided to take preventive action.

Which document should the project manager review with their team?

A.

Risk management plan

B.

Quality management plan

C.

Communications management plan

D.

Procurement management plan

Full Access
Question # 394

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.

What should the project manager do?

A.

Assess the schedule impact and evaluate the most feasible solution to keep the project on track.

B.

Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.

C.

Initiate regular conference calls with the vendor for status updates to keep this item in focus.

D.

Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.

Full Access
Question # 395

After a recent status review meeting, the project manager becomes aware that an influential stakeholder is unclear about the purpose and benefits of the project Consequently, the stakeholder has questioned the viability of continuing the project What should the project manager do next to address the situation?

A.

Speak with the project sponsor to find out if the stakeholder would agree to a one-on-one review session

B.

Log the stakeholder's comments in the risk register as a high-impact threat to the project's completion

C.

Consider the stakeholder's concerns and review the project charter with the project sponsor.

D.

Note the stakeholder's concerns but disregard them with regard to the project activities.

Full Access
Question # 396

A website application project is underway and the agile team has reached a stable velocity. After eight iterations, they complete 20 story points per sprint. The project lead and team plan to maintain the same velocity for the next 2 months. After this period, the team completed 100 story points. The project sponsor asks for the project status.

How should the project lead respond?

A.

The cost performance index (CPI) is below average with a 25% reduction.

B.

The schedule performance index (SPI) is 25% less than expected.

C.

The team's performance indicator is higher than expected.

D.

The cost and schedule performance indicators are equivalent.

Full Access
Question # 397

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

A.

Reject the changes as the lead time is too short.

B.

Determine whether the project team is capable of making the changes.

C.

Review the additional changes and perform integrated change control.

D.

Check if the changes are covered in the statement of work (SOW).

Full Access
Question # 398

An agile team is geographically separated across multiple continents, and the project manager is in the process of identifying the tools to manage the communication among the virtual teams. Drag the appropriate tool on the left to each project task on the right.

Full Access
Question # 399

A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings

among team members. The project sponsor has allocated a monetary award.

How should the project manager utilize the award?

A.

Meet with the team members and ask them how to spend the reward.

B.

Arrange a luncheon for all team members and include team-building sessions.

C.

Draft a points system to allocate a portion of the money for each resource.

D.

Allocate the reward to the team leaders to spend on the team as they see fit.

Full Access
Question # 400

A consultancy firm is finally selected and contracted for a project following an extensive and competitive procurement process. A few months into project execution, the client asks the project manager why the consultant is contracted for only 18 months instead of the full 32-month-long project. The project manager will need to carry out an unplanned second bidding process to ensure services are in place until the end of the project.

What should the project manager have done to prevent this?

A.

Developed a detailed, phased procurement management plan including all activities required and had the client approve it.

B.

Included the client in all negotiation phases with the consultancy to obtain their advanced approval before signing the contract.

C.

Prepared and negotiated a second contract with the consultancy firm for the remaining 14 months after the first contract signature.

D.

Agreed beforehand with the client on the frequency of reporting on the status of the procurement activities within the project.

Full Access
Question # 401

A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change

in project scope.

How should the project manager respond to this requirement?

A.

Proceed with the existing company governance policy.

B.

Perform an analysis to assess the impact on the project.

C.

Directly comply with the financial regulations.

D.

Escalate the issue to upper management and let them decide.

Full Access
Question # 402

A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.

Which measure should mitigate the impact of this key resource's departure?

A.

Offer a new contract to the resource who is leaving.

B.

Establish a proactive knowledge-sharing plan.

C.

Update the risk register and inform the customer.

D.

Develop a contingency budget to replace the key resource.

Full Access
Question # 403

A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.

What should the project manager have done to avoid this setback?

A.

Assessed feasibility and impacts

B.

Developed benchmarking

C.

Analyzed stakeholders

D.

Detailed the project charter

Full Access
Question # 404

During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and infrastructure dependencies to deliver the expected value.

How should the project manager handle this issue?

A.

Support the project sponsor so the decision is made top-down and the team follows the provided direction.

B.

Support a voting exercise so all team members can express their opinion and the reason behind their vote.

C.

Support the product owner so only items with high business value are included in the next sprint.

D.

Support the project team so technical debt and infrastructure dependencies are included in the next sprint.

Full Access
Question # 405

A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.

What should the project manager do next?

A.

Discuss the issue with the team member in a one-on-one meeting.

B.

Ask the team member to justify the delay during a team meeting.

C.

Review the human resources (HR) policies for relevant corrective actions.

D.

Escalate the performance issue to the team member's functional manager.

Full Access
Question # 406

A project is starting its second iteration out of six. During the daily meeting, a team member asks for help. In order to finish a deliverable, an

approval from the design department will be needed.

What should the project manager do?

A.

Meet with the design manager to ask for the necessary approval.

B.

Invite a design team member to the next daily meeting.

C.

Update the issue log and escalate it to the project sponsor.

D.

Replace this iteration deliverable for one without any blockers.

Full Access
Question # 407

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?

A.

Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.

B.

Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.

C.

Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.

D.

Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.

Full Access
Question # 408

A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.

What should the project manager do?

A.

Define a risk management plan (or the new approach, as needed.

B.

Review the benefits realization plan to include the cost of the change.

C.

Define a project management plan for the new approach, as needed.

D.

Review the communications management plan to identity new stakeholders.

Full Access
Question # 409

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

A.

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

Full Access
Question # 410

A project manager is working on an enterprise resource planning (ERP) initiative that contains stakeholders spanning numerous business lines. The project manager begins

to identify, evaluate, and categorize the stakeholder relationships to the program.

What is the purpose of this process?

A.

Identify all stakeholders who can negatively affect the project.

B.

Incorporate the needs of all stakeholders into the communications management plan.

C.

Incorporate only primary stakeholders into the communications management plan.

D.

Identify all stakeholders who can positively affect the project.

Full Access
Question # 411

An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).

What should the project lead do?

A.

Facilitate the meeting so anyone can share their ideas and is heard during the session.

B.

Allow the team to self-organize so one of the resources can lead the team to achieve consensus.

C.

Discuss the product owner's recommendations with the team and implement the agreed-on solutions.

D.

Discuss the recommendations with the test manager and request better quality control.

Full Access
Question # 412

A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half-yearly review of the project, the project manager raises serious concerns with

the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.

What should the project manager do?

A.

Propose to close the project because it no longer fits the business values of the organization.

B.

Calculate earned value (EV) because the project manager is forecasting a loss for this project in the yearly review.

C.

Calculate float on the project because it has severely affected the project's major critical path.

D.

Request additional resources from the business unit manager due to the project's complexity.

Full Access
Question # 413

A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

A.

Ask the sponsor to increase the budget and schedule of the project to accommodate the additional scope.

B.

Encourage the sponsor to start another project for the additional location so that the current project is not impacted.

C.

Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project.

D.

Discuss with the sponsor that the project scope is approved and it is not possible to include two locations as it will affect the budget.

Full Access
Question # 414

A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration.

What should the project manager do to lead the project?

A.

Use a servant leader approach.

B.

Assume the functional manager role.

C.

Perform the project sponsor activities.

D.

Act as the project owner.

Full Access
Question # 415

During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal

impact on project resources. However, the client has only been focused on the next milestone.

How should the project manager approach this situation?

A.

Apply additional resources to realize the early deliverable and ensure the next milestone is achieved.

B.

Focus on the deliverable of the next project milestone as per the client's strict instructions.

C.

Review the change management plan to discuss early benefits realization with the client.

D.

Evaluate whether the client's request will add extra features to the project deliverable.

Full Access
Question # 416

A large, multinational organization is reevaluating its policy on project management approaches. Team members are complaining about having different processes for each project they are on. Currently, predictive, agile, and hybrid methodologies are being used. A project manager is now part of a team working on standard criteria for approach selection for new projects.

What should the project manager recommend?

A.

Identify the most commonly used methodology currently and apply that to all future projects.

B.

Determine the types of projects, constraints, and resources to initiate standard tailoring.

C.

Incorporate both structure and flexibility through custom tailoring for all projects.

D.

Simplify the approaches to use either a single agile or a single predictive methodology.

Full Access
Question # 417

A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team

member's deliverables do not meet the requirements.

What should the project manager do first?

A.

Assemble the project team via conference call to tell them that disciplinary action will be taken if any more noncompliant deliverables aresubmitted.

B.

Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.

C.

Schedule time with the project sponsor to inform them that the project schedule is slipping due to the time it will take to rework thedeliverables.

D.

Meet with the project team to explain that noncompliant deliverables must be reworked and submitted immediately to avoid project delays.

Full Access
Question # 418

A senior vice president requested the creation of more agile teams to run projects of varying lengths and complexities in parallel with each other.

This will impact the amount of time the project managers will be able to dedicate to each project. The project managers typically dedicate 50% of

their time to projects regardless of their complexity.

What should the project manager do as a servant leader to help achieve this transformation?

A.

Review the organizational process assets (OPAs) to evaluate mitigation plans for similar risks.

B.

Create a risk entry regarding the project manager's capacity and develop a mitigation plan.

C.

Empower the team to develop the necessary skills to move the project forward independently.

D.

Issue a change request to hire additional project managers based on the increased workload.

Full Access
Question # 419

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

A.

Adapt the resource management plan and ask for financial approval before sending it to the customer.

B.

Assess the impact of the change and review the project management plan for next steps.

C.

Ask the financial manager to delay implementation due to potential project delays and penalties.

D.

Review the project schedule to determine which technique will reduce impact on project duration.

Full Access
Question # 420

After conducting a performance assessment, the project manager identified that some gaps still exist. What should the project manager ensure?

A.

Assessment results are kept private and not shared among team members.

B.

Performance improvement programs are organized for all team members who were assessed.

C.

All team members rotate their job schedules immediately to make them versatile.

D.

Awards are given to all team members for playing a role in the project and undertaking the assessment.

Full Access
Question # 421

A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor's developer has been reporting the same status for

several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company.

What should the project manager do next?

A.

Update the risk register to reflect the delay, communicate the impact to the schedule, and escalate to management for assistance.

B.

Conduct a project review with the project sponsor to explain the delay and add a developer to work with the vendor.

C.

Review the contract with the vendor to go over the financial penalty that is applicable to this situation.

D.

Add the delay to the issue log and work with the vendor for a resolution that will bring the schedule back on track.

Full Access
Question # 422

A global program is being kicked off, and various distributed teams are involved in delivering the initiative. Besides planning and executing the scope for the initiative, team

interactions must be considered.

How should the project teams interact in their meetings?

A.

Phone conversations

B.

Video conferencing

C.

Encrypted emails

D.

Chat conversations

Full Access
Question # 423

A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.

What should the project manager do to improve the situation?

A.

Ask the team members to tolerate the cultural differences as they have a different cultural background.

B.

Ask the construction manager to meet with the two team members to resolve the situation.

C.

Provide the construction manager with instructions on how to resolve the situation.

D.

Discuss the team members' concern with the construction manager and seek solutions.

Full Access
Question # 424

At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried

to contact the consultant but has been told that the consultant does not have the time to discuss the project.

What should the project manager do to move the project forward?

A.

Escalate the issues about the consultant to the functional manager so the consultant dedicates the necessary time to the project.

B.

Include a new project risk into the risk register and allocate the consultant as the risk owner as it is their responsibility to provide input.

C.

Discuss the request with the consultant and set up time with the business analyst and consultant to discuss the project requirements.

D.

Urge the business analyst to continue contacting the consultant to discuss the project since this is the responsibility of the business analyst.

Full Access
Question # 425

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?

A.

By scheduling iterative meetings with the product owner to improve project tracking

B.

By focusing on the delivery of incremental working products lo the customer

C.

By reviewing burnup charts to determine the effort required against estimated earned value

D.

By conducting daily standups to more accurately track project deliverables

Full Access
Question # 426

A senior manager attends one of the project review meetings and expresses concern that the project will not meet the quality standards. What should the project manager do?

A.

Estimate the backlog items to forecast quality.

B.

Ask the senior manager to approve the user acceptance testing (UAT) plan.

C.

Review the quality management plan with the senior manager.

D.

Inform the senior manager that there are approved quality standards.

Full Access
Question # 427

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are

being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting

market requirements.

What should the project manager do?

A.

Continue the iteration and add the requested changes.

B.

Continue the iteration and review the change with the customer.

C.

Cancel the iteration and meet with the product owner.

D.

Cancel the iteration and add the requested changes.

Full Access
Question # 428

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

A.

Ask the project team to review and modify all of these reports.

B.

Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.

C.

Explain to the stakeholder that these are the approved templates for the reports.

D.

Ensure that the reports comply with the communications management plan.

Full Access
Question # 429

A project is about to start with a global project team. Travel is not a viable option for project team members, so most will participate virtually.

What should the project manager do to engage the team?

A.

Have one-on-one meetings with team members to improve communication.

B.

Ask human resources (HR) for team-building recommendations.

C.

Schedule weekly team meetings to encourage collaboration.

D.

Invest in a virtual collaboration/colocation environment.

Full Access
Question # 430

A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict

schedule and budget, and the project manager is concerned about their ability to deliver it.

What should the project manager do?

A.

Request a budget extension to get local resources experienced in agile.

B.

Plan to have the agile resources temporarily relocate to the project manager's location.

C.

Engage the agile resources through video conferencing on a daily basis.

D.

Advise the sponsor that the project will be delayed as agile training will be required.

Full Access
Question # 431

An organization is initiating a project that will be using new technology. The complexity of the project requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor asks for options to reduce the labor cost without introducing risk to the project delivery.

What should the project manager do first?

A.

Review the risk register and assign functional managers as resources.

B.

Analyze the resource pool and assign internal resources who participated in past projects.

C.

Perform an analysis of the key cost drivers and present alternatives.

D.

Review the work breakdown structure (WBS) to ensure there are adequate resources.

Full Access
Question # 432

A project manager is assigned to a multiyear project. During project execution, the customer delegates a new representative who contacts the project manager directly with a concern about their participation in status meetings. The representative wants to contact team members directly.

What should the project manager do next?

A.

Send the new representative the approved project management and communications management plans.

B.

Reach out to the customer directly for assistance in incorporating the new representative into the project management plan.

C.

Meet with the project sponsor to discuss how to incorporate the new representative in the project.

D.

Meet with the new representative to determine their understanding of the project and address their concerns.

Full Access
Question # 433

A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.

What should the project manager do next?

A.

Agree with the project team to modify and delete some of the stories in the current sprint backlog

B.

Obtain approval from the project team and add the new story to the product backlog

C.

Receive an agreement from the product owner and add the new story to the product backlog

D.

Negotiate with the scrum master before adding the new story to the sprint backlog

Full Access
Question # 434

A project manager is assigned to a project where a vendor has been engaged to build a new system One week before user acceptance testing (UAT) is scheduled the vendor informs the project manager that they can only deliver half of the promised functions by the UAT start date.

What should the project manager do next?

A.

Wait until the vendor cannot deliver and then invoke liquidated damages based on the contract

B.

Escalate to management and prepare tor project closure by canceling the contract with this vendor

C.

Adjust the protect schedule to accommodate the current development progress of the vendor

D.

Communicate with the vendor and project team and explore possibilities lor resolving the issue

Full Access
Question # 435

A senior project manager has included a junior project manager as part of the project team. During a coaching session, the junior project manager

asks the senior project manager how to be efficient and reduce rework.

How should the senior project manager respond?

A.

Use a work breakdown structure (WBS) to create a project schedule based on the project and resource requirements.

B.

Monitor resource allocation to ensure that team members work 8 hours per day.

C.

Assign project tasks to the team regardless of their skills to accomplish the project schedule.

D.

Schedule daily meetings with key stakeholders to assess the effectiveness of the project management plan.

Full Access
Question # 436

In the initiating phase of a project, the project manager and team members are prioritizing the product backlog along with the product owner. What should the project

manager do next?

A.

Produce a value-added product for the customer as continuously as possible.

B.

Produce a value-added product for the customer in the beginning of the project.

C.

Produce a value-added product along with the supporting documentation.

D.

Produce a value-added product for the customer in each phase of the project.

Full Access
Question # 437

A project is continuously overlapping phases. Due to a recent human error, the team, which is made up of senior members, is experiencing distrust issues from other departments and lacking initiative. This is impacting overall performance and putting the project objectives at risk.

What should the project manager do when executing the next sprint?

A.

Coach those responsible for the error so that the whole team understands they are not responsible for it.

B.

Explain high-level objectives and ask team members to self-organize around their tasks to meet the objectives.

C.

Request offsite team-building activities and deploy incentive plans around their tasks.

D.

Identify the poor performers and ask their functional managers to assign them a mentor.

Full Access
Question # 438

Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.

What should the project manager do to obtain approval of the project budget?

A.

Provide the decision executive with all of the project details and request budget approval from the appropriate person.

B.

Identify the right person with help from local management, present the project summary, and request budget approval.

C.

Approach each of the referred individuals separately and request approval of the project budget from the appropriate person.

D.

Obtain the latest organizational chart and send an email to the appropriate person requesting budget approval.

Full Access
Question # 439

Early on during a sprint in an agile project, the project team begins deliberating two different approaches to implement a feature. The project manager is concerned that the team is spending too much time discussing this feature, because the team needs to cover other features in the sprint as well.

How should the project manager approach the situation?

A.

Intervene in the deliberation process and weigh in on which approach would be better to use.

B.

Deliberate with the team moving the item to the product backlog and taking up the next item in the list.

C.

Stop the deliberation process and ask the team to take a vote using the nominal group technique.

D.

Allow the team to continue deliberating until the team reaches a consensus on the desired approach.

Full Access
Question # 440

A project was recently flagged as being noncompliant during an inspection. Several options were suggested on how to address the noncompliance, but each may have different impacts on the budget, schedule, and quality.

How should the project manager proceed?

A.

Review the risk register.

B.

Perform a cost-benefit analysis.

C.

Determine the cost of change.

D.

Conduct a root cause analysis (RCA).

Full Access
Question # 441

An agile team is funded for a fixed 6-month period. The sponsor's request will take at least 12 months to complete.

What should the project manager do?

A.

Inform the sponsor that the team is unable to complete the requests due to a lack of funding, and defer the project.

B.

Prioritize the scope items to determine the duration needed for a minimal viable product (MVP) and adjust the funding request.

C.

Have the team work on the list of requests from the sponsor without modification until the 6-month period ends.

D.

Request the team complete all scope items, with the assumption of securing additional funding within 6 months.

Full Access
Question # 442

A project manager notices that an extroverted project team member appears to be increasingly controlling the direction of the entire team. The other team members are not complaining but seem to be more passive.

What should the project manager do?

A.

Meet with each team member to better understand the situation.

B.

Meet with the extroverted team member and ask them to be more sensitive to others.

C.

Address the situation in a team meeting and ask everyone to be more active.

D.

Observe the team dynamics closely and step in if a team member complains.

Full Access
Question # 443

A project manager found a repeated defect in a junior developer's code. The code is due in 2 days and a severe fine will be incurred if it is not fixed by then. The project manager wants to reassign the assignment to a more senior developer, but the junior developer is strongly opposed to the reassignment.

What should the project manager do?

A.

Assign the issue to a senior developer and schedule training for the junior developer after the due date.

B.

Assign the rework to the junior developer after consultation with the senior developer.

C.

Reassign the issue to the senior developer and assign the junior developer to assist in fixing the issue.

D.

Reassign the issue to the senior developer after explaining the situation to the junior developer.

Full Access
Question # 444

A project is starting with a team that is located all over the world. None of the team members have worked together before. The project goal is ambitious with an aggressive timeline.

What should the project manager do?

A.

Ask for financial support to set up a physical meeting for the team.

B.

Create a virtual room for the team to facilitate their collaboration.

C.

Schedule quarterly in-person meetings to enhance the team's relationships.

D.

Facilitate a virtual session with the team to start planning as soon as possible.

Full Access
Question # 445

The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?

A.

Assign a project team member to document exchanged communication for future reference.

B.

Assign the project sponsor as the point of contact for all provider communication.

C.

Ensure that all project stakeholders participate in the scope definition meetings.

D.

Establish a common language of terms with which to communicate with the provider.

Full Access
Question # 446

An organization is implementing a solar power system at its production plant. During the execution phase, one of the key stakeholders noticed and communicated that authorities are developing solar power regulation, which might impact the overall feasibility of the project.

What should the project manager do first?

A.

Collect and analyze information about the new regulation.

B.

Put the project on hold and wait for the regulation information to be confirmed.

C.

Proceed with the project as long as the regulation is not yet finalized.

D.

Meet with the sponsor to discuss the regulation issue and determine the proper action.

Full Access
Question # 447

A project team is working on a critical release and the customer wants this feature to be made available as early as possible. The business owner suggests an enhancement during the product demo.

How should the project manager address this request?

A.

Determine the additional funding needed and seek the sponsor's guidance.

B.

Support value-based delivery that is aligned with the project objectives.

C.

Follow the project change control process to formalize the change.

D.

Estimate the additional funding needed and seek the client's approval.

Full Access
Question # 448

A company in the manufacturing industry has started a new initiative to integrate project management and improve product innovation. What first step should the project manager take to increase transparency among the stakeholders?

A.

Define a plan on how communication throughout the project will be handled among the stakeholders.

B.

Set up a project dashboard to show day-to-day project status across the company.

C.

Invite key stakeholders to retrospective and review sessions to receive feedback as often as possible.

D.

Invite upper management to process workshops where current project statuses will be discussed.

Full Access
Question # 449

Negotiations are underway to secure an agreement with a critical supplier for the project. The negotiation situation has become contentious as it is becoming apparent that both parties will not receive everything they want and that a compromise might be necessary to avoid project delays, cost overruns, and damage to reputations.

What should the project manager do to help ensure a successful outcome for the project?

A.

Collaborate with stakeholders to complete an analysis of priorities with ranked objectives.

B.

Withhold from revealing the priorities and objectives until midway through negotiations.

C.

Begin the negotiation process with predetermined objectives to guide the discussions.

D.

Adjust priorities and objectives based on real-time developments during the negotiation process.

Full Access
Question # 450

During a sprint, the product owner requested a change in the features to be delivered in the same sprint. According to the product owner, the request from the customer is due to regulatory reasons and they have a deadline to meet.

What should the project manager do?

A.

Perform the change only if it has a higher or equivalent priority of the current remaining features.

B.

Submit the feature changes to the change control board (CCB) so they can evaluate and approve.

C.

Follow the plan by delivering the features and handle the change later in the project.

D.

Discuss with the stakeholders about the possibility of accommodating the feature changes.

Full Access
Question # 451

A newly hired project team lead was assigned a project using a hybrid delivery approach. As the project onboards a lot of new team members, the lead feels overwhelmed with the effort of explaining the project delivery process to each new team member.

What should the project lead do?

A.

Use Pareto techniques to identify the knowledge required by the majority of the team.

B.

Recommend putting the project temporarily on hold and focus on onboarding and training.

C.

Develop a training curriculum and schedule training delivery throughout the project.

D.

Document the processes and organize a week-long, off-site meeting with the project team.

Full Access
Question # 452

A virtual project team has members located on four continents. The project director is concerned about the declining motivational levels of team members and feelings of noninclusion by other team members. The project director has tasked the project manager with finding a solution.

What should the project manager do?

A.

Develop a plan for individual team members' growth and organize more team-building events.

B.

Recommend that the project director appoint project managers for each continent.

C.

Set up ground rules for team engagement, taking into consideration different cultures.

D.

Take differences in time zones into consideration when scheduling team meetings.

Full Access
Question # 453

A virtual product development team is working well together and is on schedule. One team member wants to take 1 week off to attend a training.

What should the project manager do?

A.

Decline the team member's request as it might jeopardize the schedule.

B.

Approve the team member's request as it will increase motivation.

C.

Decline the team member's request since the goal is not individual team member advancement.

D.

Approve the team member's request on condition they work additional hours when they return from training.

Full Access
Question # 454

A work package to configure new computer hardware is received, and a list of related project activities have also been identified. What should the project manager do?

A.

Define the project management plan.

B.

Estimate the resources needed for the activities.

C.

Consult subject matter experts (SMEs) to review the schedule.

D.

Estimate the cost of each activity.

Full Access
Question # 455

An important project to build a new airport was suddenly stopped because of the complaints from residents in the surrounding communities. The residents stated that they were not consulted and that the project would cause ecological and pollution damage.

What should that project manager have done first in order to avoid this situation?

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Full Access
Question # 456

A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.

In closing this project midway, which activities should the project manager execute first?

A.

Perform contract, financial, and administrative tasks.

B.

Finalize the in-progress administrative tasks.

C.

Evaluate contract and administrative tasks.

D.

Execute financial and administrative tasks.

Full Access
Question # 457

A virtual project team is working on a multinational project with a risk management strategy. An unexpected situation occurs in one of the project countries, creating the possibility that project operations will shut down for at least two months.

What should the project manager do to address this risk?

A.

Relocate the project to another country that is not shutting down.

B.

Evaluate the possibility of having another country complete the task.

C.

Identify additional team members who are able to complete the task.

D.

Determine if the project has built-in slack to remain on schedule.

Full Access
Question # 458

A project is 20% complete. The client has accepted a project order amendment that involves a major change. Without this major change, the project result will be useless for the client organization.

What should the project manager do?

A.

Update the project status from "active" to "on hold" until there is more clarity on the scope of the change.

B.

Initiate planning for the project with the modified scope as laid out in the client's purchase order.

C.

Set up a meeting with the client and the project team to identify ways to safeguard the project from the change.

D.

Consult the project sponsor to understand if the change must be processed for project execution.

Full Access
Question # 459

A railroad construction project is in the planning stage. During a monthly progress meeting, an external project manager from the sponsoring organization mentioned there is a potential delay in the design completion date. The external project manager wants to know the impact of this delay on the overall project completion date in the next monthly meeting.

Which three actions should the internal project manager take next? (Choose 3)

A.

Perform variance analysis.

B.

Validate the critical path method (CPM).

C.

Establish what-if scenario analysis.

D.

Determine the schedule performance index (SPI).

E.

Execute a Monte Carlo simulation.

Full Access
Question # 460

A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.

What should the project manager do?

A.

Investigate alternatives for team member needs.

B.

Evaluate the engagement needs for stakeholders.

C.

Identify the root cause of the team member's misunderstanding.

D.

Build trust and influence stakeholders.

Full Access
Question # 461

Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?

A.

Create a communications management plan.

B.

Create a responsible, accountable, consulted, informed (RACI) chart.

C.

Develop a kanban board.

D.

Send a copy of the project charter to all project stakeholders.

Full Access
Question # 462

A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.

What should the project manager do next?

A.

Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.

B.

Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.

C.

Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.

D.

Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.

Full Access
Question # 463

A project manager notices during project meetings that some team members repeatedly threaten to resign when they do not agree with something. Which phase of conflict escalation is the project in?

A.

Beginning

B.

Resolution

C.

Intensification

D.

Final

Full Access
Question # 464

A project manager is confused when the operational results from previous iteration solutions have not been acceptable to the client. Team members have already delivered all previous solutions, which were accepted by the client as complete.

What should the project manager do?

A.

Recommend a change in the project methodology or the approach.

B.

Develop and execute a stakeholder engagement strategy.

C.

Determine the criteria and measuring systems for objective success.

D.

Allocate more time for mentoring project team members.

Full Access
Question # 465

Due to their different ideas regarding the execution of a project, a conflict has occurred between two stakeholders.

What should the project manager do to resolve the conflict?

A.

Arrange a group meeting with the stakeholders to generate creative alternatives.

B.

Address the conflict in a planned meeting with all stakeholders and project team members.

C.

Assess the conflict based upon the stakeholders' past disagreements.

D.

Focus on the personal issues between the stakeholders.

Full Access
Question # 466

A project is starting its first iteration out of eight. The team realizes that a key deliverable will depend on the acquisition of a new device.

What should the project manager do?

A.

Assign a resource from the core team to handle the acquisition.

B.

Register a risk and escalate it to the project sponsor.

C.

Update the status report with information about this dependency.

D.

Register a risk and monitor its exposure variation.

Full Access
Question # 467

A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.

What should the project manager do?

A.

Remove the development team's rejected feature from the backlog.

B.

Reassure all team members that the development team will fix the issue.

C.

Initiate an improvement plan for the development team to follow.

D.

Evaluate the context for the conflict with the development team.

Full Access
Question # 468

A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.

How should the project manager respond?

A.

This framework is not appropriate for agile.

B.

This is a learning experience for the agile team.

C.

An agile approach is easily adaptable.

D.

An agile approach is different.

Full Access
Question # 469

A project team is concluding the final sprint to deliver two work packages. However, the scrum master has not scheduled sprints for three packages on the critical path, which is going to cause the schedule performance index (SPI) to trend toward 0.90 the following month.

What should the project manager do first?

A.

Evaluate the schedule performance index (SPI) trend for slack to enable all five sprints while maintaining the cost performance index (CPI).

B.

Instruct the scrum master to suspend the current sprints and initiate the critical sprints immediately.

C.

Ask the scrum master to identify why sprints are in process for work that is not on the critical path.

D.

Contact the project sponsor to request adjustment to the completion date and to enable the current workflow.

Full Access
Question # 470

A project manager's team has been working very hard to meet a critical deadline. Some project team members are experiencing burnout due to the high workload.

What should the project manager do first to manage the team's workload effectively?

A.

Add additional temporary resources to the project to achieve the next milestone.

B.

Encourage open communication and involve the team in task distribution decisions.

C.

Assign additional tasks to high-performing team members to decrease the burden on others.

D.

Renegotiate the scope of the next milestone with the stakeholders to align with the team's capacity.

Full Access
Question # 471

A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project.

What should the new project manager do next?

A.

Schedule a lessons learned meeting with the project team and close out the project.

B.

Use the contingency fund to extend the timeline and conduct a detailed review of past deliverables.

C.

Prepare a transition plan to hand over the operations and other closing documentation.

D.

Document the project manager's departure and the missing documents in the risk log.

Full Access
Question # 472

An ongoing project with company A is impacted by the recent acquisition of company B. This could affect the current suppliers for the ongoing project.

What should the project manager do next?

A.

Retain company A's supplier based on the long-term relationship with them.

B.

Consolidate the list of suppliers for companies A and B.

C.

Engage the suppliers of company B to validate the current list of suppliers.

D.

Evaluate the project suppliers of company B for future use.

Full Access
Question # 473

An email arrives shortly after the beginning of a sprint. It is from a key project stakeholder who is unfamiliar with agile approaches and has a serious complaint about future work that has been scheduled. The stakeholder is insisting that a future work package be removed from the backlog entirely, claiming that it is unnecessary.

What should the project manager do?

A.

Address the stakeholder's request at the daily standup and ask for the team's opinion.

B.

Discuss the stakeholder's request at the next retrospective meeting.

C.

Invite the stakeholder to the backlog refinement meeting to discuss their request.

D.

Alter the backlog to accommodate the stakeholder's request.

Full Access
Question # 474

A project manager is in the middle of executing the construction of a high-rise plaza when the government regulatory agency announces an increase in the price of fuel. The project still has seven months left on the schedule.

What should the project manager do first?

A.

Meet with the vendors to evaluate the impact on the budget.

B.

Implement crashing to mitigate the impact on the budget.

C.

Review the organizational process assets (OPAs) as a reference.

D.

Request the release of management reserve for the project.

Full Access
Question # 475

During a planning session, the development team and the product owner are arguing about the effort needed to deliver a specific feature in a software development project. The product owner says that the feature can be developed in one week, whereas the team estimates that it will take at least two weeks. After several hours of discussion, they have not reached an agreement.

What should the project lead do?

A.

Communicate to the stakeholders that the project has to be delayed for two weeks.

B.

Ask the project team to accept the shorter estimate as it is important to keep a good relationship with the product owner.

C.

Decide what should be the time estimate and proceed with the planning meeting.

D.

Educate the product owner that the project team members are the most appropriate group for assessing the effort.

Full Access
Question # 476

A key stakeholder of a project wants to include additional work before completion.

What should the project manager do?

A.

Request the additional work through governance.

B.

Meet with the stakeholder and explain that additional work cannot be added.

C.

Prioritize the additional work in the backlog.

D.

Collaborate immediately with the stakeholder to complete the additional work.

Full Access
Question # 477

A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.

What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?

A.

Involve all of the stakeholders in the escalation by setting up a conference call.

B.

Escalate to the other party's management and inform the steering committee.

C.

Reach out to peer managers for similar escalation situations and follow past experiences.

D.

Review the established project escalation process and take the appropriate action.

Full Access
Question # 478

A new employee has joined the management team and wants to get a quick overview of all the agile team's projects. What should the agile team lead recommend to the employee as a first step to gain this understanding?

A.

Review the information radiators for each project.

B.

Connect with each project's scrum master to assess progress.

C.

Meet with each project's development team separately.

D.

Attend the daily standup meetings for each project.

Full Access
Question # 479

A project manager assigned to an agile project realizes that after iteration demos, new user stories to fix issues reported by the product owner are not included in prioritization of the following sprint. This has led to a high number of unprioritized stories in the backlog and will lead to delay of the product release.

What should the project manager do?

A.

Review the minimum viable product (MVP) user stories and ensure all related stories are prioritized.

B.

Ask the team and product owner to reprioritize the user stories in the backlog for an updated iteration schedule.

C.

Ask the team to include the user stories as spikes in the next iteration to bring the project back on schedule.

D.

Add additional iterations to the schedule to accommodate for the work required on the stories.

Full Access
Question # 480

A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.

What should the project manager do first?

A.

Establish a communication channel.

B.

Create a communication protocol.

C.

Develop the stakeholder analysis.

D.

Distribute the risk register.

Full Access
Question # 481

The team's velocity is inconsistent, leading the product owner to believe the team is creating too many points in their user stories.

What should the scrum master do first?

A.

Remind the product owner that their role is to determine what the team should work on during the iteration.

B.

Meet with the product owner for planning and to resize the stories in the backlog.

C.

Invite the product owner to planning poker meetings and get their approval after each story is sized.

D.

Raise this concern with the team and review the performance of the past three sprints.

Full Access
Question # 482

An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team.

How should the project manager approach this situation?

A.

Measure the team's psychological safety.

B.

Reschedule the team's retrospective meeting.

C.

Coach the team to be more inclusive.

D.

Rotate the team's daily meeting roles frequently.

Full Access
Question # 483

A company has decided to create a new product to prepare itself for the changing economy. The technology required for the new product is not well understood yet, and the requirements are still being debated.

Which approach should the project manager advise for this project?

A.

Lean

B.

Predictive

C.

Agile

D.

Hybrid

Full Access
Question # 484

A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.

What should the project manager suggest?

A.

Request that all team members receive the newest quality standards training and review one another's work.

B.

Request that a quality specialist be assigned to the project to check the final product at the end of the project.

C.

Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.

D.

Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.

Full Access
Question # 485

A project sponsor is replaced during a hybrid project closure. The new project sponsor wants to change all of the project documentation to reflect a fully predictive approach.

What should the project manager do next?

A.

Review the key existing project documents with the new project sponsor.

B.

Ask the team to estimate the time it will take to update the documentation.

C.

Address the issue during the lessons learned session of the closing phase.

D.

Set up a meeting with the new project sponsor to understand their concerns.

Full Access
Question # 486

A drone manufacturing company is designing its first drone. The new project architect has called the project manager to review the project scope. The architect wants to reshuffle the scope and schedule to test the drone functionality first. The project team disagrees because the scope has already been approved and any change might affect the timelines set by the CEO.

What should the project manager recommend?

A.

Review the timelines with the architect and invite the CEO to the meeting to make sure all the stakeholders are involved.

B.

Reject the review as the completed project timeline is set by the company's CEO and has already been approved.

C.

Agree to review the architect's new proposal to assess the impact on the timelines set by the CEO.

D.

Register an issue in the log regarding the timeline delay to the CEO's approved plans before agreeing to change the project scope.

Full Access
Question # 487

A project manager is creating the quality management plan for deliverables with very precise requirements. The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.

Which two actions should the project manager take first? (Choose 2)

A.

Review the conformity management plan to ensure the requirements are clearly defined.

B.

Reference the quality management plans from old projects to determine if they apply to these deliverables.

C.

Add a conformity team member to inspect each deliverable upon receipt from the supplier.

D.

Evaluate industry standards of similar products to determine which apply to this project.

E.

Ask the suppliers to create a statement of conformity when the product is delivered.

Full Access
Question # 488

A project manager notices that the project team is encountering product issues while coding client-specific developments. The project manager foresees delays to the project's timeline because of these product issues.

Which methods should the project manager use to communicate project delays and other difficult messages to stakeholders?

A.

Oral feedback, project meetings, and reporting

B.

Project meetings and reporting

C.

Project meetings and oral feedback

D.

Written feedback, project meetings, and reporting

Full Access
Question # 489

To ensure effective team communication and processes, a standard set of software including video conferencing is defined for a virtual scrum team. Several team members are reporting problems with their access and cannot adhere to team processes.

How should these issues be resolved?

A.

Individual team members should discuss solutions to resolve the issues after the Scrum is concluded.

B.

The scrum master should ensure the appropriate escalation to resolve the issues.

C.

The product owner owns the open issues until they are resolved.

D.

Individual team members need to submit service desk tickets to resolve the issues.

Full Access
Question # 490

A project manager was just assigned to an ongoing project. According to the project's status, all the increments produced passed the acceptance criteria. During the last meeting with the project sponsor, the prototype is far from the sponsor's original expectations.

What should the project manager do first?

A.

Cancel the ongoing project and start a new one.

B.

Invite the sponsor to the retrospective meeting so they can clarify expectations.

C.

Add additional sprints to modify the deliverables with the new information.

D.

Complete the project and start a new one for the updated scope.

Full Access
Question # 491

A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.

What should the project manager do?

A.

Invite the new manager to the next daily scrum.

B.

Invite the new manager to the next sprint review.

C.

Invite the new manager to the next sprint planning.

D.

Invite the new manager to the next sprint retrospective.

Full Access
Question # 492

A project manager coordinates several projects in one program. Each project concerns a different country, has a different sponsor, and has specific business priorities. The resources are shared among the projects. The project manager anticipates this could result in delays and/or conflicts that will affect the program outcomes.

What should the project manager do to prevent such a situation?

A.

Review all project schedules and add a 3-month time period to each to cover such a risk and ensure there will be no delay that could affect the program.

B.

Organize regular meetings to identify risks related to the projects and program, assess them, and define action plans when needed to mitigate the risks.

C.

Ask each project manager to write a detailed weekly report listing all the activities, what was achieved, what needs to be done, and the identified risks.

D.

Ask the project managers to work on their own schedules independently of one another and aggregate these schedules to present at the monthly steering committee meeting.

Full Access
Question # 493

After the first iteration, a scrum master notices that some of the team members are struggling with testing their developed product. What should the scrum master do next?

A.

Log the issue and see if improvements show in the second iteration.

B.

Log the issue and ask a senior member to coach these team members.

C.

Hire new team members to implement the correct way of testing.

D.

Check lessons learned and use the testing process from previous projects.

Full Access
Question # 494

A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.

What should the project manager do to have a high-performing team?

A.

Set up regular project status meetings and invite all team members.

B.

Encourage the team to define the ground rules for performance.

C.

Set up individual calls to follow up on each team member's progress.

D.

Invite team members to an informal meeting to get to know one another.

Full Access
Question # 495

A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.

What should the project manager do?

A.

Recommend that the team use industry-accepted guidelines.

B.

Contact the chief information officer (CIO) and request the enterprise development guidelines.

C.

Contact the previous team and ask for a copy of their guidelines.

D.

Recommend that the team develop their own guidelines.

Full Access
Question # 496

During planning, a virtual project team agreed to the project reporting structure and established a meeting cadence that fits multiple time zones. One month into execution, the project manager notices that certain members are disengaged during project meetings.

What should the project manager do to resolve this issue?

A.

Work with the team to review the effectiveness of the agreed project practices.

B.

Set up follow-up sessions on all action items for team members.

C.

Distribute the meeting agenda and objectives the day before the project meetings.

D.

Review the project reporting structure to clarify the project objectives.

Full Access
Question # 497

While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.

What should the scrum master do?

A.

Determine the average of the two estimates and assign that amount.

B.

Ask the product owner to rewrite the story so the final estimate can be agreed upon.

C.

Consult the lessons learned for insight into the correct estimate.

D.

Select the junior member's estimate since they will most likely be doing the work.

Full Access
Question # 498

A project manager was notified about a new regulatory requirement that could impact the project schedule.

What should the project manager do first?

A.

Increase the amount of slack in the critical path to reduce the impact of the regulatory requirement.

B.

Update the schedule and project risk register according to the regulatory requirement.

C.

Consult the project management plan for guidance on addressing the regulatory requirement.

D.

Assess the impact of implementing the potential regulatory requirement on the project.

Full Access
Question # 499

A steering committee has asked the project manager to assist with the decision-making process between build versus buy delivery options. Which value metric should the project manager evaluate to respond to the steering committee's request?

A.

Impact value

B.

Expected monetary value (EMV)

C.

Net present value (NPV)

D.

Earned value (EV)

Full Access
Question # 500

A project manager is leading a project that is kicking off next month. The project manager realizes that there are many stakeholders that need updates on different aspects of the project at different frequencies.

What should the project manager do first to ensure each stakeholder has the information they need?

A.

Develop a communications management plan that reflects the needs of the stakeholder community.

B.

Engage with each stakeholder to determine their information needs related to the project.

C.

Create a responsible, accountable, consulted, and informed (RACI) chart based on the stakeholders and their communications needs.

D.

Determine the most appropriate mechanisms to leverage when communications are necessary.

Full Access
Question # 501

During a sprint, the team is experiencing conflict because the customer asks for additional features that increase the complexity. The scrum master is trying to resolve the conflict.

Which approach should the scrum master use?

A.

Discuss the definition of done (DoD) with the customer.

B.

Approach the product owner to determine the next course of action and update the backlog.

C.

Discuss the acceptance criteria with customer.

D.

Perform backlog prioritization to ensure that everyone is working on the highest value features.

Full Access
Question # 502

A project manager is working on a global project and realizes that one team member is not performing as expected. The project manager meets with the team member to find out what is causing this low performance. The project manager discovers the team member is experiencing conflict and feels uncomfortable with the team. The team member then asks to be moved to another project.

What should the project manager do?

A.

Request human resources (HR) to help.

B.

Move the team member to another project.

C.

Confront the issue with the rest of the team directly.

D.

Ask other team members to be more welcoming.

Full Access
Question # 503

An IT team has reached out to the project manager for guidance on which communication method to use when system downtime will impact the resources working on the project.

Which two communication methods should the project manager recommend? (Choose 2)

A.

Communicate via email to the project's email distribution group.

B.

Communicate via instant messaging.

C.

Communicate via the project team's document management site.

D.

Communicate in the IT risk forum.

E.

Communicate verbally to the key project stakeholders.

Full Access
Question # 504

A company is working on the prototype of a new contract document that includes visual elements. The product owner shared the project sponsor's feedback about the elements to be included, but the project team pushed back. However, when the project sponsor spoke with the team, they confirmed that all of the changes are possible.

How should the project manager mitigate this situation?

A.

Execute a retrospective meeting to solve the misalignment.

B.

Review the actions listed in the risk management plan.

C.

Review and update the organizational process assets (OPAs).

D.

Submit a change request to replace the product owner.

Full Access
Question # 505

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.

What should the project manager of the contracting company do?

A.

Record that the delay is attributable to the client and request a meeting.

B.

Check the contractual terms about liquidated damages and reject if not applicable.

C.

Meet with the sponsor to analyze the delays and the associated liquidated damages.

D.

Schedule a detailed analysis of the delays using cause and effect.

Full Access
Question # 506

In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.

Which action should the project manager avoid?

A.

Escalating a conflict within the project

B.

Creating a new communication channel

C.

Giving special attention to this stakeholder

D.

Dismissing the stakeholder's opinions

Full Access
Question # 507

Developers spend most of the sprint writing code for user stories, leaving little time for testing. As a result, user stories cannot be tested in time and the stories remain unfinished by the end of the iteration, resulting in poor metrics.

What should the scrum master do first in this situation?

A.

Divide the user stories into two categories: development stories and test stories.

B.

Increase the number of developers on the team so stories are completed faster.

C.

Revalidate the team's velocity to ensure development and testing can be completed within the iteration.

D.

Request the developers work overtime to ensure the testers have enough time to perform their tests.

Full Access
Question # 508

A project manager with global teams is managing a project that is progressing as expected. However, recently the project manager has learned of some team members missing the daily meetings. After investigating the issue, the project manager realizes different time zones is the main cause of the issue.

What should the project manager do next?

A.

Schedule a team-building workshop involving all teams to support better communication.

B.

Schedule a meeting and ask all teams to sort the issues and move ahead with full participation.

C.

Ask everyone to only invite team members in different parts of the world as necessary.

D.

Share the time-overlap schedule with the team to make meeting scheduling convenient.

Full Access
Question # 509

During a contract renewal meeting, an organization's commercial team and the customer are disagreeing and negotiations are failing. What should the project manager do to reach an agreement that will satisfy all parties?

A.

Reinforce the initial rules of the negotiations.

B.

Engage a facilitator to support the negotiations.

C.

Concentrate on meeting the customer's requests.

D.

Set clear expectations among the participants.

Full Access
Question # 510

During a project iteration, half of the project team was reallocated to a new project. How should the project lead handle the situation?

A.

Raise the risk of having the velocity impacted for the current iteration and discuss it with the product owner.

B.

Raise the issue with the product owner to bring additional resources to the project team.

C.

Raise the risk with the project stakeholders and wait until the velocity for the current iteration is calculated.

D.

Raise the issue with the project stakeholders to analyze the project impact and take the proper actions.

Full Access
Question # 511

A team is performing above expectations, and the sponsor wants to expand the project scope to benefit the organization. However, there are only a few team members with the needed leadership experience.

What should the project manager do?

A.

Communicate the risks and propose hiring members with leadership experience before continuing with the request.

B.

Decline the scope expansion until the team members get appropriate leadership opportunities within the project.

C.

Implement the scope expansion and suggest the team members get a mentor due to their lack of leadership experience.

D.

Recognize each team member for their contributions and recommend them to the leadership development program.

Full Access
Question # 512

In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.

What should the project manager do first?

A.

Escalate the issue to the change control board (CCB).

B.

Ask the project team to analyze the impact.

C.

Register the risk and document the contingency plan.

D.

Have the project team brainstorm alternatives.

Full Access
Question # 513

A project manager is working on a hybrid project and is responsible for ensuring the design, build, and delivery of the software is completed in an agile way. How should the project manager plan the iteration?

A.

Use a work breakdown structure (WBS) with firm start and end dates for all phases to ensure nothing is missed.

B.

Use a kanban board as an information radiator to manage work in progress (WIP) at the individual and organizational levels.

C.

Use a minimum viable product (MVP) to test and discover which features to schedule when and what to fail early.

D.

Use a product backlog of the functionalities and features required to provide the expected business benefit.

Full Access
Question # 514

A project manager is quantifying risk for their project. The project manager needs an expert opinion in this process, but experts are spread over different geographic locations and time zones.

What should the project manager do?

A.

Apply the critical path method (CPM).

B.

Use the Delphi Technique.

C.

Use the Monte Carlo analysis online.

D.

Utilize story point estimating.

Full Access
Question # 515

An agile team member discovers an impediment that is preventing them from doing their work efficiently. At which of the meetings should they bring up this impediment for resolution?

A.

Sprint review meeting

B.

Retrospective meeting

C.

Daily Scrum meeting

D.

Sprint planning meeting

Full Access
Question # 516

Two project team members are having difficulty communicating updates and issues. One team member prefers telephone calls for any kind of urgency, whereas the other team member prefers email communication. This difference results in a lack of understanding between the team members and sometimes hinders timely communication.

What should the project manager do?

A.

Ask the team members to resolve this issue themselves.

B.

Provide these team members with feedback that this issue is causing a delay.

C.

Ask the team members to follow the ground rules in the project management plan.

D.

Provide guidance to the team members to resolve the conflicts.

Full Access
Question # 517

During a project's execution phase, the team faced a setback in one of the deliveries and was asked to come up with a new plan. All team members joined a meeting to address the issue and, after a while, the project manager observed that two members of the team were just agreeing with anything that was proposed even though they were opposed to the outcome.

What conflict resolution style were the team members adopting?

A.

Avoidant style

B.

Combative style

C.

Collaborative style

D.

Accommodative style

Full Access
Question # 518

A project manager is asked to manage an agile project, allowing the company to comply with a new upcoming regulation. After the project kickoff, the scope is modified to have the project team work on specific tasks, while a global team will manage the program for several countries in parallel. The project management plan has not yet been shared, and the deadline to complete the project is fixed.

What should the project manager do to handle the scope change?

A.

Define an initial backlog and start working on the clearest tasks, then incrementally refine the scope.

B.

Create a risk entry in the risk management plan due to the lack of a global project management plan.

C.

Review the organizational process assets (OPAs) from past projects with similar scope changes.

D.

Formalize the change in the scope with the project sponsor to limit accountability for the specific tasks.

Full Access
Question # 519

A scrum master noticed that one of the team members is afraid to ask questions, does not like to collaborate with other team members, and avoids taking responsibility for their actions. What is the likely reason that would cause a team member to behave that way?

A.

Lack of technical skills

B.

Fear of conflict

C.

Lack of experience

D.

Company culture

Full Access
Question # 520

A project's planning process is finished, and all resources were budgeted for and approved by senior management. Just before the kickoff meeting, a member of the production department realizes that the plan does not meet the requirements for their area.

What should the project manager have done during the planning process?

A.

Monitored the budget variations during the planning process

B.

Developed a good resource estimation in the planning process

C.

Included all functional managers in the planning process

D.

Distributed the resource estimates to all areas during the planning process

Full Access
Question # 521

A transformation project that is composed of agile streams has come to an end.

How should the project manager collect the experience gained during this project?

A.

Organize a lessons learned session with the team.

B.

Create a document with the information from the last sprint retrospective.

C.

Ask for feedback during the next standup meeting.

D.

Conduct a session with the members of the project steering committee.

Full Access
Question # 522

A project team is defining the ground rules during their first meeting as a team. During this session, only a few of the team members suggested and approved the ground rules while most remained silent. As a result, the team's ground rules favor those few team members.

What should the project manager do?

A.

Conduct a round table and ask the team to share their opinions one by one.

B.

Propose new team ground rules and communicate them to all.

C.

Ask the silent team members to share their opinions via email.

D.

Perform focus group interviews based on the new team ground rules.

Full Access
Question # 523

A team member is not getting along with one of the project sponsors. The sponsor has requested to move the team member to another project.

What should the project manager do next to resolve the situation?

A.

Meet with the team member and identify areas of improvement to satisfy the sponsor.

B.

Review the resolution of a similar past situation and apply the same strategy for the team.

C.

Identify the reasoning behind the behavior of the sponsor and team member.

D.

Hold a meeting with the team and explain the ground rules for the project.

Full Access
Question # 524

A company is building a minimum viable product (MVP). How should the project manager help to ensure the company builds a high-quality product?

A.

Ask the product manager to spend more time improving quality.

B.

Determine the quality metrics for the product and recommend options for improvements.

C.

Partner with a qualified third-party vendor to develop a product that meets the requirements.

D.

Hire a quality engineering leader to drive the strategy.

Full Access
Question # 525

A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.

What should the project manager have done to prevent this conflict?

A.

Provided copies of the stakeholder engagement plan to all team members.

B.

Defined the roles and responsibilities of the team members.

C.

Updated the communications management plan.

D.

Established ground rules for the team

Full Access
Question # 526

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

Full Access
Question # 527

A labor union contract negotiation is delaying the completion of a project to build

a new manufacturing plant. Because the labor contract was due for renewal this year, the

project manager documented the negotiation process as a risk to the project. The project

was about to start the first phase of equipment installation at the plant when the negotiation began.

How should the project manager address the situation?

A.

Meet with the project team to determine options for risk mitigation.

B.

Log the issue and follow the planned actions in the risk response plan.

C.

Acquire contract resources and submit a change request for the cost impact.

D.

Escalate the issue to the steering committee to ask for mitigation support.

Full Access
Question # 528

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.

How should the project manager approach this situation?

A.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.

B.

Continue to work on the project until the stakeholders and management come to a decision.

C.

Socialize with the stakeholders to better understand their needs and reset expectations.

D.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.

Full Access
Question # 529

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

A.

Reschedule the project execution date.

B.

Continue project execution using the current blueprints from the client.

C.

Escalate this issue to the project sponsor

D.

Consult with the client to determine if project execution should be continued.

Full Access
Question # 530

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

Full Access
Question # 531

For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.

Full Access
Question # 532

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.

Escalate the issue to the functional manager

C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.

Perform the quantitative risk analysis for the team member.

Full Access
Question # 533

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

A.

Concentrate on the current project milestones.

B.

Update the project management plan for this new work.

C.

Develop a business case and submit it to the client.

D.

Make all the changes and then show the client the results.

Full Access
Question # 534

A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member's success in the project documentation

What should the project manager do?

A.

Attach a note to the project management plan about the team member

B.

Hold a project team meeting about the team member's contribution and take minutes

C.

Record the team member's contribution in the responsibility assignment matrix (RAM)

D.

Send a communication to management recognizing the team member's contributions

Full Access
Question # 535

The team architect resigned from the company. The new architect points out a

design flaw during a planning meeting that may potentially impact the final quality.

What should the project manager do first?

A.

Review the scope management plan.

B.

Update the design with changes.

C.

Request an architecture review.

D.

Update the quality management plan

Full Access
Question # 536

A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.

What should the project manager do?

A.

Seek help from the project sponsor to get an SME from another team in the organization.

B.

Provide an opportunity to one of the existing team members to become an SME.

C.

Hire a contractor from outside of the organization to continue with the project.

D.

Ask team members to document the issue and address it in the next project meeting.

Full Access
Question # 537

In a multinational project, stakeholders are in different time zones. The project

manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the

project sponsor that they know very little about the project.

What should the project manager do?

A.

Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.

B.

Ensure that the stakeholders who are complaining are present for the next project update meetings.

C.

Record the regular project update meeting and share it with all stakeholders after the meeting is completed.

D.

Change the meeting time to the working time zones of the stakeholders who are complaining.

Full Access
Question # 538

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

A.

Escalate the issue to the project sponsor.

B.

Review the stakeholder engagement plan.

C.

Update the issue log.

D.

Neutralize the negative stakeholders.

Full Access
Question # 539

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

Full Access
Question # 540

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

A.

Focus on remediation not merely on correcting symptoms

B.

Compare the team's performance against other project teams

C.

Identify potential failure points based on the iteration workload

D.

Motivate the team to perform better

Full Access
Question # 541

A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?

A.

Ask the project sponsor to replace the contractor since they do not have agile experience

B.

Issue a formal notice to the contractor to obtain an agile certification

C.

Consult the project team to understand the extent of the training needs for the contractor

D.

Instruct the contractor to receive agile training since the project has already started

Full Access
Question # 542

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

A.

Meet with the team to reinforce their responsibilities and the consequences if theproject deliverables are not completed on time.

B.

Apply additional controls to the project deliverables to ensure that all milestonesare achieved on time.

C.

Contact the functional manager to ensure that team motivation remains high untilthe end of the project.

D.

Schedule a team event with the project sponsor to highlight the importance of theproject and recognize the work of the team.

Full Access
Question # 543

A project management team received news that a competitor has released the

latest version of a program. What should the team do next?

A.

Review the project plan to evaluate if any updates should be made.

B.

Crash the existing schedule with additional resources to deliver more features.

C.

Stop the project immediately as the market opportunity has already been missed.

D.

Continue with the project plan and target delivery date as expected.

Full Access
Question # 544

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

Full Access
Question # 545

The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.

What should the project manager have done?

A.

Conveyed task completion information to accounting

B.

Closed the procurement process properly

C.

Completed the transition process

D.

Performed administrative closure of the project

Full Access
Question # 546

Match the project situation on the left to the meeting on the right where the situation could occur.

Full Access
Question # 547

A project needs to purchase a specific piece of equipment, as stated in the

project documents and approved by the project sponsor. The procurement division is

questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.

What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?

A.

Communicated the project charter to the procurement division

B.

Included a procurement division member on the project team

C.

Reminded the project sponsor about the procurement division's reputation

D.

Communicated the project management plan to the procurement division

Full Access
Question # 548

A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.

What should the project manager have done to avoid this situation?

A.

Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred

B.

Set up weekly status meetings to review team progress, prepared weekly status reports to track progress and regularly escalated delays

C.

Met with the team, allowed team members to make decisions about what to do and established performance goals

D.

Conducted routine meetings and identified team members who are under performing

Full Access
Question # 549

A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.

What should the project manager do to ensure the velocity is under control?

A.

Ask the product owner to look at a minimum of four to eight iterations and replan the velocity for the next iteration based on the team's current performance.

B.

Ask the scrum master to plug gaps in the team's performance by adding a team member to compensate for the velocity decrease.

C.

Request that the team improve their cycle time to compensate for the velocity decrease.

D.

Request the team to improve the lead time, cycle time, and response time individually and track closure.

Full Access
Question # 550

A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.

What should the project manager tell the team members to focus on?

A.

Reducing cost for the customer

B.

Delivering value to the customer

C.

Working together as a team

D.

Finishing the project on schedule

Full Access
Question # 551

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

A.

Rebaseline the project schedule to show the current status of the project.

B.

Create a benefits management plan mapped to the organization's strategic objectives

C.

Perform a project cost-benefit analysis for the stakeholders

D.

Update the deliverables map against the agreed-upon project requirements

Full Access
Question # 552

Due to a recent budget reduction, two team members were released from an agile

team. The customer is still expecting early results for the project.

Which two actions should the project manager take to align customer expectations? (Choose

two)

A.

Ask the agile team to review the updated sprint velocity with the customer.

B.

Ask the product owner to review the prioritized backlog with the customer.

C.

Ask the agile team to review and update the quality management plan with thecustomer.

D.

Review the impediments log with the customer.

E.

Send a detailed project management plan to the customer.

Full Access
Question # 553

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

A.

Assign the tasks to the resources based on their expertise.

B.

Ensure that the priority of each task is clear to the team.

C.

Ask the team to self-organize and manage the work assigned.

D.

Tell the team which task to focus on at the next daily standup.

Full Access
Question # 554

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

A.

Give the new team member time to contribute until they ask for help and support.

B.

Assign the new team member tasks so that the team member knows on what to focus.

C.

Approach the team member to identify any issues and then plan a resolution accordingly.

D.

Review the project with the team member to ensure the project scope is understood

Full Access
Question # 555

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

A.

The team with the higher velocity is performing better and should be rewarded.

B.

The issue should be addressed as part of a retrospective in the next iteration.

C.

The velocity should not be compared as teams can size items differently.

D.

The velocity of both teams should be compared at the end of every iteration.

Full Access
Question # 556

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments

B.

Incremental delivery and frequent backlog refinement based on user feedback

C.

Iterative development and collection of frequent feedback from project team members

D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented

Full Access
Question # 557

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Full Access
Question # 558

A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?

A.

Provide opportunity for team members to learn and adjust to the technology.

B.

Move team members who are not performing from the team.

C.

Add new members to the team and increase the velocity

D.

Re-assign the project to a team that has worked with this technology

Full Access
Question # 559

An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.

What should the project manager do to help move the project forward?

A.

Review documents provided by other teams, such as lessons learned and the risk matrix.

B.

Attend the Scrum of Scrums to identify roadblocks and manage dependencies.

C.

Study the technology to assist the team in decision-making if progress slows.

D.

Encourage the stakeholders to collaborate by facilitating meetings and sharing knowledge.

Full Access
Question # 560

An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?

A.

Ask for additional team members to maintain the velocity

B.

Implement a checkpoint in the iteration to verify if the team is on track

C.

Conduct a focused retrospective to help the team to discover the root cause

D.

Ask the team to have a lower commitment for the next iteration

Full Access
Question # 561

A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?

A.

Evaluate the project risk and try to replace the project with another one within the organization.

B.

Inform the project sponsor about the risk and try to convince them to withdraw the project.

C.

Study and apply the lessons learned from the failed project so that this project does not follow the same pattern.

D.

Continue executing the project using the project manager's usual methods as all projects are unique.

Full Access
Question # 562

A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team

requests a change in the sprint goals and sprint backlog items.

What should the project manager do?

A.

Create a parallel sprint to deliver the additional items.

B.

Guide the agile team to add the new scope to the product backlog.

C.

Pause the sprint to allow time to include the new items.

D.

Moderate the expectations for sprint quality.

Full Access
Question # 563

A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?

A.

Cancel the meeting and create the risk register using the project documents.

B.

Continue the meeting and send the updated risk register to all stakeholders.

C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.

D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.

Full Access
Question # 564

On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner's requirements.

Who is responsible for analyzing the new requirement and making the final decision?

A.

Project manager

B.

Scrum master

C.

Project sponsor

D.

Product owner

Full Access
Question # 565

The project manager has recently received funding approval for a training program

for the entire project team but has not yet defined the most effective training course. One

team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?

A.

Send this change request to the change control board (CCB) for approval.

B.

Approve the request for the specialized training.

C.

Reject the request as it does not impact the project deliverables.

D.

Validate if the training is within scope and budget.

Full Access
Question # 566

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?

A.

Ask the team leader to assign other resources.

B.

Update the issue log.

C.

Include this in the risk register.

D.

Escalate the issue to the functional manager.

Full Access
Question # 567

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

A.

Propose a solution redesign for the project

B.

Perform risk analysis against the issue.

C.

Revise the project's quality control measurements

D.

Develop a mitigation based on the solution design

Full Access
Question # 568

A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.

What should the project manager do?

A.

Implement the agile risk manifesto to ensure the proper tracking, analysis, and remediation of the project risks.

B.

Ask the product owner to act as a risk manager to assist with the remediation of risks.

C.

Implement the role of an agile risk manager to take care of the risk management process.

D.

Follow the risk management process while ensuring that risks are identified, analyzed, and managed during each iteration.

Full Access
Question # 569

A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is

frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.

What should the project manager do?

A.

Request that the team identifies, documents, and registers the issues to locate the source of the problems.

B.

Evaluate the cost and schedule variance in order to determine how much the project is off track.

C.

Ask the team to commit to a new date to fix all the problems and proceed with a change request to adjust the baseline.

D.

Request that a senior subject matter expert (SME) be hired to analyze and solve the problems.

Full Access
Question # 570

During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.

The customer is asking the project manager for guidance.

What should the project manager do?

A.

Wait to start the project execution phase until all requirements and acceptance criteria are clear.

B.

Ask the customer to include all of the requirements in the project charter to officially start the project planning phase.

C.

Schedule a brainstorming session and select the top ten most important requirements.

D.

In the planning meeting, focus on releasing a minimum viable product (MVP) quickly and getting feedback from the end users.

Full Access
Question # 571

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

A.

Ask the team.to accelerate the iterations and avoid interruptions.

B.

Discuss the problem with the team and decide how to do the work together.

C.

Verify team performance and ask for improvement during daily standup meetings.

D.

Recommend that the project sponsor increases the budget to bring new resources.

Full Access
Question # 572

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

A.

Review the base model with the team leaders in each country to establish anindependent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of differentcultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

Full Access
Question # 573

In an agile project, the project manager notices that one team member rarely reports blockers during daily check-ins. Additionally, the team member is too shy to participate in team activities and prefers to provide status updates individually to the project manager.

How should the project manager rectify this situation?

A.

Review team culture and the personality traits of the individual to address status update gaps.

B.

Create a safe space for status updates and encourage the team to approach the project manager.

C.

Review the team status updates more thoroughly to address the gaps.

D.

Support team inclusion and change the format of status updates to email.

Full Access
Question # 574

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

A.

Initiated requirements planning to analyze, document, and manage requirements

B.

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.

Implemented the change request process to harness change to the stakeholders’ advantage

D.

Used progressive elaboration to enhance the scope management plan with additional details

Full Access
Question # 575

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.

What should the project manager have done to avoid this situation?

A.

Ensured the project repository is up to date.

B.

Updated the job descriptions for all team roles.

C.

Provided specialist training for all team members.

D.

Made an effort to reemploy the senior project team member.

Full Access
Question # 576

A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders

What document should the project manager use to communicate these requests?

A.

Risk log

B.

Change log

C.

Backlog

D.

Issue log

Full Access
Question # 577

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

A.

Consider cultural differences among stakeholders.

B.

Conduct an integration meeting among all stakeholders.

C.

Schedule communication training for management-level stakeholders.

D.

Understand how political aspects can affect the project.

Full Access
Question # 578

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?

A.

Update the assumptions log and change log, and implement the change control process.

B.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.

Deliver what was planned in the project management document according to the specifications.

Full Access
Question # 579

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

A.

Organize a planning session with the development team and use their estimations to complete the schedule.

B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.

C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.

D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.

Full Access
Question # 580

At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?

A.

Stop the meeting and reschedule for another time with a more concise presentation.

B.

Set up information review sessions before reconvening another approval session.

C.

Get approval and promise to email more information to the stakeholders to clarify the technical details.

D.

Obtain approval as fast as possible and close the meeting.

Full Access
Question # 581

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?

A.

Monitor the interactions between the vendor and infrastructure manager going forward.

B.

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.

C.

Escalate the issue to the sponsor so appropriate action can be taken.

D.

Instruct the vendor to correct the problem without additional arguments.

Full Access
Question # 582

A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team's productivity.

What should the project manager do next?

A.

Review the iteration duration with the team.

B.

Discuss the issue in the next retrospective.

C.

Encourage the team to improve their performance.

D.

Reduce the iteration backlog.

Full Access
Question # 583

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

A.

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.

Create a dedicated sprint to complete all of the pending specifications from previous sprints.

Full Access
Question # 584

Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?

A.

Discuss the issue with the project sponsor.

B.

Review the resources required for the tasks on the critical path.

C.

Review and update the risk management plan.

D.

Allocate resources to develop the competencies of the other team members

Full Access
Question # 585

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?

A.

Create an entry in the impediment board and assign it.

B.

Invite the project team to a swarming session to define a solution

C.

Leverage the network of the former department and ask for help

D.

Escalate the issue to the product owner to define the next steps

Full Access
Question # 586

A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

A.

Ensure that relevant stakeholders and expectations are identified and assess the component delay.

B.

Perform a detailed analysis of the release content for each component of the solution.

C.

Propose a new design of the solution to replace the external component with an internal one.

D.

Ask for expedited delivery of the component to mitigate the risk of schedule delays.

Full Access
Question # 587

A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?

A.

Follow the change management process and work with procurement if needed

B.

Engage an arbitrator to resolve any conflict while handling the new requirement

C.

Add the change to the next sprint to meet the customer's needs

D.

Allocate resources to work on the new feature immediately to complete the request

Full Access
Question # 588

The portfolio management office wants to cut costs by suspending some ongoing

projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio

management office has not backed down on their plan.

What should the project manager do to continue the project?

A.

Meet with the project team and revise the project goals.

B.

Update the project charter to make it align with organizational strategy.

C.

Demonstrate the project alignment to the organizational strategy.

D.

Escalate the issue with the project sponsor to request support.

Full Access
Question # 589

A project manager has joined a company m an unfamiliar industry and has been given a strategically important project Being new, and not fully understanding the interdependences of the various departmental work items, the project manager is unsure of how to plan the project

How should the project manager proceed?

A.

Consult the project sponsor and request their feedback

B.

Consult the product owner and request a complete prioritization session

C.

Consult a senior project manager within the organization and request their expert judgement

D.

Consult a senior developer within the organization and request their input.

Full Access
Question # 590

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

A.

Accommodate the change request to serve the client's needs

B.

Consult with team members and allow them to make a decision

C.

Convince the client not to make changes to the project

D.

Make transactional decisions focusing on the project goals

Full Access
Question # 591

Close to the end of a project, a customer claims that some deliverables have not

been met and starts initiating change requests. What should the project manager do next?

A.

Refer to the requirements traceability matrix.

B.

Revise the project scope baseline.

C.

Escalate the change request to the project sponsor.

D.

Review the approved project charter.

Full Access
Question # 592

A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.

What should the project manager do?

A.

Report the violation to the change control board (CCB) and seek comprehensiveapproval for these modifications.

B.

Update the change management plan to define the level of control required forthese types of modifications.

C.

Ask the quality control team to evaluate the modifications, but take no actionbecause the associated quality risks are insignificant.

D.

Request the engineering team to update the specifications to reflect the modifications made by the contractor.

Full Access
Question # 593

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

A.

Apply fast-tracking techniques to compress the schedule of the critical project

B.

Analyze both projects to determine the most effective use of common resources

C.

Use resource optimization to justify requesting more resources for the critical project.

D.

Provide schedule optimization training to the project teams to improve their skills.

Full Access
Question # 594

Drag the technical practices on the left to the scenario on the right.

Full Access
Question # 595

After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.

What should the project manager do to prevent this frustration going forward?

A.

Request the human resource (HR) department to provide the key performance indicators (KPls) that were defined for this project.

B.

Set team performance goals and explain how the team receives the same performance scores.

C.

Review the key performance indicators (KPIs) for this team member and remind the team member how they are determined.

D.

Provide the team member with velocity tracking tools and explain how the team member can see and track performance.

Full Access
Question # 596

A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.

What should the project manager do?

A.

Inform the stakeholder that the new requirement will be considered in the next release planning session.

B.

Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.

C.

Ask the product owner to determine if this requirement needs to be treated as a top priority.

D.

Direct the development team to work on this requirement right away.

Full Access
Question # 597

A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.

What should the project manager do?

A.

Create a training schedule for the new team member to follow over the next few weeks.

B.

Escalate the inquiry to the team member's functional manager.

C.

Clarify the relevance of reviewing the documentation on the intranet.

D.

Ask a senior team member to help the new team member navigate through all the documentation.

Full Access
Question # 598

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

A.

Ensure that customer requirements do not change from the start of the project.

B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.

Ensure that the development and quality assurance team members implement the feature correctly.

D.

Ensure that the team facilitator allocates tasks correctly to team members.

Full Access
Question # 599

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

Full Access
Question # 600

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance

team is requesting a project budget for the new product.

What should the team do to address this request?

A.

Work with the finance team to transition to incremental budgeting.

B.

Request the finance team to allocate a budget based on historical data.

C.

Provide the budget to the finance team for only the planned increments.

D.

Extrapolate the budget based on the current cost performance index (CPI).

Full Access
Question # 601

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

A.

Stakeholders are satisfied with the current status.

B.

The project is under budget and on schedule

C.

The project is aligned with the project charter

D.

The protect is aligned with the benefits management plan

Full Access
Question # 602

An organization in a regulated industry has decided to switch from a predictive to

an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum,

and the project manager is still accountable for the project outcomes. During the fourth sprint

demo, the customer notices that a feature is not compliant with the regulations.

What should the project manager do?

A.

Have the team consult with the compliance officer to update the definition of done(DoD) for the user stories in the past sprint.

B.

Have the product owner consult with the change control board (CCB) to have thenecessary compliance requirements implemented.

C.

Have the scrum master organize a weekly meeting with the compliance officer, theproduct owner, and the project team.

D.

Have the product owner review the user stories in the product backlog with thecompliance officer on a regular basis to identify any gaps.

Full Access
Question # 603

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?

A.

Discuss with the product owner that the user story will not be completed this iteration.

B.

Meet with the team member's functional manager to try to remove the impediment.

C.

Tell the project team member not to work on the production issue and to inform their manager.

D.

Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.

Full Access
Question # 604

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

A.

Accept risks as they decrease over a period of time.

B.

Create a risk value profile to track the relative importance of risks.

C.

Log and track risks separately as only business value is important.

D.

Assess risks together with business value during prioritization.

Full Access
Question # 605

An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?

A.

Change the approach with the team.

B.

Meet with an agile coach to handle this issue.

C.

Analyze the level of the team's agile maturity.

D.

Support the team members' growth and development.

Full Access
Question # 606

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?

A.

Schedule a meeting between the team members to find a solution.

B.

Refer the team members to the project charter to resolve the conflict.

C.

Issue a new change request to evaluate this situation and communicate the result.

D.

Document the facts explained by the team members in the issue log.

Full Access
Question # 607

A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.

What should the project manager do first?

A.

Organize a conference call with the internal expert and the client to estimate the amount of effort required to fix it.

B.

Decline the request politely since the issue, although critical, is not the responsibility of the project team.

C.

Allocate a task to the team member as a high priority and inform the customer that the issue will be resolved the next day.

D.

Inform the customer that they should contact the sales manager and submit a formal request for a quote.

Full Access
Question # 608

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?

A.

Submit new user stories to the product owner in order to put documentation in the product backlog.

B.

Introduce a document management tool to support the agile teams in preparing the documentation.

C.

Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.

D.

Add an additional team member to take up the role of scribe for the required documentation.

Full Access
Question # 609

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)

A.

Create a change request to discuss with the change control board (CCB).

B.

Request additional budget for contingency.

C.

Perform a risk identification process with the project team.

D.

Consult with the project stakeholders.

E.

Discuss the possible impacts with subject matter experts (SMEs).

Full Access
Question # 610

Having managed a similar project while working with previous stakeholders, a

project team decided to use the same report format they used in the earlier project.

However, stakeholders new to the project are not fully comprehending the status of the

project based on the reports that are being circulated.

How should the project manager address this concern moving forward?

A.

Add the issue to the issue log and determine the corrective action.

B.

Create a fishbone diagram to determine the root cause for the misunderstanding.

C.

Employ Monitor Communications techniques, which may eventually trigger changes to the communications management plan.

D.

Share the communications management plan and remind all stakeholders of the agreed-upon reporting templates.

Full Access
Question # 611

At the end of the last iteration, the customer rejects the deliverables since they did

not meet the customer's expectations. What should the project manager have been done

to prevent this situation?

A.

Involved the customer more in the planning process for the project, and ensuredagreement on the proceedings.

B.

Included all relevant criteria in the agreed upon definition of done (DoD), and crafted a shared product vision.

C.

Provided the customer with the backlog and the specified user stories at the beginning of the iteration.

D.

Developed the DoD in close cooperation with all stakeholders to ensure their expectations were included.

Full Access
Question # 612

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

A.

Adjust the original budget estimates with the current cost variance.

B.

Negotiate the project changes and adjust stakeholder expectations.

C.

Perform a root cause analysis of the project performance.

D.

Review the activity duration to reforecast the project completion date.

Full Access