The figure given below demonstrates the communications model for a project. What role does component C play in the communication model?
You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?
In which of the following process groups does Integration Change Control Process fall?
You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?
Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?
Gary is the project manager of the NGH project for his organization. He and the project team have created the initial WBS. Before Gary and the project team begin creating the activity list, Gary wants the project team to help him create a unique numbering system for the deliverables identified in the WBS. What numbering system can Gary and the project team apply to the WBS to identify the components of the WBS?
Complete this sentence:
_________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.
Frank is the project manager of a construction project. In this project, Frank has elected to allow the interior design phase of the project to overlap with the pool construction phase of the project. Normally, Frank would not allow these two phases to overlap, but for this project, he has elected to do so in order to compress the project schedule. What is this schedule compression technique called?
A project team installs 2,500 light fixtures in a new office building, and each light fixture takes one hour to install. The project manager can predict that it will take 2,500 hours to complete the work. However, which of the following statements most accurately describes this parametric estimate assumption?
You work as the project manager for BlueWell Inc. You are reviewing and regulating the progress to meet the performance objectives defined in the project management plan. Mark, a trainee, has a doubt related to the inputs of monitor and control project work. Which of the following is the input to monitor and control project work?
Harry is the project manager of a large network installation project. This project requires Harry to add network cable to each office and cubicle of a 14-story office building. Harry will receive a bonus for good time and cost performance in this project. What law of economics would prevent Harry from exponentially adding labor to the project work in an effort to complete the work in a very small amount of time?
You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start-to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?
In which of the following group decision making techniques does the largest block in a group decide the group decision even if a bulk is not achieved?
Which of the following allows activities to be done in parallel that would normally be done in sequence?
Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?
You are the project manager for your organization. Maagement has asked you for this current project. You use the critical chain method to create the project network diagram rather than the more traditional critical path method. What is the critical chain method?
You are the project manager for your organization. You have worked with the project team to create the project scope statement. The key stakeholders have signed off on the project scope and they are eager for you and the project team to begin creating the deliverables identified within the project scope. What process must you and the project team complete next in this scenario?
You are the project manager for your organization. Your current project has a schedule variance of -$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance?
You work as a project manager for BlueWell Inc. You have to identify the specific actions to be performed to produce the project deliverables. For this, you have to explain the three inputs for the define activities process to your project team. Which of the following is NOT a valid input?
Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news. What is the most likely reason why management does not like an SPI of 2.12?
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?
Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance?
Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?
You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?
You are the project manager for the NHQ Project. Management has asked you to create a time estimate for this project although you have only just received the project charter. They would like some idea of how long the project will take based on the information in the project charter. While you are uncomfortable giving any type of estimate at this point, you work with your assigned project to create a quick time estimate. What type of estimate have you created for management?
Fill in the blank with an appropriate phrase. The_____ allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.
The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?
The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?
Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channels will Ben's project have next week?
Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?
You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?
Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?
You are the project manager for your organization. You are meeting with your customers to discuss the project performance. In this meeting, you will have eight project customers, the project sponsor, and ten members of your project team. What type of communication method are you using in this instance?
Mary is the project manager for her company. She's working with the project team to compress the project schedule as the project must be completed by December 30. For some of the project activities, she and the project team have agreed to crash the project work. What must be true of these project activities for crashing to be acceptable?
John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?
You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for this activity?
Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?
You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?
You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?
Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule performance index for this project?
Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?