A risk manager has been assigned to prepare a risk management plan for a new project. Which factor should the risk manager prioritize when tailoring the risk management processes for the new project?
in a complex and critical project, a sponsor asks the risk manager to determine where the project's concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.
Which tool could the risk manager use to discover the project risk categories?
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?
An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?
A risk manager is integrated into a team overseeing a crucial software development project. During the information gathering phase, the risk manager notices significant weaknesses in the maturity of the risk management process. The team needs to establish a more structured approach to managing risks, including the documentation of strategies, ownership structures, and details about the organization's project risk baseline.
What should the risk manager do?
A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?
As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.
What additional information should the risk manager prioritize in the risk register updates?
When should the benefits of quantitative risk analysis be weighed against the effort required to ensure that the additional insights and value justify the extra effort?
A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.
Which data analysis tool should the risk manager use to forecast future performance?
A major data center initiative involves performing a sensitivity analysis to determine the center's required amount of disaster recovery. Several key stakeholders are in disagreement about which level of disaster recovery is required. The lessons learned disaster recovery plans, and the difference for this data center is its geographical location and unique climate requirements. The database includes examples from previous similar initiatives, as well as the competitor's advertised plans.
What should the risk manager do to quantify the risk?
A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?
The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?
A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?
Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.
How should the risk manager proceed?
An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.
What should the risk manager do next?
The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project's budget, potentially increasing the duration by two weeks.
What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?
The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks; however, some of the risk response strategies created secondary risks.
What should the risk management team have done to manage this situation?
A project team successfully implemented a risk response plan for a major risk event. Residual risks were evaluated and actions were taken to keep them under control. There were no secondary risks after the implementation.
What should the risk manager do?
A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?
A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.
Which analytical tool should the risk manager use?
The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.
How should this documentation be utilized in the future?
When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.
What should the risk manager complete first?
A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.
What should the risk manager do first?
A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?
The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.
How should the risk manager document the impact of the residual risk?
Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.
What should the risk manager do next?
The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.
What should the project manager do regarding those risks?
During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.
What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?
The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.
What should be the risk manager's next step?
In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.
In implementing this plan, which response should the risk manager use?
During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?
An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.
What should the risk owner do?
A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)
The project’s customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?
A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.
What is the expected outcome of developing the risk management plan?
A project manager has requested the risk manager's support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.
What should the risk manager recommend?
A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?
In the middle of a project to improve internal workflows, the team realizes that some previously identified challenges, such as lack of stakeholder engagement, have diminished. However, the risk manager determines that concerns related to resource availability and regulatory compliance are becoming more significant.
Which measures should the risk manager implement?
While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.
What should the risk manager do to manage this risk?
The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.
What should the risk manager do?
A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?
An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.
What should the risk manager do next?
After completing the sprint on an agile project, a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project's risk exposure to an acceptable level?
Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?
A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.
Which type of analysis should the project manager use in this instance?
Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?
During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.
What should the risk manager do next to understand the differences between planning and execution?
A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.
What should the project manager have done differently?
A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.
What should the project manager do?
During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.
What could have been done during project planning to avoid overspending?
During a project's initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk's likelihood and impact with the risk manager.
What should the risk manager do?
A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project's total duration.
After analyzing the quantitative analysis results, which activity should the team pay more attention to?
Use the chart for the analysis.
A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.
Which technique should the risk manager use?
A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?
A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.
What type of risk is being referred to here?
A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.
What should the risk manager of the related project have done to prevent this situation from happening?
During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?
A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.
What should the risk manager do first?
A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?
A project manager for a large product development project assigned a risk manager to perform the risk management. The project sponsor questions why this project requires a risk manager as it is similar to a previous project with a developed risk strategy.
How should the risk manager explain the need for a risk strategy specific to this project?
A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.
What type of risk response is this?
A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project's technical debt and meet the project deadline.
What should the risk manager advise the project manager to do to address this situation?
The project manager wants to use an objective method to evaluate the key project risks and develop response plans.
What action should the risk manager propose?
In a complex project, individual risks have been identified with the stakeholders. The project sponsor asks the risk manager about the likelihood of project success. Which risk analysis tool(s) should the risk manager use as a basis for their response?
In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.
How should the project manager address this concern with the health authorities?
A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:
1 = Very Low
2 = Low
3 = Medium
4 = High
5 = Very High
What type of risk analysis is the risk manager performing?
At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization's business functions are not properly identified and categorized, making it difficult to develop an effective risk response.
How should the project manager handle this situation?
A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.
What should the risk manager advise the team to do first?
In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.
Which technique is the risk manager using?
A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.
What should the risk manager do first to understand the impact on project cost?
A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices.
What should the risk manager do?
A company has been awarded a large government contract to develop a new transportation system. There is uncertainty surrounding the project's timeline. The project team is struggling to finalize the project's budget due to unclear estimates from vendors. An updated vendor price list detailing the costs of available technologies is an essential component in determining the project's final cost. The project team will not be able to finalize the project's timeline until the budget is finalized.
What should the risk manager do?
During a virtual workshop presenting a product to potential clients, a facilitator emails the product brochure and asks attendees to check their spam folder if the email does not appear in their inbox. What kind of threat strategy is the facilitator applying?