Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: myex65

Home > CompTIA > Project+ > PK0-005

PK0-005 CompTIA Project+ Certification (2025) Question and Answers

Question # 4

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Full Access
Question # 5

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

C)

D)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 6

A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

A.

Build

B.

Subscription

C.

Lease

D.

Buy

Full Access
Question # 7

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

A.

Quote

B.

Information

C.

Proposal

D.

Bid

Full Access
Question # 8

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

A.

Kanban board

B.

Pareto chart

C.

Ishikawa diagram

D.

Decision tree

Full Access
Question # 9

Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Full Access
Question # 10

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

A.

Resource allocation

B.

Communication security

C.

Technological factors

D.

Cultural differences

Full Access
Question # 11

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

A.

Development

B.

Production

C.

Testing

D.

QA

Full Access
Question # 12

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?

A.

RFP

B.

WBS

C.

SLA

D.

SOW

Full Access
Question # 13

Which of the following contract types in project procurement has the highest risk for the buyer?

A.

Time and material

B.

Cost-plus

C.

Fixed-price

D.

Unit price

Full Access
Question # 14

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

A.

Work breakdown structure

B.

Project charter

C.

Quality plan

D.

Solution design

Full Access
Question # 15

Which of the following is the best example of CapEx?

A.

Taxes

B.

Vehicles

C.

Salaries

D.

Utilities

Full Access
Question # 16

Which of the following best represents an intellectual property breach?

A.

Internal developers use code from a legacy in-house system to develop a new solution for the marketing department.

B.

The price list to end customers was stored on a stolen external hard drive.

C.

A service provider that worked on a project uses the developed software on a project for a new customer.

D.

Customer data is stored on a shared network drive that is accessible by employees from all departments.

Full Access
Question # 17

Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?

A.

Percentage of controls with identified business owners

B.

Percentage of risk investments with defined business cases

C.

Ratio of control cost to operational budget

D.

Senior management satisfaction scores related to the security program

Full Access
Question # 18

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to

identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?

A.

Meeting chat

B.

Email

C.

Real-time survey

D.

Whiteboard

Full Access
Question # 19

Which of the following is the most important activity for the project manager during the closure of a project?

A.

Obtain project sign-off.

B.

Capture lessons learned.

C.

Document historical information.

D.

Release resources.

Full Access
Question # 20

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

A.

Start-to-finish

B.

Finish-to-finish

C.

Finish-to-start

D.

Start-to-start

Full Access
Question # 21

A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).

A.

Formal

B.

Internal

C.

Informal

D.

Verbal

E.

Indirect

F.

External

Full Access
Question # 22

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

A.

Some work packages are missing from the WBS.

B.

Information is missing from the RACI matrix.

C.

New knowledge bases were introduced.

D.

Team touch points are missing.

Full Access
Question # 23

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

A.

Notify customers the downtime will take longer than expected.

B.

Add new team members to help speed up validation.

C.

Begin executing the rollback plan.

D.

Record the issue and proceed with the implementation.

Full Access
Question # 24

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

A.

Update the WBS.

B.

Escalate to the CCB.

C.

Accept the change.

D.

Implement the change.

Full Access
Question # 25

After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

A.

Smoke test

B.

Stress test

C.

Penetration test

D.

Regression test

Full Access
Question # 26

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

A.

Review the detailed plan.

B.

Develop a preliminary scope.

C.

Develop a transition plan.

D.

Develop a project management plan.

E.

Review the resource pool.

F.

Review the project objectives.

Full Access
Question # 27

A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).

A.

Update the issue log

B.

Create a project charter

C.

Validate the status report

D.

Monitor performance

E.

Approve deliverables

F.

Baseline the project schedule

Full Access
Question # 28

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

A.

Business collaboration tool

B.

Email

C.

Virtual meetings

D.

Enterprise CMS

Full Access
Question # 29

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

Full Access
Question # 30

Which of the following items must be protected as Pll? (Select TWO).

A.

Job title

B.

Home address

C.

Work phone number

D.

Time zone

E.

Date of birth

F.

Blood type

Full Access
Question # 31

A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?

A.

Perform a gap analysis.

B.

Escalate the issue.

C.

Submit a change request.

D.

Approve deliverables.

Full Access
Question # 32

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Full Access
Question # 33

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

A.

Executing the approved contingency plan

B.

Constructing an Ishikawa diagram to determine the root cause

C.

Using a Pareto chart to prioritize the different causes

D.

Engaging the senior management team in regard to the issue

Full Access
Question # 34

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

A.

Inform the CCB to stop communication.

B.

Establish a RACI matrix.

C.

Escalate the communication issues.

D.

Revise the communication plan.

Full Access
Question # 35

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

A.

laaS

B.

XaaS

C.

PaaS

D.

SaaS

Full Access
Question # 36

A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?

A.

Cultural differences

B.

Technological factors

C.

Time zones

D.

Language barriers

Full Access
Question # 37

While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?

A.

It highlights the performance issues of the project manager and team members.

B.

It lets the project manager know which stakeholders are allies for future projects.

C.

It helps the project manager create a more structured lessons-learned session.

D.

It identifies the stakeholders' real opinions about the project.

Full Access
Question # 38

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

A.

Creating a backlog

B.

Managing the quality of deliverables

C.

Updating the issue log

D.

Performing a risk assessment

E.

Validating the deliverables

F.

Reconciling the project budget

Full Access
Question # 39

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

A.

Regression testing

B.

Smoke testing

C.

Stress testing

D.

Automation testing

Full Access
Question # 40

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

Full Access
Question # 41

During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?

A.

Work breakdown structure

B.

Change log

C.

Project success criteria

D.

Milestone chart

Full Access
Question # 42

After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?

A.

Rollback plan

B.

Release plan

C.

Deployment plan

D.

Contingency plan

Full Access
Question # 43

Which of the following BEST identifies the intent and purpose of a project closeout report?

A.

To provide documentation of lessons learned

B.

To document variances from the initial project baseline

C.

To validate that a project has been successfully completed

D.

To release resources and terminate all access rights

Full Access
Question # 44

In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

A.

Developing a RACI

B.

Identifying and assessing stakeholders

C.

Assigning project resources

D.

Establishing communication channels

Full Access
Question # 45

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

A.

Waterfall method

B.

Simulation method

C.

Precedence diagramming method

D.

Cost ratio analysis

Full Access
Question # 46

A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

13 days and $3,600

Full Access
Question # 47

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Full Access
Question # 48

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Full Access
Question # 49

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Full Access
Question # 50

While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

A.

Instruct the team members to set their speakers to maximum volume and mute their microphones.

B.

Require everyone to turn on their cameras and use the same background filter.

C.

Encourage the use of the chat and use plain language when speaking.

D.

Allow one person to speak at a time after receiving acknowledgment from the facilitator.

Full Access
Question # 51

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

A.

Project scope

B.

Quality plan

C.

Contract obligations

D.

Work breakdown structure

Full Access
Question # 52

During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?

A.

Baseline

B.

RBS

C.

WBS

D.

Milestones

Full Access
Question # 53

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Full Access
Question # 54

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

A.

Use an on-premises project management scheduling tool.

B.

Limit access to members of the project team.

C.

Mandate overtime to get the project completed sooner.

D.

Ensure all team members have signed a non-disclosure agreement.

Full Access
Question # 55

Which of the following software programs would be BEST to use lo store information related to business transactions?

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Full Access
Question # 56

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

Full Access
Question # 57

A manufacturing company is experiencing a high number of defects in its products and wants to identify the root cause to improve its processes Which of the following should the company use?

A.

Run charts

B.

Fishbone/lshikawa diagrams

C.

Scatter plot

D.

Decision tree

Full Access
Question # 58

Which of the following communication methods would be the most appropriate to finalize the handoff of deliverables?

A.

A virtual meeting with all the stakeholders

B.

A face-to-face kickoff meeting with the stakeholders

C.

A closure meeting with the project team and stakeholders

D.

A final report submitted via email to the stakeholders

Full Access
Question # 59

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Full Access
Question # 60

Which of the following situations would require a project manager to revise the communication plan during a project's execution?

A.

A change is approved that impacts the project schedule and budget

B.

The test results are not as expected

C.

The team is unclear which meetings they should attend

D.

A stakeholder requests some changes to the scope

Full Access
Question # 61

A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?

A.

Discovery

B.

Execution

C.

Initiating

D.

Planning

Full Access
Question # 62

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

A.

Forcing

B.

Avoiding

C.

Compromising

D.

Smoothing

Full Access
Question # 63

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Full Access
Question # 64

Which of the following is a typical characteristic of Scrum?

A.

Large teams

B.

Low-risk scope

C.

Self-organized team

D.

Well-defined scope

Full Access
Question # 65

Which of the following provides the best justification for undertaking a project?

A.

Scope statement

B.

Business case

C.

Sponsor request

D.

Project charter

Full Access
Question # 66

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

A.

Social engineering

B.

Phishing

C.

Spoofing

D.

Hacking

Full Access
Question # 67

A project team has implemented a new system and needs to ensure it is usable. Which of the following should be performed first?

A.

Provide end-user training.

B.

Decommission old systems.

C.

Release external consultants.

D.

Monitor performance.

Full Access
Question # 68

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Full Access
Question # 69

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

A.

Assign more resources to complete similar stories in the future.

B.

Break the stories into workable items that can be completed within one sprint.

C.

Extend the sprint duration when required with the approval of the product owner.

D.

Release the current progress into production and carry over the rest of the code for the next sprint.

Full Access
Question # 70

Which of the following offers administrators more direct control over operating systems?

A.

Infrastructure as a service

B.

Software as a service

C.

Functions as a service

D.

Platform as a service

Full Access
Question # 71

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Full Access
Question # 72

To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?

A.

Process moving

B.

Brainstorming

C.

Interview

D.

Focus group

Full Access
Question # 73

A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?

A.

Consult with the legal department.

B.

Update the issue log.

C.

Start a new RFP immediately.

D.

Perform a PERT analysis.

Full Access
Question # 74

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

A.

Planning

B.

Initiating

C.

Controlling

D.

Executing

Full Access
Question # 75

A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

A.

Agile

B.

SDLC

C.

Waterfall

D.

PRINCE2

Full Access
Question # 76

Which of the following should be considered first when determining the privacy management for project data?

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Full Access
Question # 77

A project manager has noticed that one-hour status calls are consistently lasting an extra 10 to 15 minutes. Which of the following techniques would be best for the project manager to use?

A.

Meeting minutes

B.

Action items

C.

Timeboxing

D.

Follow-up notes

Full Access
Question # 78

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

A.

Evaluating the project

B.

Releasing the resources

C.

Closing the contracts

D.

Reconciling the budget

Full Access
Question # 79

Which of the following aspects are true of waterfall as compared to agile? (Select two).

A.

Waterfall is composed of smaller teams working together

B.

Waterfall reinforces customer collaboration

C.

In waterfall, solution validation occurs later in the development cycle.

D.

In waterfall, working software is more of a focus than comprehensive documentation.

E.

Waterfall is less tolerant to changes in scope.

F.

Waterfall is made up of sprints

Full Access
Question # 80

Which of the following is the best alternative to allow multiple users to edit a project plan in real time?

A.

Send the file through email as an attachment

B.

Share access to the file on a wiki knowledge base.

C.

Access the file through an online application.

D.

Schedule an in-person meeting to review the plan

Full Access
Question # 81

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

A.

Exploit the risk.

B.

Accept the risk.

C.

Avoid the risk.

D.

Transfer the risk.

Full Access
Question # 82

During a gate review meeting, the deliverable was rejected by the customer.

INSTRUCTIONS

Review the dashboard.

• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.

• Part 2: Select the proper document(s) to be updated.

If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Part 1:

Part 2:

Full Access
Question # 83

A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?

A.

The project closeout report

B.

A handover to operations

C.

Phase-gate review documentation

D.

A transition plan

Full Access
Question # 84

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Full Access
Question # 85

A quality assurance team is based in three different locations To validate the project deliverables, a project manager sent the hardware for testing purposes to the team in each of the locations. Two teams confirmed the hardware arrived, but one group did not receive it because of local customs Which of the following ESG factors is the project team facing?

A.

Awareness of the company vision, mission statement, and values

B.

Impact of the project on the company's brand value

C.

Awareness of applicable regulations and standards

D.

Impact of the project on the local and global environments

Full Access
Question # 86

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Full Access
Question # 87

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Which of the following is the current status of the process?

A.

Based on the rule of seven, the process is under control

B.

The amount of data is insufficient to determine if quality is low.

C.

The process is out of control and should be revised.

D.

The goal should be adjusted since most of the data points are close to the lower limit.

Full Access
Question # 88

A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

Based on the chart, which of the following is the current status of the project?

A.

Behind schedule and over budget

B.

Behind schedule and under budget

C.

Ahead of schedule and over budget

D.

Ahead of schedule and under budget

Full Access
Question # 89

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

Full Access
Question # 90

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

A.

Issue log

B.

Risk register

C.

Defect log

D.

Traceability matrix

Full Access
Question # 91

How does data discovery assist with data classification'?

A.

It shows where specific data is stored

B.

It automatically classifies data by keywords

C.

It helps to identify the data owner

D.

It provides assurance of data integrity

Full Access
Question # 92

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

A.

Change the precedence of the tasks to "finish-to-start".

B.

Evaluate and modify the schedule with a burndown chart

C.

Assign additional resources to prevent overwork.

D.

Perform critical path analysis

Full Access
Question # 93

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

A.

Trigger the contingency plan and communicate with the stakeholders.

B.

Work with the functional managers to create a work-around.

C.

Submit a change request to the change control board.

D.

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.

Set up an escalation meeting with the sponsor.

Full Access
Question # 94

A retail store is rolling out a new point-of-sale solution to several locations where the staff members normally use cash registers. Which of the following activities will best assist staff members with integrating this new solution? (Select two).

A.

Documentation

B.

Team collaboration

C.

Gap analysis

D.

Training sessions

E.

Touch points

F.

Progress monitoring

Full Access
Question # 95

Which of the following is the focus of DevSecOps?

A.

Securing, testing, and maintaining new software

B.

Developing, testing, and maintaining software

C.

Developing, maintaining, and securing software

D.

Developing, securing, and testing software

Full Access
Question # 96

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

Full Access
Question # 97

Which of the following demonstrates awareness of regulations and standards when conducting a project?

A.

Establishing a measurement system for the team members' performance

B.

Controlling project costs to fall within the company-approved variance

C.

Reviewing advertising trends in the market before launching a new product

D.

Submitting architectural plans for approval before commencing construction

Full Access
Question # 98

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Which of the following most likely represents the number of items in the backlog?

A.

23

B.

5

C.

10

D.

15

Full Access
Question # 99

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Full Access
Question # 100

A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

A.

Bringing attention to the project sponsor

B.

Sharing lessons learned

C.

Collecting feedback

D.

Celebrating the team's hard work

Full Access
Question # 101

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

A.

RFB

B.

RFQ

C.

RFI

D.

RFP

Full Access
Question # 102

A project manager is working on an existing, large, complex project that involves regulatory and environmental considerations. The development of a detailed project plan will be critical. Which of the following should the project manager do first?

A.

Review the project charter.

B.

Start the process of engaging the stakeholders.

C.

Arrange a kickoff meeting.

D.

Evaluate potential risks.

Full Access
Question # 103

Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?

A.

Project status report

B.

Project evaluation review

C.

Project management software

D.

Requirements traceability matrix

Full Access
Question # 104

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?

A.

Reviewing project blockers

B.

Defining roles and responsibilities

C.

Establishing a project schedule

D.

Determining a project budget

Full Access
Question # 105

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Full Access
Question # 106

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

Full Access
Question # 107

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

A.

Escalate the communication issues.

B.

Implement a communication platform.

C.

Review the communication plan.

D.

Talk with the head of the PMO.

Full Access
Question # 108

Which of the following best represents the project impact to a company's brand value?

A.

The project is compliant with local and state laws and becomes the standard for new projects.

B.

The project promotes new initiatives to expand its benefit to other communities.

C.

The project exceeds the sales quota for the third quarter and raises the bar for next periods.The project meets the expected milestones and finishes on time and within budget.

Full Access
Question # 109

Which of the following best explains the importance of artifacts during the discovery/concept preparation phase of a project?

A.

To develop a detailed project plan and timeline

B.

To enable a lessons learned session

C.

To identify and assess potential vendors for the project

D.

To ensure that all stakeholders have a shared understanding of the project's objectives

Full Access
Question # 110

A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Full Access
Question # 111

A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?

A.

A plan for capturing issues and conflicts in a project's knowledge base

B.

A plan for avoiding potential issues that may arise during project execution

C.

A plan for documenting the outcomes of the project

D.

A plan for addressing and resolving identified issues once the project has been completed

Full Access
Question # 112

A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

A.

Status report

B.

Project plan

C.

Change log

D.

Meeting minutes

Full Access
Question # 113

Which of the following is a capital expense?

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Full Access
Question # 114

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Full Access
Question # 115

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

A.

Sprint retrospective

B.

Sprint review

C.

Sprint planning

D.

Daily Scrum

Full Access