Summer Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 28522818

Home > CompTIA > Project+ > PK0-005

PK0-005 CompTIA Project+ Certification (2024) Question and Answers

Question # 4

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Full Access
Question # 5

Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?

A.

Percentage of controls with identified business owners

B.

Percentage of risk investments with defined business cases

C.

Ratio of control cost to operational budget

D.

Senior management satisfaction scores related to the security program

Full Access
Question # 6

Which of the following items must be protected as Pll? (Select TWO).

A.

Job title

B.

Home address

C.

Work phone number

D.

Time zone

E.

Date of birth

F.

Blood type

Full Access
Question # 7

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

A.

Resource allocation

B.

Communication security

C.

Technological factors

D.

Cultural differences

Full Access
Question # 8

A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?

A.

Milestone chart

B.

Work breakdown structure

C.

Project charter

D.

Detailed scope statement

Full Access
Question # 9

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Full Access
Question # 10

A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?

A.

Integrity

B.

Security

C.

Archival

D.

Lessons learned

Full Access
Question # 11

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

A.

Transfer

B.

Mitigate

C.

Avoid

D.

Accept

Full Access
Question # 12

A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?

A.

Identify and assess stakeholders.

B.

Hold daily status meetings.

C.

Remove access and plan the project sign-off.

D.

Review assumptions and constraints for input to the risk register.

Full Access
Question # 13

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish

Full Access
Question # 14

Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

A.

Send out a survey to the potential end users to gather information about the best functional setup for work productivity.

B.

Provide clear instructions based on personal preference and aesthetics for setup of the work areas.

C.

Explain to team members that the placement of the items is not too important, as long as everything is connected and working.

D.

Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

Full Access
Question # 15

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Full Access
Question # 16

Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?

A.

Storage project

B.

Computer services project

C.

Database project

D.

Multitiered architecture project

Full Access
Question # 17

Which of the following is a reason to use a SOW on a project?

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Full Access
Question # 18

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

Full Access
Question # 19

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

A.

Each feature will have a different owner.

B.

The majority of the team can only meet on a weekly basis.

C.

The stakeholders have provided a specific deadline to meet.

D.

Each feature has a specific budget allocation.

Full Access
Question # 20

A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

A.

Change log

B.

Issue log

C.

Risk register

D.

Defect log

Full Access
Question # 21

Which of the following statements best represents a network issue?

A.

The development team on the fourth floor is unable to access servers and email services.

B.

Cell phones served by a specific telecom company are getting a "no service" message.

C.

A user cannot connect to Wi-Fi because of a wrong ID or password.

D.

A user is receiving an automatic reply message saying that an email address does not exist.

Full Access
Question # 22

A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?

A.

Planning

B.

Closure

C.

Initiation

D.

Execution

Full Access
Question # 23

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

Full Access
Question # 24

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Full Access
Question # 25

A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?

A.

Milestone chart

B.

Gantt chart

C.

PERT chart

D.

WBS

Full Access
Question # 26

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

Full Access
Question # 27

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

A.

Synchronous

B.

Informal

C.

Asynchronous

D.

Formal

Full Access
Question # 28

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

A.

negotiating resources.

B.

assigning resources.

C.

assessing the resource pool.

D.

adding resources to the schedule.

Full Access
Question # 29

Which of the following statements best describes a content management system?

A.

A system to manage electronic signatures and document workflow

B.

A system to manage database integration and provide messaging services

C.

A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish

D.

A system to manage documents archival, such as emails, spreadsheets, and support tickets

Full Access
Question # 30

A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?

A.

Train the team members.

B.

Assess the resource pool.

C.

Develop a QA plan.

D.

Create RACI matrix.

Full Access
Question # 31

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

A.

Reassigning resources

B.

Removing access

C.

Closing contracts

D.

Evaluating the project

Full Access
Question # 32

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

Full Access
Question # 33

A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?

A.

ROI

B.

KPI

C.

RACI

D.

SOW

Full Access
Question # 34

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Full Access
Question # 35

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

Full Access
Question # 36

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

A.

Project scope

B.

Quality plan

C.

Contract obligations

D.

Work breakdown structure

Full Access
Question # 37

Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?

A.

Assign action items to attendees.

B.

Distribute an agenda.

C.

Email the minutes from the previous meeting.

D.

Schedule a convenient time.

Full Access
Question # 38

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

Full Access
Question # 39

Which of the following describes three-tier architecture?

A.

Conceptual, design, and implementation stages

B.

Presentation, application, and data processing

C.

Network, software, and security

D.

Development, testing, and production environment

Full Access
Question # 40

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

A.

Software as a service

B.

Infrastructure as a service

C.

Data as a service

D.

Platform as a service

Full Access
Question # 41

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

A.

ESG

B.

PHI

C.

Pll

D.

ROI

Full Access
Question # 42

A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

A.

Project transition

B.

Project management

C.

Project communications

D.

Project quality assurance

Full Access
Question # 43

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Which of the following issues should be addressed FIRST?

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Full Access
Question # 44

A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?

A.

Application deployment

B.

Rollback plans

C.

Validation checks

D.

Maintenance window schedules

Full Access
Question # 45

A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?

A.

Avoid

B.

Transfer

C.

Accept

D.

Share

Full Access
Question # 46

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

A.

RFB

B.

RFQ

C.

RF

D.

RFP

Full Access
Question # 47

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

A.

Escalate directly to the project sponsor

B.

Push the kickoff meeting out by one week

C.

Proceed with the kickoff as planned

D.

Identity replacements for project stakeholders

Full Access
Question # 48

A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?

A.

Forming, storming, performing, norming, adjourning

B.

Forming, performing, storming, norming, adjourning

C.

Forming, norming, storming, performing, adjourning

D.

Forming, storming, norming, performing, adjourning

Full Access
Question # 49

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Full Access
Question # 50

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

A.

Quality assurance

B.

Organizational branding restrictions

C.

State privacy acts

D.

Country legal regulations

Full Access
Question # 51

While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?

A.

It highlights the performance issues of the project manager and team members.

B.

It lets the project manager know which stakeholders are allies for future projects.

C.

It helps the project manager create a more structured lessons-learned session.

D.

It identifies the stakeholders' real opinions about the project.

Full Access
Question # 52

A project team selected a random sample of patient accounts for testing the deliverable. The data was masked since it contained patient names. Which of the following describes this type of data?

A.

Confidential information

B.

Protected health information

C.

Personally identifiable information

D.

Security clearance

Full Access
Question # 53

After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

A.

Withdraw the offer to the candidate and raise this as a risk.

B.

Ignore a potential lawsuit since this is a critical project.

C.

Use a third-party company for the contract to legally avoid responsibility.

D.

Have a meeting with the project sponsor to discuss the situation.

Full Access
Question # 54

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

A.

Schedule

B.

Status report

C.

Issue log

D.

Task board

Full Access
Question # 55

During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?

A.

Obtain details from the owner of the project.

B.

Update the critical path for the project.

C.

Apply contingency reserves.

D.

Reestimate epic user stories.

Full Access
Question # 56

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

A.

Issue log

B.

Risk register

C.

Defect log

D.

Traceability matrix

Full Access
Question # 57

Which of the following tools is best to use for storing lessons learned?

A.

Whiteboard

B.

Wiki knowledge base

C.

Content management system

D.

Workflow platform

Full Access
Question # 58

A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

A.

Performance

B.

Smoke

C.

Regression

D.

Unit

Full Access
Question # 59

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

A.

Define the WBS.

B.

Develop a RAM.

C.

Manage the vendors.

D.

Assess the resource pool.

Full Access
Question # 60

A meeting agenda included the following items:

. Review the goals of the project.

. Review the progress of the project.

. Discuss if the project is ready to move forward.

Which of the following best describes this type of meeting?

A.

Stand-up

B.

Monthly status

C.

Gap analysis

D.

Gate review

Full Access
Question # 61

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

A.

A risk budget

B.

A risk impact

C.

A change request

D.

A contingency plan

Full Access
Question # 62

Which of the following tools is best to use when conducting project meetings across time zones?

A.

Text

B.

Calendaring tools

C.

Videoconference

D.

Email

Full Access
Question # 63

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

A.

Kanban board

B.

Pareto chart

C.

Ishikawa diagram

D.

Decision tree

Full Access
Question # 64

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Full Access
Question # 65

Which of the following should be considered first when determining the privacy management for project data?

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Full Access
Question # 66

A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?

A.

Resolution time

B.

Issue list

C.

Work breakdown structure

D.

Cost optimization

Full Access
Question # 67

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

A.

Update the WBS.

B.

Escalate to the CCB.

C.

Accept the change.

D.

Implement the change.

Full Access
Question # 68

A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?

A.

The retrospective session feedback was not communicated properly.

B.

The project resources were released ahead of time.

C.

The documentation was not archived as per the PMO standards.

D.

The validation of deliverables is running behind schedule.

Full Access
Question # 69

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

A.

Approving the change request

B.

Developing a rollback plan

C.

Gathering necessary resources

D.

Defining requirements

Full Access
Question # 70

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

A.

Use an on-premises project management scheduling tool.

B.

Limit access to members of the project team.

C.

Mandate overtime to get the project completed sooner.

D.

Ensure all team members have signed a non-disclosure agreement.

Full Access
Question # 71

A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?

A.

Cultural differences

B.

Technological factors

C.

Time zones

D.

Language barriers

Full Access
Question # 72

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Full Access
Question # 73

While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

A.

Instruct the team members to set their speakers to maximum volume and mute their microphones.

B.

Require everyone to turn on their cameras and use the same background filter.

C.

Encourage the use of the chat and use plain language when speaking.

D.

Allow one person to speak at a time after receiving acknowledgment from the facilitator.

Full Access
Question # 74

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Full Access
Question # 75

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

A.

Assemble a new project with existing resources.

B.

Obtain the final report from release management.

C.

Notify the functional manager that resources are released.

D.

Allocate resources in a different project

Full Access
Question # 76

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

A.

Data plan

B.

Contingency plan

C.

Rollback plan

D.

Recovery plan

Full Access
Question # 77

Which of the following PRINCE2 processes includes creating the project plan?

A.

Starting up a project

B.

Initiating a project

C.

Managing product delivery

D.

Directing a project

Full Access
Question # 78

A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?

A.

Pareto

B.

Scatter

C.

Network

D.

Fishbone

Full Access
Question # 79

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

A.

Trigger the contingency plan and communicate with the stakeholders.

B.

Work with the functional managers to create a work-around.

C.

Submit a change request to the change control board.

D.

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.

Set up an escalation meeting with the sponsor.

Full Access
Question # 80

Which of the following is a capital expense?

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Full Access
Question # 81

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

A.

Add a new risk.

B.

Perform an impact analysis.

C.

Escalate to the sponsor.

D.

Raise a change request.

Full Access
Question # 82

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

14 days and $4,000

Full Access
Question # 83

A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Full Access
Question # 84

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

A.

Start-to-finish

B.

Finish-to-finish

C.

Finish-to-start

D.

Start-to-start

Full Access
Question # 85

A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

A.

Secure folder

B.

Real-time, multiauthoring editing software

C.

Digital whiteboard

D.

Wiki knowledge base

Full Access
Question # 86

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?

A.

Reviewing project blockers

B.

Defining roles and responsibilities

C.

Establishing a project schedule

D.

Determining a project budget

Full Access
Question # 87

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

A.

Ishikawa diagram

B.

Scatter diagram

C.

Pareto chart

D.

Decision tree

Full Access