Under a framework agreement, which of the following are supplier selection mechanisms? Select TWO that apply:
XYZ Ltd is negotiating a long-term supply contract of important parts with a supplier. Dave, procurement manager teams up with Alla, legal manager to construct a service level agreement. Dave is concerned that poor performance of supplier may cause damages to the operations of the organisation. Which of the following can be used in conjunction with SLA to compensate the buying organisation in case of supplier's poor performance?
1. Warranties
2. Force majeure clauses
3. Penalty clauses
4. Service credits
GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.
Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.
Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?
Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.
Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.
Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.
Hank’s pre-contractual assurance is most likely to be an example of which of the following?
Infra Constructions receive a contract for construction of a building, and following terms were agreed upon. "The entire cost of the project will be reimbursed to Infra Constructions (estimated cost of the project being $ 25 million). The profits will be 20% of the entire cost of a project subject to a max of $ 5 million." This arrangement is an example of...?
Which of the following should be taken to avoid the conflicts between orally negotiated terms before the conclusion of contract and the final written contract?
Which of the following shall help the purchaser control the selection of tier 2 suppliers?
A large company supplies a lot of products. Their shipments are often delayed and customers are not satisfied. Which of the following KPIs is most likely to be applied to this situation?
Which of the following is the set of principles that enables courts to determine exactly what the written contract says and what that must mean, then the court will uphold that?
Which of the following should be taken to avoid the conflicts between orally negotiated terms before the conclusion of contract and the final written contract?
Which of the following is set down in statute as a liability that exists without any need to prove fault?
XYZ Ltd and Engineer Corp signed a long-term supply contract in which both parties had agreed on performance targets. Recently, due to increased customer demands, XYZ Ltd realises that they should make changes to the contract with Engineer Corp with regards to performance management. These changes are approved and signed by both the buyer and seller. The changes to the contract are known as...?
Transformers & Rectifiers Ltd wanted to buy some specialist gaskets. They sent a request for quotation with specification to Needs Ltd. The supplier replied with a quotation in which had its own terms and conditions. The buyer edited delivery terms on the quotation and sent the document back to Needs Ltd. Gaskets were delivered to Transformers’ premise with an invoice from Needs Ltd. Which of the following is most likely to be the governing terms if the two companies must settle the dispute at court?
Which of the following are most likely to be liabilities of suppliers under a guarantee clause? Select A. TWO that apply
B. Repair
C. Decommissioning
D. Upgrading
E. Replacement
F. Installation
In a contract, both buyer and supplier agreed the lead time is 3 days. The contract also requires that any variation must be made in writing. Then the buyer places an order by phone call and requests delivery the next day, but the supplier delivers on the third day since the order. Can buyer refuse to pay as supplier did not deliver per time?
If service level agreement is used as a schedule that makes up the contract, it will be most likely to be a part of...?
Which of the following is likely to reduce risks of different rules regarding when offers and acceptance become effective between legal systems?
Which of the following are true statements about RFQ process? Select TWO that apply.
If service level agreement is used as a schedule that makes up the contract, it will be most likely to be a part of...?
In common law, which of the following documents is legally binding without the need for consideration?
A construction company often subcontracts approximately 50% of the project works because of unpredictable customer's demand. Although larger corporate customers require quick response to RFQ, the time lapse between tender bid submission and contract commencement is usually long. Which of the following arrangement would benefit both the contractor and customer?
Southwark is negotiating a contract with Orchard to provide software and IT services. Orchard will manufacture and install the products which are contractually supplied by IBM. Southwark’s procurement manager is worried that during the contract there would be some problems that they would not able to claim for damages from Orchard. Which of the following should be included in the head contract so that Southward can sue IBM, should the need arise?
Which of the following are likely to be implied terms in a contract? Select TWO that apply: