Easter Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > BCS > ISTQB Certified Tester > CTFL4

CTFL4 ISTQB Certified Tester Foundation Level CTFL 4.0 Exam Question and Answers

Question # 4

A program is used to control a manufacturing line (turn machines on and off. start and stop conveyer belts, add raw materials to the flow. etc.). Not all actions are possible at all times. For example, there are certain manufacturing stages that cannot be stopped - unless there is an emergency. A tester attempts to evaluate if all such cases (where a specific action is not allowed) are covered by the tests.

Which coverage metric will provide the needed information for this analysis?

A.

Code coverage

B.

Data flow coverage

C.

Statement coverage

D.

Branch Coverage

Full Access
Question # 5

Consider a review for a high-level architectural document written by a software architect. The architect does most of the review preparation work, including distributing the document to reviewers before the review meeting. However, reviewers are not required to analyze the document in advance, and during the review meeting the software architect explains the document step by step. The only goal of this review is to establish a common understanding of the software architecture that will be used in a software development project.

Which of the following review types does this review refer to?

A.

Inspection

B.

Audit

C.

Walkthrough

D.

Informal review

Full Access
Question # 6

Which ONE of the following activities TYPICALLY belongs to the planning phase of the review process?

A.

A separate defect report is created for each identified defect so that corrective actions can be tracked.

B.

Each reviewer conducts an individual review to identify anomalies, recommendations, and questions.

C.

The purpose and scope of the review are defined, as well as the work product to be reviewed and the exit criteria.

D.

The reviewers analyze and discuss the anomalies found during the review in a joint meeting.

Full Access
Question # 7

Consider the following list of activities (I to V):

I. Test design

II. Test planning

III. Review test basis

IV. Be a facilitator of a peer review

V. Test monitoring and control

Which ONE of the following options identifies the activities that the test management role is MAINLY focused on?

A.

Activities III, IV, and V

B.

Activities II and V

C.

Activities I and V

D.

Activities I, III, and IV

Full Access
Question # 8

Which ONE of the following options MOST ACCURATELY describes the activities of “testing” and “debugging”?

A.

Testing triggers a failure that is caused by a defect in the software, whereas debugging is concerned with finding the causes of this failure (defects), analyzing these causes, and eliminating them.

B.

Testing triggers a failure that is caused by a defect in the software, whereas debugging is concerned with finding the causes of this failure (defects), analyzing these causes, and reproducing them.

C.

Testing identifies a defect that is caused by an error in the software, whereas debugging is concerned with finding the causes of this defect, analyzing these causes, and eliminating them.

D.

Testing triggers a defect that is caused by an error in the software, whereas debugging is concerned with finding the causes of this defect, analyzing these causes, and eliminating them.

Full Access
Question # 9

Which of the following are the phases of the ISTQB fundamental test process?

A.

Test planning and control, Test analysis and design, Test implementation and execution, Evaluating ex t criteria and reporting. Test closure activities

B.

Test planning, Test analysis and design. Test implementation and control. Checking test coverage and reporting, Test closure activities

C.

Test planning and control, Test specification and design. Test implementation and execution, Evaluating test coverage and reporting, Retesting and regression testing, Test closure activities

D.

Test planning. Test specification and design. Test implementation and execution. Evaluating exit criteria and reporting. Retesting and test closure activities

Full Access
Question # 10

Which of the following statements is incorrect regarding the involvement of testers in the software development lifecycle (SDLC)?

A.

Testers should contribute to all activities in the SDLC and participate in design discussions.

B.

Testers should be involved from the beginning of the SDLC to increase understanding of design decisions and detect defects early.

C.

Testers should only be involved during the testing phase.

D.

Testers' involvement is essential; developers find it difficult to be objective.

Full Access
Question # 11

A typical objective of testing is to

A.

Determine the most appropriate level of detail with which to design test cases.

B.

Verify the compliance of the test object with regulatory requirements.

C.

Plan test activities in accordance with the existing test policy and test strategy

D.

Verify the correct creation and configuration of the test environment

Full Access
Question # 12

Which of the following statements about error guessing is true?

A.

Error guessing is a system that adopts artificial intelligence to predict whether software components are likely to contain defects or not

B.

Experienced testers, when applying error guessing, rely on the use of a high-level list of what needs to be tested as a guide to find defects

C.

Error guessing refers to the ability of a system or component to continue normal operation despite the presence of erroneous inputs

D.

Experienced testers, when applying error guessing technique, can anticipate where errors, defects and failures have occurred and target their tests at those issues

Full Access
Question # 13

Which of the following statements is true?

A.

Experience-based test techniques rely on the experience of testers to identify the root causes of defects found by black-box test techniques

B.

Some of the most common test basis used by white-box test techniques include user stories, use cases and business processes

C.

Experience-based test techniques are often useful to detect hidden defects that have not been targeted by black-box test techniques

D.

The primary goal of experience-based test techniques is to design test cases that can be easily automated using a GUI-based test automation tool

Full Access
Question # 14

Which of the following answers describes a reason for adopting experience-based testing techniques?

A.

Experience-based test techniques provide more systematic coverage cnteria than black-box and white-box test techniques

B.

Experience-based test techniques completely rely on the tester's past experience for designing test cases.

C.

Experience-based test techniques allow designing test cases that are usually easier to reproduce than those designed with black-box and white-box test techniques.

D.

Experience-based test techniques tend to find defects that may be difficult to find with black-box and white-box test techniques and are often useful to complement these more systematic techniques.

Full Access
Question # 15

Which of the following is a test task that usually occurs during test implementation?

A.

Make sure the planned test environment is ready to be delivered

B.

Find, analyze, and remove the causes of the failures highlighted by the tests

C.

Archive the testware for use in future test projects

D.

Gather the metrics that are used to guide the test project

Full Access
Question # 16

Which of the following is a typical potential risk of using test automation tools?

A.

Reduced feedback times regarding software quality compared to manual testing.

B.

Reduced test execution limes compared to manual testing.

C.

Reduced repeatability and consistency of tests compared to manual testing

D.

Underestimation of effort required to maintain test scripts.

Full Access
Question # 17

Which of the following statements about exploratory testing is true?

A.

Exploratory testing is an experience-based test technique in which testers explore the requirements specification to detect non testable requirements

B.

When exploratory testing is conducted following a session-based approach, the issues detected by the testers can be documented in session sheets

C.

Exploratory testing is an experience-based test technique used by testers during informal code reviews to find defects by exploring the source code

D.

In exploratory testing, testers usually produce scripted tests and establish bidirectional traceability between these tests and the items of the test basis

Full Access
Question # 18

Which of the following statements refers to a good testing practice that applies to all software development lifecycles?

A.

Each test level should have its own specific test objectives that should be consistent with the software development lifecycle phase or type of activities it addresses.

B.

Test analysis and design for any test levels should begin as soon as coding is complete, and all system components are available for testing

C.

The most efficient and effective method of conveying information to and within a development team is face-to-face conversation.

D.

All the tests should be automated and run as part of the continuous integration process with every software change

Full Access
Question # 19

Your organization's test strategy states that it is desirable to usemore than one method for estimating test effort. You are responsible for estimating test effort for the next project. Based on historical data, thedevelopment-to-test effort ratiois5:3.

The initial estimate for thedevelopment effort is 450 person-days.

Which ONE of the following options corresponds to the estimatedtest effortusing the ratio-based method?

A.

750 person-days

B.

180 person-days

C.

720 person-days

D.

270 person-days

Full Access
Question # 20

The following rules determine the annual bonus to be paid to a salesman of a company based on the total annual amount of the sales made (referred to as TAS).

If the TAS is between 50k€ and 80k€, the bonus is 10%. If the TAS exceeds 80k€ by a value not greater than 40k€, the bonus is 15%. Finally, if the TAS

exceeds the maximum threshold which entitles to a 15% bonus, the bonus is 22%.

Consider applying equivalence partitioning to the TAS (Note: 1k€ = 1000 euros).

Which one of the following answers contain only test cases that belong to the same equivalence partition?

A.

TC1 = 81 k€; TC2= 97k€; TC3=111k€; TC4=118k€

B.

TC1 = 40k€; TC2= 46k€; TC3=51k€; TC4=53k€

C.

TC1 = 79k€; TC2= 80k€; TC3=81k€; TC4=82k€

D.

TC1 = 90k€; TC2= 110k€; TC3=125k€: TC4=140k€

Full Access
Question # 21

Which one of the following statements IS NOT a valid objective of testing?

A.

To build confidence in the level of quality of the test object.

B.

To find all defects in a product, ensuring the product is defect free.

C.

To find failures and defects

D.

To evaluate work products such as requirements, user stories, design, and code.

Full Access
Question # 22

Which two of the following statements describe the advantages provided by good traceability between the test basis and test work products?

I. Analyzing the impact of changes.

ii. A measure of code quality.

iii. Accurate test estimation.

iv. Making testing auditable.

Select the correct answer:

A.

i and ii

B.

i and iv

C.

i and iii

D.

ii and iii

Full Access
Question # 23

Which of the following statements refers to good testing practice to be applied regardless of the chosen software development model?

A.

Tests should be written in executable format before the code is written and should act as executable specifications that drive coding

B.

Test levels should be defined such that the exit criteria of one level are part of the entry criteria for the next level

C.

Test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly

D.

Involvement of testers in work product reviews should occur as early as possible to take advantage of the early testing principle

Full Access
Question # 24

Consider an estimation session in which a six-member Agile team (Memb1..... Memb6) uses the planning poker technique to estimate a user story (in story points). The team members will use a set of cards with the following values: 1,2, 3,5, 8,13,21. Below is the outcome of the first round of estimation for this session:

Which of the following answers BEST describes how the estimation session should proceed?

A.

The final estimate of the user story in story points is determined by applying the three-point estimation technique with the following input values most optimistic estimate - 1, most likely estimate - 3, and most pessimistic estimate - 21

B.

Further estimation rounds should be performed until all team members will pick the card having the same value: this value will represent the final estimate of the user story in story points.

C.

The final estimate of the user story in story points is determined by calculating the average value between the most optimistic estimate of 21 story points (Memb4> and the most pessimistic estimate of 1 story point (Memb6)

D.

Memb6 and Memb4 which have produced the most pessimistic and the most optimistic estimates respectively, should explain the reasons of their choices to stimulate a discussion between all members before proceeding to another estimation round

Full Access
Question # 25

Which of the following applications will be the MOST suitable for testing by Use Cases

A.

Accuracy and usability of a new Navigation system compared with previous system

B.

A billing system used to calculate monthly charge based or large number of subscribers parameters

C.

The ability of an Anti virus package to detect and quarantine a new threat

D.

Suitability and performance of a Multi media (audio video based) system to a new operating system

Full Access
Question # 26

Exploratory testing is an experience-based test technique

A.

Where a developer and a tester work together on the same workstation while the developer actively writes code, the tester explores the code to find defects.

B.

That can be organised into sessions guided by test charters outlining test objectives that will guide the testers' exploration

C.

Where a team of testers explores all possible test techniques in order to determine the most suitable combination of these techniques to apply for a test project.

D.

That aims at finding defects by designing tests that exercise all possible combinations of input values and preconditions

Full Access
Question # 27

Which TWO of the following are benefits of continuous integration?

I. Allows earlier detection and easier root cause analysis of integration problems and conflicting changes.

II. Removes the need for manual test analysis, design and execution.

Hi. Removes the dependency on automated regression packs when integrating larger systems, or components.

iv. Gives the development team regular feedback on whether the code is working.

Select the correct answer:

A.

i and iv

B.

i and ii

C.

i and iii

D.

iii and iv

Full Access
Question # 28

Which of the following lists factors That contribute to PROJECT risks?

A.

skill and staff shortages; problems in defining the right requirements, contractual issues.

B.

skill and staff shortages; software does not perform its intended functions; problems in defining the right requirements.

C.

problems in defining the right requirements; contractual issues; poor software quality characteristics.

D.

poor software quality characteristics; software does not perform its intended functions.

Full Access
Question # 29

Which of the following statements about white-box test techniques is true?

A.

Achieving full statement coverage and full branch coverage for a software product means that such software product has been fully tested and there are no remaining bugs within the code

B.

Code-related white-box test techniques are not required to measure the actual code coverage achieved by black-box testing, as code coverage can be measured using the coverage criteria associated with black-box test techniques

C.

Branch coverage is the most thorough code-related white-box test technique, and therefore applicable standards prescribe achieving full branch coverage at the highest safety levels for safety-critical systems

D.

Code-related white-box test techniques provide an objective measure of coverage and can be used to complement black-box test techniques to increase confidence in the code

Full Access
Question # 30

Following a risk-based testing approach you have designed 10 tests to cover a product risk with a high-risk level. You want to estimate, adopting the three-point test estimation technique, the test effort required to reduce the risk level to zero by executing those 10 tests. You made the following three initial estimates:

• most optimistic = 6 person hours

• most likely = 30 person hours

• most pessimistic = 54 person hours

Based only on the given information, which of the following answers about the three-point test estimation technique applied to this problem is true?

A.

The final estimate is between 22 person hours and 38 person hours

B.

The final estimate is exactly 30 person hours because the technique uses the initial most likely estimate as the final estimate

C.

The final estimate is between 6 person hours and 54 person hours

D.

The final estimate is exactly 30 person hours because the technique uses the arithmetic mean of the three initial estimates as the final estimate

Full Access
Question # 31

Which of the following statements is TRUE?

A.

User acceptance tests are usually automated and aim to verify the acceptance criteria for user stories

B.

Acceptance criteria for user stories can include details on data definitions, for example by describing the format, allowed values, and default values for a data item

C.

Acceptance criteria for user stones should focus on positive scenarios, while negative scenarios should be excluded

D.

Tests derived from acceptance criteria for user stories are not included in any of the four testing quadrants

Full Access
Question # 32

Which ONE of the following options MOST ACCURATELY describesstatement testing?

A.

In statement testing, the coverage items are control flow transfers between branches. The aim is to design test cases to exercise branches in the code until an acceptable level of coverage is achieved, expressed as a percentage.

B.

In statement testing, the coverage items are decisions and statements. The aim is to design test cases that exercise statements in the code until an acceptable level of coverage is achieved, expressed as a percentage.

C.

In statement testing, the coverage items are branches, and the aim is to design test cases to exercise branches in the code until an acceptable level of coverage is achieved, expressed as a percentage.

D.

In statement testing, the coverage items are executable statements. The aim is to design test cases that exercise statements in the code until an acceptable level of coverage is achieved, expressed as a percentage.

Full Access
Question # 33

Mark the correct sentences:

* Defects are a result of environmental conditions and are also referred to as "Failures"

* A human mistake may produce a defect

* A system mil totally fail to operate correctly when a failure exists in it

* When a defect exists in a system it may result in a failure

* Defects occur only as a result of technology changes

A.

II, IV

B.

I, II

C.

IV, V

D.

II, III, IV

Full Access
Question # 34

Which ONE of the following elements is TYPICALLY part of atest plan?

A.

The budget and schedule for the test project.

B.

A detailed analysis of the defects found and their causes.

C.

A detailed report on the test results after the test project is completed.

D.

A list of test logs from the test execution.

Full Access
Question # 35

Which of the following statements about the typical activities of a formal review process is TRUE?

A.

Individual review is only mandatory when the size of the work product under review is too large to cover at the review meeting

B.

Various review techniques that may be applied by participants during individual review are described in the ISO/IEC/IEEE 29119-3 standard.

C.

Choosing which standards to follow during the review process is usually made during review planning.

D.

One of the main goals of the review meeting is to make sure that all participants are aware of their roles and responsibilities in the review process

Full Access
Question # 36

Which statement is true regarding confirmation testing and regression testing?

A.

Confirmation testing confirms the quality of the test being run while regression testing ensures that the software still works after a change has been made.

B.

Confirmation testing is an optional activity whilst regression testing is not negotiable.

C.

Confirmation testing aims to verify that a defect has been resolved and regression testing ensuring that existing functionality still works after a change.

D.

Testers' involvement is essential whilst running retesting and regression testing.

E.

TESTER Involvement is essential whilst running retesting and regression testing.

Full Access
Question # 37

The statement: "Test activities should start in the early stages of the lifecycle, adhering to the testing principle of early testing” is relevant to which of the recognized software development models?

A.

Sequential development model.

B.

Iterative development model.

C.

Incremental development model.

D.

All the above

Full Access
Question # 38

Test automation allows you to:

A.

demonstrate the absence of defects

B.

produce tests that are less subject to human errors

C.

avoid performing exploratory testing

D.

increase test process efficiency by facilitating management of defects

Full Access
Question # 39

What type of testing measures its effectiveness by tracking which lines of code were executed by the tests?

A.

Acceptance testing

B.

Structural testing

C.

Integration testing

D.

Exploratory testing

Full Access
Question # 40

In which of the following test documents would you expect to find test exit criteria described9

A.

Test design specification

B.

Project plan

C.

Requirements specification

D.

Test plan

Full Access
Question # 41

Which of the following characterizations applies to a test tool used for the analysis of a developer's code prior to its execution?

A.

Tool support for test design and implementation.

B.

Tool support for static testing.

C.

Tool support for test execution and logging.

D.

Tool support for performance measurement and dynamic analysis.

Full Access
Question # 42

Which ONE of the following options MOST ACCURATELY describesbranch testing?

A.

In branch testing, the coverage items are executable statements. The aim is to design test cases that exercise statements in the code until an acceptable level of coverage is achieved, expressed as a percentage.

B.

In branch testing, the coverage items are control flow transfers between decisions, and the aim is to design test cases to exercise flow transfers in the code until an acceptable level of coverage is achieved. Coverage is measured as the number of branches exercised by the test cases divided by the total number of branches expressed as a percentage.

C.

In branch testing, the coverage items are branches, and the aim is to design test cases to exercise branches in the code until an acceptable level of coverage is achieved. Coverage is measured as the number of branches exercised by the test cases divided by the total number of branches expressed as a percentage.

D.

In branch testing, the coverage items are executable decisions. The aim is to design test cases that exercise statements in the code until an acceptable level of coverage is achieved. Coverage is expressed as a percentage.

Full Access
Question # 43

Which of the following statements about traceability is FALSE?

A.

Traceability between test basis items and the test cases designed to cover them, makes it possible to determine which test basis items have been covered by the executed test cases.

B.

Traceability between test basis items and the test cases designed to cover them, enables experience-based test techniques to be applied

C.

Traceability between test basis items and the test cases designed to cover them, enables identification of which test cases will be affected by changes to the test basis items.

D.

Traceability can be established and maintained through all the test documentation for a given test level, such as from test conditions through test cases to test scripts.

Full Access
Question # 44

Which of the following statements about static testing and dynamic testing is TRUE?

A.

Static testing is better suited than dynamic testing for highlighting issues that could indicate inappropriate code modulansation.

B.

Dynamic testing can only be applied to executable work products, while static testing can only be applied to non-executable work products.

C.

Both dynamic testing and static testing cause failures, but failures caused by static testing are usually easier and cheaper to analyse.

D.

Security vulnerabilities can only be detected when the software is being executed, and thus they can only be detected through dynamic testing, not through static testing

Full Access
Question # 45

Which of the following best describes the relationship between a test progress report and a test summary report?

A.

The test report prepared during a test activity may be referred to as a test progress report, while a test report prepared at the end of a test activity may be referred to as a test summary report.

B.

The test report prepared during a test activity may be referred to as a test summary report, while a test report prepared at the end of a test activity may be referred to as a test progress report.

C.

There is no difference between a test progress report and a test summary report.

D.

Both the test progress report and the test summary report should always be generated via an automated tool.

Full Access
Question # 46

Which ONE of the following tools would be MOST SUITABLE for facilitating thecreation of test cases, test data, and test procedures?

A.

Test design and implementation toolsare specifically designed for creating test cases, test data, and test procedures.

B.

Static testing toolsas they assist the tester in conducting reviews and static analysis.

C.

DevOps tools, as they support the automated build process and CI/CD.

D.

Test execution and coverage toolsfacilitate the automated execution of tests and the measurement of test coverage.

Full Access
Question # 47

Which ONE of the following options corresponds to an activity in the testing process in which testable features are identified?

A.

Test design

B.

Test analysis

C.

Test implementation

D.

Test execution

Full Access
Question # 48

You are testing the latest version of an air-traffic control system prior to production deployment using exploratory testing. After following an unusual sequence of input steps, the system crashes. After the crash, you document a defect report with the following information:

•Title: System crashes unexpectedly during input.

•Brief summary: System crashes when an unusual sequence of inputs is used.

•Version: V1.001

•Test: Exploratory testing prior to production deployment

•Priority: Urgent

•Risk: High

•References: Screenshot of crashed application

What critical Information Is missing from this report?

A.

Conclusions, recommendations, and approvals.

B.

Change history.

C.

Description of the defect to enable reproduction.

D.

Status of defect

Full Access
Question # 49

Scenario 2 “Big Drop”:

A company“The Big Drop”providesbulk discounts and frequent customer discountsas follows:

How manypossible decision rulescan be extracted from this table?

A.

5 decision rules

B.

6 decision rules

C.

32 decision rules

D.

8 decision rules

Full Access
Question # 50

Which of the following statements best describe Behavior-Driven Development (BDD)?

A.

A collaborative approach that allows every stakeholder to contribute to how the software component must behave.

B.

Expresses the behavior of an application with test cases written in Given When Then format.

C.

Is used to develop code guided by automated test cases.

D.

A psychological technique in which the team's behavior in agile teams is evaluated.

Full Access
Question # 51

Which of the following is not an example of a typical generic skill required for testing?

A.

Be able to apply test-driven development

B.

Be able to use test management tools and defect tracking tools

C.

Be able to communicate defects and failures to developers as objectively as possible

D.

Possess the necessary social skills that support effective teamwork

Full Access
Question # 52

Which ONE of the following statements about maintenance testing is CORRECT?

A.

Maintenance testing is performed exclusively for adaptive maintenance.

B.

Maintenance testing is only required when defects are reported in production.

C.

Maintenance testing should be performed when enhancements, fixes, or updates are applied to an existing system.

D.

Maintenance testing does not require test cases since it focuses solely on defect verification.

Full Access
Question # 53

Which of the following statements best describes the way in which decision coverage is measured?

A.

Measured as the number of statements executed by the tests, divided by the total number of executable statements in the code.

B.

Measured as the number of lines of code executed by the tests, divided by the total number of lines of code in the test object.

C.

Measured as the number of decision outcomes executed by the tests, divided by the total number of decision outcomes in the test object.

D.

It is not possible to accurately measure decision coverage.

Full Access
Question # 54

Confirmation testing is performed after:

A.

a defect is fixed and after other tests do not find any side-effect introduced in the software as a result of such fix

B.

a failed test, and aims to run that test again to confirm that the same behavior still occurs and thus appears to be reproducible

C.

the execution of an automated regression test suite to confirm the absence of false positives in the test results

D.

a defect is fixed, and if such testing is successful then the regression tests that are relevant for such fix can be executed

Full Access
Question # 55

Which of the following statements about the testing quadrants is TRUE?

A.

The higher the number of the testing quadrant, the more important the tests associated with this quadrant are

B.

Automated acceptance tests produced during BDD and ATDD are classified in quadrant 02.

C.

Exploratory tests are classified in quadrant Q3, and they are usually included in a continuous integration process.

D.

Automated unit tests produced during TDD are classified in quadrant Q4 as they are technology facing.

Full Access