New Year Special Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > Exin > EPI Data Centre > CDCS

CDCS EXIN EPI Certified Data Centre Specialist Question and Answers

Question # 4

The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.

What is the set-up in this data center?

A.

2+N+1

B.

2(N+1)

C.

N+N(+1)

D.

(N+1)-(N+1)

Full Access
Question # 5

What indicates the breaking capacity of a fuse or breaker?

A.

Mechanical strength of the casing of a fuse or breaker.

B.

The maximum voltage, in case of an electrical surge, that the fuse or breaker can handle without being destroyed or causing an electric damaging arc.

C.

The current at which the device will trip.

D.

The current that a fuse or breaker is able to interrupt without being destroyed or causing an electric damaging arc.

Full Access
Question # 6

What is a potential disadvantage of using a hypoxic-based fire suppression system as a fire extinguishing system?

A.

It can only be used in computer rooms which have sufficient air changes per hour.

B.

The gas containers need to be close to the hazard area.

C.

It can only be used in non-continuous occupied areas.

D.

It can only be used in computer rooms where you have sufficient positive pressure.

Full Access
Question # 7

Do you need to consider bullet (ballistics) protection when designing a data center?

A.

Bullet (ballistics) protection is required by ANSI/TIA-942 for all data centers.

B.

Bullet (ballistics) protection is only required when the data center is located in an area with a high crime rate.

C.

Bullet (ballistics) protection is required by ANSI/TIA-942 for data centers Rated 3/4.

D.

Bullet (ballistics) protection is only required if the facility is a potential target or the building is in the vicinity of a potential target.

Full Access
Question # 8

You are allowed to use a calculator for this question. The total power consumption of the ICT equipment in a rack is 6 kW. The equipment is traditional ICT equipment with a Delta-T of approximately 11 °C / 20 °F. Calculate the approximate CFM required to cool the equipment in the rack.

A.

Approximately 1,500 CFM

B.

Approximately 1,000 CFM

C.

Approximately 500 CFM

D.

Approximately 160 CFM

Full Access
Question # 9

What is a potential disadvantage of using water mist as a fire extinguishing system?

A.

It only uses 10% of the water normally used in a water-based fire suppression, which might not be enough to suppress the fire

B.

It will rapidly increase the humidity level in the data center, which can cause a potential risk for the operation of the equipment

C.

It extracts oxygen from the air creating a potential risk for humans inside the computer room

D.

It has droplets that are too small (100-120 microns) so it can only be used for small fires

Full Access
Question # 10

A data center scores Rated-3 in mechanical, Rated-4 in electrical, and Rated-2 in architectural.

What is the overall Rating of this data center when the Rating is based on the ANSI/TIA-942?

A.

Rated-2 since that is the lowest rating received

B.

Rated-4 since that is the highest rating received

C.

Rated-4 since electrical is more important than mechanical and architectural

D.

Depends on the Rating scored in telecommunications

Full Access
Question # 11

Do you need to consider blast protection when designing a data center?

A.

No, there is no reason for implementing blast protection as nobody can predict the impact of a bomb explosion.

B.

Yes, if the data center is a potential target or the building is located within the vicinity of (close by) a potential target.

C.

No, blast protection is not a requirement of ANSI/TIA-942.

D.

Yes, blast protection is a requirement of ANSI/TIA-942.

Full Access
Question # 12

A data center has its own power supply from the public utility and receives chilled water supply from the building owner.

What needs to be taken into consideration when calculating the PUE?

A.

Nothing, as the chiller plant in the building also uses electrical power

B.

You will need to take the value for COP of the chiller plant into consideration

C.

You will need to take a weight factor of 0.4 for district chilled water into consideration

D.

PUE calculations are not possible in shared buildings

Full Access
Question # 13

A computer room with a raised floor has been designed with racks in a hot/cold aisle setup.

What should you recommend for the placement of down-flow air conditioners?

A.

Air conditioners perpendicular to (at the end of the row of) the Cold-Aisle

B.

Air conditioners perpendicular to (at the end of the row of) the Hot-Aisle

C.

Air conditioners should always be placed at both sides of each row of racks

D.

Air conditioner placement has no influence on cooling effectiveness and efficiency. Hence, they can be placed at any convenient location.

Full Access
Question # 14

The air intake of the mission-critical server at the top of the rack is measuring 25 °C/77 °F.

Is this acceptable?

A.

Yes, this is allowed according to the standards and guidelines

B.

As long as it does not exceed the average server room temperature of 38 °C/100 °F

C.

Depends on the ANSI/TIA-942 Rating the data center needs to comply with

D.

No, the temperature needs to be 20 °C/68 °F

Full Access
Question # 15

From the options indicated, what is the correct starting point for the raised floor installation?

A.

Point A

B.

Point B

C.

Point C

D.

Point D

Full Access
Question # 16

In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?

A.

Security guards should perform regular inspections verifying the system works.

B.

The system should not be based on motion detection as the lights might suddenly switch off while staff is still at work.

C.

It is not advisable to use such a system since it will reduce the lifetime of LED lighting.

D.

At all times, the levels should allow for security cameras to function properly.

Full Access
Question # 17

The noise levels in the data center are approximately 91 dB (A).

Do employers need to take precautions?

A.

No, anything less than 100 dB (A) is acceptable.

B.

There are no regulations regarding noise levels inside a building. Regulations only apply to noise pollution outside of the building.

C.

As long as the data is compliant to ISO/IEC 27001 it is acceptable.

D.

Yes, since it is mandated by regulations.

Full Access
Question # 18

The data center has been in operation for about 1 year and 2 months. The dust levels in the computer room are relatively high.

What is the most likely root cause?

A.

The cleaning crew is not doing their work properly

B.

Every computer room has high dust levels due to constant high-speed air movement

C.

Low pressure in the computer room

D.

Floorboards are most likely not fitted correctly

Full Access