Summer Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 28522818

Home > AACE International > AACE > CCP

CCP Certified Cost Professional (CCP) Exam Question and Answers

Question # 4

You have been hired as the cost engineer for a mechanical contractor and have been provided the following information:

What is the schedule performance index (SPI)?

A.

ACWP/BCWS= 110,000/100,000= 1.10

B.

BCWS/ACWP = 100,000/110,000 = 0.91

C.

BCWP/BCWS = 105,000/100,000- 1.05

D.

BCWS/BCWP= 100,000/105,000-0.95

Full Access
Question # 5

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $20,000 is invested at the end of each fiscal year for the next 10 years, how much would our total investment be worth assuming the interest is at 10%?

A.

$289,370

B.

$318,740

C.

$265,798

D.

$420,236

Full Access
Question # 6

You are analyzing historic unit costs for 18'' Class 5 reinforced concrete pipe is a database. The unit costs include all costs-material, labor, equipment, and other, for the excavation, bedding, pipe and backfill. Refer to the following table:

What is the median unit cost?

A.

$48.22

B.

$48.35

C.

$40.00

D.

$46.59

Full Access
Question # 7

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The recognition of loss of value of a natural resource used in the production process is referred to as:

A.

Capital reduction

B.

Net loss

C.

Depreciation

D.

Depletion

Full Access
Question # 8

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Assuming the average life span of a lithium battery is two years and is normally distributed with a standard deviation of two months, what is the probability the battery will last between 20 months and 26 months?

A.

82%

B.

75%

C.

90%

D.

84%

Full Access
Question # 9

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Calculate the mean unit cost.

A.

$48.09

B.

$48.22

C.

$48.35

D.

$46.59

Full Access
Question # 10

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The value of the truck at the end of year five (5) would be:

A.

$0

B.

$14,265

C.

$25,000

D.

$23,366

Full Access
Question # 11

The following question requires your selection of Scenario 1.4.150 from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Annual depreciation (in USS) would be calculated as follows for a capital recovery with salvage analysis:

A.

5,343 par year

B.

4,343 pet year

C.

8,0X10 per year

D.

7,000 per year

Full Access
Question # 12

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Depreciation (in the United States) is calculated in accordance with which of the following?

A.

Modified Accelerated Cost Recovery System (MACRS)

B.

The Federal IRS Reform Act (FIRSRA)

C.

Generally Accepted Accounting Practices (GAAP)

D.

Accelerated Cost Recovery System (ACRS)

Full Access
Question # 13

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the schedule variance (SV)?

A.

BCWS - BCWP = 100.000 – 105,000 = -5,000

B.

ACWP - BCWS = 110.000 – 100,000 = 10,000

C.

BCWS -ACWP = 100.000 – 110,000 - -10,000

D.

BCWP - BCWS = 105.000 - 100.000 =- 5,000

Full Access
Question # 14

The purpose of a communication must be understood by ____________ if the message is to be clear to the

A.

Workers; management

B.

The speaker; the receiver

C.

Management; workers

D.

The receiver; the speaker

Full Access
Question # 15

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The taxable income in year number 5 is:

A.

$17,543

B.

$121,551

C.

$42,543

D.

$125,00

Full Access
Question # 16

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Why is a +/- notation necessary when developing an estimate?

A.

Contingency cushion

B.

It makes up for the lack of time to develop a real estimate

C.

It is a government requirement

D.

There are unknowns that affect the final cost of a project

Full Access
Question # 17

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the cost of manufacturing labor for the piece of equipment today?

A.

$140,000

B.

$875,000

C.

$210,000

D.

$105,000

Full Access
Question # 18

A schedule's late dates are calculated during the:

A.

Loop calculations

B.

Backward pass

C.

Forward pass

D.

Float

Full Access
Question # 19

What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?

A.

Liability insurance

B.

Performance bond

C.

Bid bond

D.

Surety bond

Full Access
Question # 20

An effort by a prime contractor to reduce the price quoted by a vendor, by providing the bid price to other vendors in an attempt to get the other vendors to underbid the original price quoted is referred to as:

A.

Costing

B.

Cost-price analysis

C.

Bid shopping

D.

Negotiating a best and final offer

Full Access
Question # 21

The goal of listening is to:

A.

Analyze what the speaker is saying

B.

Find out what is going on

C.

Have time to formulate your thoughts on the subject

D.

Improve communication

Full Access
Question # 22

Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?

A.

Productivity efficiency factor

B.

Value engineering

C.

Cash flow

D.

The learning curve

Full Access
Question # 23

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The compound interest factor used to determine Present Value in year number 5 is:

A.

0.3790

B.

0.6209

C.

1.6051

D.

0.6830

Full Access
Question # 24

AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.

A.

Risk analysis

B.

Benefit/Cost ratio (B/C) method

C.

Net present worth method

D.

Life cycle costs method (LCC)

Full Access
Question # 25

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

If the fixed rent remains unchanged, and XYZ pays S0.01 per unit as additional rent, the monthly breakeven point in numbers of units becomes:

A.

48,500 units

B.

66,667 units

C.

52,500 units

D.

33,333 units

Full Access
Question # 26

Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)

A.

ACWP/BCWS

B.

BCWS/BCWP

C.

ACWP/BCWP

D.

BCWP/ACWP

Full Access
Question # 27

Which of the following are used for profitability analysis in a construction company?

A.

Sum of years digits

B.

Return on Investment (ROI) and Rate of Return (ROR)

C.

Opportunity costs

D.

Booked costs

Full Access
Question # 28

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Resource planning must take all of the following into account except:

A.

Types of materials, equipment and labor skills required to complete the project

B.

Cash flow (expenditures) limitations for completing work on the project

C.

Time available to complete the project

D.

Earned value techniques established for the project

Full Access
Question # 29

Two of the most important things to know when planning a speech or lecture are the ______________and______________ of your audience.

A.

Motivation, professionalism

B.

Background, attitude

C.

Political preference, sense of humor

D.

Culture, understanding

Full Access
Question # 30

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following would NOT be considered part of a project cost and schedule forecast?

A.

Usage of contingency

B.

Current trends of time and money

C.

Peripherals report

D.

Changes to the project execution plan

Full Access
Question # 31

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to have reached the ______________ stage of Maslow's hierarchy of needs.

A.

Need satisfaction

B.

Belonging needs

C.

Self-actualizations

D.

Esteem

Full Access
Question # 32

If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual Percentage Rate) compounded monthly, how much will you have at the end of the period?

A.

$2,424

B.

$2,976

C.

$2,688

D.

$2,697

Full Access
Question # 33

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

A cyclical process model was chosen as the basis for total cost management (TCM) because:

A.

It is one of the basic tenets of quality improvement

B.

Refinement is needed to prepare the estimate at completion (EAC)

C.

Strategic assets and projects have inherent life cycles

D.

It facilitates development of budgets and schedules

Full Access
Question # 34

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the relative frequency of unit costs amounting to $55.00/unit?

A.

22.22%

B.

$55.00

C.

2

D.

338.5

Full Access
Question # 35

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $10,000 is scheduled to be paid out 5 years from now, what is the minimum amount we can invest today?

A.

$3,855

B.

$8,129

C.

$6,209

D.

$3,791

Full Access
Question # 36

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions)

A.

4.62

B.

4.24

C.

4.10

D.

4.31

Full Access
Question # 37

When a person hears the words being said to him/her, but does not receive the message of the words, it is called

A.

Reflective listening

B.

Judgmental listening

C.

Passive listening

D.

Directive listening

Full Access
Question # 38

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

It S480 is the target net profit, then the total sales volume (in dollars) is:

A.

$30,000

B.

$37,500

C.

$34,400

D.

$32,400

Full Access
Question # 39

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

All of the following are included in "income tax" calculations except:

A.

Annual income

B.

Annual expenditures

C.

Depreciation

D.

Initial cost of investment

Full Access
Question # 40

A work breakdown structure (WBS) is developed because:

A.

It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.

B.

It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans

C.

It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup

D.

It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence

Full Access
Question # 41

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the 25 year after tax present worth of this project?

A.

$13,738

B.

$137,466

C.

$(22,533)

D.

$22,533

Full Access
Question # 42

Which of the following is NOT an aspect of quality management?

A.

Quality assurance

B.

Quality planning

C.

Quality checking

D.

Quality control

Full Access
Question # 43

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)

A.

8.7%

B.

8.2%

C.

4.6%

D.

8.0%

Full Access
Question # 44

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

What Kind of optimization modeling is used in making investment analysis to evaluate the risks associated with the potential investment?

A.

Linear Probability Model

B.

Business Modeling

C.

Five-stop Regression Model

D.

Monte Carlo Simulation

Full Access
Question # 45

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

Calculate the weighted average unit cost.

A.

$46.13

B.

$47.63

C.

$48.35

D.

$48.09

Full Access
Question # 46

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

In the A relationship, the subcontractor might use an unbalance bid to:

A.

To get more payment early in the job

B.

Decrease the chances of extended claim litigation

C.

Reduce the risk of quantities being greater than estimated

D.

Provides an alternative to competitive bidding

Full Access
Question # 47

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Based on the information provided, which statement is most correct?

A.

The truck should be leased

B.

The truck should be purchased

C.

The truck should not be leased

D.

The truck should not be purchased

Full Access
Question # 48

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

All of the following are characteristics of standard normal distribution, except:

A.

means and median are not equal

B.

about 68% of its value is within one standard deviation

C.

the total area underneath the curve is 1

D.

the curve shape is symmetrical

Full Access
Question # 49

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

In an exit interview, an employee comments that the reason he is leaving the organization is lack of teamwork and cohesion among his co-workers. Which need of Maslow's hierarchy of needs is unmet?

A.

Belongingness needs

B.

Primary needs

C.

Self-actualization needs

D.

Esteem needs

Full Access
Question # 50

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the company needs to repay a loan of $100,000 in 10 uniform annual payments, how much will each payment be?

A.

$16,380

B.

$16,578

C.

$15,937

D.

$16,273

Full Access
Question # 51

If a project is said to be on a "fast track program/' the fast track method is:

A.

Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and duration for all of the work

B.

First completing engineering and procurement, then executing construction

C.

Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance

D.

Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime

Full Access
Question # 52

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the owner in A has a primary goal of completion within budget, the following contract types with the engineer/contractor would be best:

A.

Engineer — cost plus, contractor fixed price

B.

Engineer — cost plus, contractor cost plus

C.

Engineer fixed price, contactor cost plus

D.

Engineer — fixed price, contractor fixed price

Full Access
Question # 53

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The following question requires your selection of Scenario 1.4.150 from the right side of your split screen. using the drop down menu, to reference during your response/choice of responses.

Using normally accepted engineering economic practices, what are the two expected methods that should be used to determine the capital recovery costs for the new press?

A)

B)

C)

D)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 54

An owner advertised his villa for sale. An investor worked out an estimate on the basis mat the villa could be rented out for $1000 per month. Maintenance charges and other taxes are estimated to be $1,500 per year. The tenant has to pay all utility charges. The investor thinks that he can sell this villa for S100.000 alter 6 years. Assuming that the minimum acceptable rate of return is 12%. answer the following question.

The villa could be recommended for purchase at all of the below-mentioned prices except:

A.

$94,500

B.

$92.800

C.

$90,5000

D.

$93,500

Full Access
Question # 55

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the cost variance (CV)?

A.

BCWP-ACWP = 105,000-110,000 = -5,000

B.

ACWP-BCWP = 110,000-105,000 = 5,000

C.

BCWS-ACWP = 100,000-110,000 = -10,000

D.

ACWP-BCWS = 110,000-100,000 = -10,000

Full Access
Question # 56

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of S45 cents is estimated.

The monthly fixed costs are:

Rant-$1,500

Wages - $4.000

Miscellaneous fixed expenses - $500

If the rent increases by 100% and the unit sales/other costs remain unchanged, the new break even amount is?

A.

$60,000

B.

$41,250

C.

$33,000

Full Access