You have been with the organization; you constantly hear rumours about a certain CAPM failing to live up to the CAPM Code. What you should do?
Delivery dates and availability of resources can be found in the details of the __________.
Assumptions are factors that, for planning purposes, are considered to be ______.
Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?
A scope management plan In which of the following scope management processes is the scope management plan prepared?
Customer formally accepts the deliverables of each project phase. This process is known as ________.
You are the project manager of a project. Your project just went into integration mode. This means that your project __________.
Your project team is composed of team members in three countries plus a contractor team in a fourth country. What tool would optimize communication?
An activity that consumes no time or resource and shows only that a dependency exists between two activities is called:
You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?
Which of the following is a common characteristic of most project life cycle descriptions?
You are the project manager of a project .You have just completed the Define Activities, activity resources estimating, and Estimate Activity Durations processes. Which process have you left out?
Which process group is for detailed resource assignments and responsibilities?
Define Scope involves subdividing the major project deliverables into smaller, more manageable components to __________.
You are the project manager of a project. Project is installing AC to hotel rooms. You have done project cost and time estimates, told the customer that the estimates provided will be accurate if the rooms meet the requirements like (wooden coated). This is an example of which of the following?
Which of the following relationship is used in the Arrow Diagramming Method [ADM] :
A major assumption of all network scheduling methods is that the activity duration must be _____.
You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?
When you are developing the estimates for project, you choose in a mathematical model to predict estimate. What type of estimation method are you using?
Function of the __________ is to make sure that changes to anything in the project are recorded and agreed to by the stakeholders.
During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.
What is the communication channel delta if the members in the communication plan are increased from 5 to 10?
You are the project manager of a project and budgeted money to provide cash awards to team members that exceed expectations. A project team member that is motivated by the chance to earn cash reward can most accurately be explained by which theory
You are creating your WBS and keep decomposing tasks into smaller units. How can you tell when you are done?
___________ is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.
Which document contains initial requirements that satisfy stakeholders' needs and expectations?
What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?
Which of the following is one of the key components of the basic communications model?
Which of the following can be used to track the requirements throughout the project life cycle?
What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measure for a future project?
What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.75?
The Monitoring and Controlling process group contains which of the following processes?
A Project Management Office (PMO) manages a number of aspects, including what?
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
A project manager has limited authority in which type of organizational structure?
Which analysis uses beta and triangular distributions as a tool and technique?
Initiating, Planning, Executing, Monitoring and Controlling and Closing are called:
Quality and credibility of the qualitative risk analysis process requires that different levels of the risk's probabilities and impacts be defined is the definition of what?
If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?