You want to create a production order. What methods can you use?
Note: There are 2 correct answers to this question.
Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.
Advanced Planning uses master data from SAP S/4HANA Cloud Private Edition. In which data objects can you set the Advanced Planning flag? Note: There are 2 correct answers to this question.
Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.
Which business processes are affected by settings in the order type dependent parameters? Note: There are 2 correct answers to this question.
Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?
What information do you have to maintain to define the relationship between supply source dem source in the Kanban process? Note: There are 2 correct answers to this question.
Your project team decides to use a maketoorder planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question.
Your company produces a finished good based on a forecast expects it to be in stock when customers order it. If customers order more than the forecasted quantity this must NOT have any impact on the production program.
Which planning strategy do you use?
Why do you use Engineering Change Management? Note: There are 2 correct answers to this question.
How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.
For production orders cost object controlling (COC) can be carried out on an order related or product related basis. Which of the following do you have to consider?
Note: There are 2 correct answers to this question.
Which time elements does MRP consider in backward scheduling to determine the basic dates for components from depender Note: There are 2 correct answers to this question.
You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
Your company manufactures materials whose characteristics differ for each manufacturing process.
Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track use this information in all areas of logistics?
Which SAP applications can be used for forecasting in Supply Chain Planning? Note: There are 2 correct answers to this question.
What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
What are some benefits of planning with planned independent requirements for finished materials? Note: There are 2 correct answers to this question.
Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?
What are the key features of using a low level code? Note: There are 2 correct answers to this question.