How can a material availability check be triggered automatically for a production order?
Note: There are 2 correct answers to this question.
which SAP application can be used for forecasting in Supply Chain Planning?
Note: there are 2 correct answers to this question.
You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched, how does the insertion take place?
in your Plant, MRP is activated.
which options do you have to exclude a material from the MRP run?
Note: there are 2 correct answers to this question.
How can you set up the supply source for the Kanban process in SAP S/4HANA?
Note: There are 3 correct answers to this question.
Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?
Note: There are 2 correct answers to this question.
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question
What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,
You want to schedule an operation finitely, without removing other operations. Which scheduling strategy do you select?
Which of the following questions do you have to answer before you start creating a bill of material (BOM)?
You use planning strategy Finite Scheduling with Reverse and want to allow scheduling the past. How can you parameterize this in the strategy profile?
You want to set up a make-to-order planning scenario for a finished material. The bill of materialcontains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.
You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
You need to model goods receipt processing time in detailed scheduling. Which modeling options do you have?
Note: There are 3 correct answers to this question.
For production orders, cost object controlling (COC) can be carried out on an order-related or product- related basis. Which of the following do you have to consider?
Note: There are 2 correct answers to this question.
What does the material type influence?
Note: There are 2 correct answers to this question.
How can you support a GMP (Good Manufacturing Practice)-compliant production process?
Note: There are 3 correct answers to this question.