Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct answers to this question.
Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question
What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question
How can you search in the structure overview based on the user status? Note: There are 2 correct answers to this question
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use ?
You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the
project.
What are the prerequisites?
Note: There are 3 correct answers to this question
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?