Based on which of the following the checking control function determines whether an order type will be checked and if so, which checking rules should be used?
Please choose the correct answer.
Response:
With reference to material requirements in Project System (PS-MAT), which of the following statements are true?
Please choose the correct answer.
Response:
What are the different views available for capacity planning and work center planning?
There are 2 correct answers to this question.
Response:
Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?
Please choose the correct answer.
Response:
You are using the billing and down payment processing in Sales and Distribution and updating the actual data to billing elements in the project system.
Which of the following business processes can be mapped in Sales and Distribution?
There are 3 correct answers to this question.
Response:
Which of the following cannot be entered when using service activities in networks for planned and unplanned services?
Please choose the correct answer.
Response:
In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how?
Please choose the correct answer.
Response:
You are using the bottom-up scheduling scenario for a project containing WBS elements and networks. This means that ...
There are 2 correct answers to this question.
Response:
Items procured through which of the following methods are not assigned to a stock segment and do not pass through a warehouse?
Please choose the correct answer.
Response:
If the material is not assigned to any sales order or project and are available for use by general plant requirements. We consider this under which type of stock?
There are 2 correct answers to this question.
Response:
Based on which of the following; reservations or purchase requisitions can automatically be created for a project?
There are 2 correct answers to this question.
Response:
Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?
Please choose the correct answer.
Response:
Which of the following helps you to adjust cost planning to changing circumstances during the execution phase of the project?
Please choose the correct answer.
Response:
Which manual cost planning method is used in WBS?
There are 3 correct answers to this question.
Response:
What are the pre-requisites for distributing work to HR Resources?
There are 2 correct answers to this question.
Response:
In which transactions can you specify whether networks are scheduled together with maintenance orders that have been assigned as sub networks?
There are 2 correct answers to this question.
Response:
Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network?
Please choose the correct answer.
Response:
Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response?
Please choose the correct answer.
Response:
Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?
Please choose the correct answer.
Response:
Capacity planning board