Question # 4

What can be done when decommissioning a location that cannot be done when decommissioning an asset?

A.

Roll New Status down to All Assets in All Changed Locations?

B.

Remove All Reference to This Location from All Contracts?

C.

Remove All References to This Location from All Job Plans?

D.

Delete Associated Service Addresses That will be made Redundant?

Full Access
Question # 5

Where can Default Values be specified for Service Requests created using the Service Request Work Center?

A.

Service Desk Application

B.

in the users Profile

C.

Administration Work Center

D.

Application Designer

Full Access
Question # 6

What must first be done in order to apply a price adjustment to an Approved Labor Rate Contract?

A.

Use Edit History Contract from the More Actions menu.

B.

The contract should be revised.

C.

The contract should be suspended.

D.

Change the contract status to closed.

Full Access
Question # 7

A client has a requirement to manage access permits and risk assessments in Maximo. Which add-on provides this capability?

A.

Maximo Safety

B.

Maximo Health Safety and Environment

C.

Maximo Asset Configuration Manager (ACM)

D.

Maximo Spatial

Full Access
Question # 8

What are the three default classes of a Ticket?

A.

Problem

B.

Activity

C.

Service Request

D.

Change

E.

Incident

F.

Release

Full Access
Question # 9

A company wishes to configure Flow Control for Work Orders. In which application can they change the Start Status and Complete Status that will be used?

A.

System Properties

B.

Work Order Tracking

C.

Job Plans

D.

Organizations

Full Access
Question # 10

A Service Level Agreement is defined at the System level. What is the purpose of the Organization and Site fields?

A.

They are used to filter the SLAs which a user can see based on Security Group Site access.

B.

They are used to filter the SLAs that can be associated with a Contract.

C.

They are used to filter the SLAs that can be included as Related SLAs.

D.

They are used to filter the SLAs that could be applied to the object.

Full Access
Question # 11

Which two domain types can have a specified error message?

A.

SYNONYM

B.

NUMERIC

C.

TABLE

D.

CROSSOVER

E.

ALN

Full Access
Question # 12

When creating a new Inspection form, a client requires a Work Order to be created if certain responses are recorded. Which two actions are required for this to be achieved?

A.

Choose Work Order on question action.

B.

Make the question response interactive.

C.

In Form Settings add an Action Script.

D.

In the Question Options, set the Require action flag.

E.

Create an escalation on the QRESPONSE Object.

Full Access
Question # 13

What are the three Service Level Agreement Commitment Types that require a unit of measure because they calculate a date? (Choose three.)

A.

RESOLUTION

B.

FIRSTFIX

C.

DELIVERY

D.

RESPONSE

E.

COMPLETION

F.

CONTACT

Full Access
Question # 14

When using flow control on a Work Order, how ca from the Parent to Child Work Orders?

user ensure that Work Order status changes are inherited

A.

Check the Inherit Status Changes flag on the Work Order and ensure the mxe.app.wo.flowControlStatuslnheritance System Properties is set to 1.

B.

In the Organization application, check the Intarit Status Changes flag in Work Order Options -> Flow Control Options.

C.

Ensure the Asset or Location

on both the Parent and Child Work Order.

D.

Check the Roll Down Status Changes flag on the Parent and Child Work Order.

Full Access
Question # 15

To what type of objects can a Service Level Agreement be applied?

A.

only the objects based on the Work Order or Ticket Classes, and Assets, Locations and Configuration Items

B.

only the Main Object that are Internal

C.

only the objects based on the Work Order or Ticket Classes

D.

any Main Object

Full Access
Question # 16

What are two of the filters in the Select Value of a Location or Asset in the Service Requests application?

A.

Public

B.

Service Address

C.

Service Group/Services

D.

User/Custodians

E.

Work Zones

Full Access
Question # 17

In the Organizations application, which action is used to create Inventory Usage documents for new reservations?

A.

Inventory Usage Options

B.

Inventory Options

C.

Work Order Options

D.

Reservation Options

Full Access
Question # 18

Which two domain types support lookups? (Choose two.)

A.

NUMERIC RANGE

B.

TABLE

C.

SYNONYM

D.

UPPER

E.

INTEGER

Full Access
Question # 19

Which application in the IBM Maximo Application Suite can be used to perform criticality scoring?

A.

Maximo Supervision

B.

Maximo Manage

C.

Maximo Prevent

D.

Maximo Health

Full Access
Question # 20

Which three coverage options can be included on a contract line in a Warranty Contract? (Choose three.)

A.

Financial Loss

B.

Labor

C.

Children

D.

Shipping

E.

Replacement

F.

Materials

Full Access
Question # 21

Which two statuses of a Purchase Order will allow a receipt of new items to be processed in the Receiving application if the Purchase Order is not being revised?

A.

APPR

B.

HOLD

C.

INPRG

D.

REVISD

E.

PNDREV

Full Access
Question # 22

What are three statuses used in the Service Requests application? (Choose three.)

A.

COMPLETED

B.

ENTERED

C.

RESOLVED

D.

QUEUED

E.

APPROVED

F.

PENDING

Full Access
Question # 23

If a Service Request has a follow-up Work Order, by default at what two Work Order internal statuses would the Service Requests status be updated? (Choose two.)

A.

INPRG

B.

CLOSE

C.

APPR

D.

comp

E.

CAN

Full Access
Question # 24

In which three applications can Asset Depreciation be configured?

A.

Chart of Accounts

B.

Tools

C.

Asset Templates

D.

Locations

E.

Assets

F.

Item Master

Full Access
Question # 25

In the Manage Inventory Work Center a pick list can be created, its initial status is Entered. Which three actions will cause the status to change to in Progress? (Choose three.)

A.

Picked

B.

Restocked

C.

Prepared

D.

Issued

E.

Staged

F.

Returned

Full Access
Question # 26

In the Inventory Usage application, which three statuses will activate the Split Usage Quantity feature? (Choose three.)

A.

CANCELED

B.

RETURNED

C.

ENTERED

D.

STAGED

E.

COMPLETE

F.

SHIPPED

Full Access
Question # 27

In which application can a user view a history of changes made to attributes in the Specifications tab?

A.

Locations

B.

Item Master

C.

Purchase Orders

D.

Assets

Full Access
Question # 28

When setting up Premium Pay Codes in the Crafts application, what are the three rate types available? (Choose three.)

A.

Formula

B.

Hourly

C.

Increment

D.

Weekend

E.

Overtime

F.

Multiplier

Full Access
Question # 29

How can a user be granted access to a Work Center application?

A.

using the Maximo Management Interface

B.

using the Security Groups application

C.

by using self-registration

D.

using the Administration Work Center

Full Access
Question # 30

Which two search types can be found on an attribute in the Database Configuration application when using an Oracle or SQL Server database? (Choose two.)

A.

INDEXED

B.

NONE

C.

FUNCTION

D.

HIERARCHY

E.

TEXT

Full Access
Question # 31

What are three available associations in the Hazards application?

A.

Lock Outs

B.

Material Safety Data Sheets (MSDS)

C.

Hazardous Materials

D.

Tag Outs

E.

Precautions

F.

Safety Plans

Full Access
Question # 32

In the Meters application what are the three meter types?

A.

GAUGE

B.

CHARACTERISTIC

C.

CONTINUOUS

D.

FEATURES

E.

CONSTANT

F.

CALIBRATION

Full Access
Question # 33

What Downtime Types are available?

A.

Critical and Non-critical

B.

Operational and Non-operational

C.

Planned and Unplanned

D.

Started and Stopped

Full Access
Question # 34

Which two records can be included as a contract line item on a Lease/Rental Contract?

A.

Non-Rotating Asset

B.

Rotating item

C.

Asset

D.

Tool

E.

Non-Rotating item

Full Access
Question # 35

Where can the Asset Up/Down status be modified?

A.

use the Move/Modify Asset action in the Assets application

B.

from the Report Downtime action on the Work Order

C.

use the Move/Swap/Modify action on the Work Order

D.

use the Failure Reporting option on the Work Order