You can pre-order your "Associate in Project Management (APM)" exam to us if you are in need this urgent. Dumpsmate.com Team will prepare your Exam Questions & Answers From Real Exam within next 2 to 3 Weeks Time only.
In the unlikely event if we can't make this exam available to you then you will issue a full refund! So there is no risk.
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?
Which tools or techniques are used during the Close Project or Phase process?
When closing a project or phase, part of the process may require the use of which type of analysis?
The following is a network diagram for a project.
The total float for the project is how many days?
An issue log is an input to which Project Human Resource Management process?
In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
Stakeholder communication requirements should be included as a component of:
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Which of the following correctly explains the term "progressive elaboration'?
Which type of estimating is used to improve the accuracy of an activity's duration?
Which Process Group contains those processes performed to define a new project?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?
Which of the following statements is true regarding project and product lifecycles?
Which of the following types of a dependency determination is used to define the sequence of activities?
Which of the following project documents is an input to the Control Scope process?
Which of the following is a tool and technique used in the Develop Schedule process?
Which cost estimate technique includes contingencies to account for cost uncertainty?
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
As the project progresses, which of the following is routinely collected from the project activities?
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
Which of the following is the primary output of the Identify Risks process?
Project contracts generally fall into which of the following three broad categories?
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
A procurement management plan is a subsidiary of which other type of plan?
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
Which of the following involves making information available to project stakeholders in a timely manner?
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:
Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?
Which risk response strategy is common for both positive and negative risks?
Funding limit reconciliation is a tool and technique used in which process?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Which of the following is an input to Direct and Manage Project Execution?
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Prototype development may be used as a tool for which of the following risk response strategies?
Which type of dependency is contractually required or inherent in the nature of the work?
Which of the following is an input to the Develop Project Charter process?
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
Organizational theory is a tool used in which Project Human Resource Management process?
The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
Lessons learned are created and project resources are released in which Process Group?
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
The process of identifying and documenting relationships among the project activities is known as:
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?
A risk that arises as a direct result of implementing a risk response is called a:
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be: