AD0-E903 Adobe Workfront Project Manager Professional Question and Answers

Question # 4

The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.

Which task settings need to be configured to meet these requirements?

A.

The Task Constraint should be set to Must Start On with Planned Time set to 2 weeks and Duration set to 10 hours.

B.

The Task Constraint should be set to Must Start On with Planned Hours set to 10 hours and Duration set to 2 weeks.

C.

The Task Constraint should be set to Start Date of September 23 with Planned Hours set to 10 hours and Issue Duration set to 2 weeks.

Full Access
Question # 5

Which wildcard should be used on a project report when filtering for projects that have a planned completion date greater than 1 month from the current date?

A.

TODAY + 1bm

B.

TODAY + 1m

C.

CURRENTDATE + 4w

Full Access
Question # 6

Task 1 on Project 1 can only be started once the final milestone on Project 2 is completed.

How can the project manager configure this relationship?

A.

Add a cross-project predecessor on the final milestone of Project 1.

B.

Add a cross-project predecessor on Task 1 in Project 1.

C.

Add a cross-project predecessor on the final milestone in Project 2.

Full Access
Question # 7

A team lead needs to regularly report on the adherence of budget and timeline of a group ofprojects.

What should the team lead use to organize these projects to allow them to be tracked together?

A.

Layout template

B.

Program

C.

Group

Full Access
Question # 8

What are two characteristics of a Group in Workfront? (Choose two.)

A.

A Group can be tagged in an Update thread communication.

B.

A Group assignment is not required for a user.

C.

A Group can be associated with a Company or a Project.

D.

A user can be assigned as Group Administrator of a Group.

Full Access
Question # 9

Which project Condition is set when the Progress Status of the project is Behind or At Risk?

A.

Late

B.

At Risk

C.

In Trouble

Full Access
Question # 10

A project manager has been asked to work on a cross-departmental company-wide initiative. There will be many individuals assigned to each task.

What should the project manager ask users to do when it comes to completing tasks?

A.

Users do not need to complete tasks when multiple users are assigned.

B.

Mark the task as "Done with my part."

C.

Make an update and tag the project manager.

Full Access
Question # 11

Which project elements can be used to measure a project’s adherence to its original schedule?

A.

Number of tasks, actual completion dates, and project status

B.

Project baselines, planned completion dates, and actual completion dates

C.

Workload balancer data, planned completion dates, and expenses

Full Access
Question # 12

What parent object can have child objects?

A.

Issue

B.

Project

C.

Portfolio

Full Access
Question # 13

How is the primary assignee of a task determined?

A.

By the user on a task that has a primary job role.

B.

By the Home Team assigned to a task.

C.

By the user that is assigned first to a task.

Full Access
Question # 14

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

A.

Projected Date

B.

Planned Date

C.

Estimated Date

Full Access
Question # 15

Which project status defaults the project condition to On Target?

A.

In Progress

B.

Idea

C.

New

Full Access
Question # 16

An organization has created unique data fields relevant to their projects. Starting by navigating from a project's landing page, where is this data found?

A.

Project Details > Custom Forms

B.

Project Details > Overview

C.

Business Case > Project Info

Full Access
Question # 17

Which two options are available with Workfront reports? (Choose two.)

A.

A chart report that references a multi-select custom field

B.

Planned date-based calendar reports

C.

Filters with a custom grouping

D.

An object name with more than 500 characters

Full Access
Question # 18

Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

A.

The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.

B.

The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.

C.

The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.

D.

The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.

Full Access
Question # 19

A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.

How should the project manager keep these team members apprised of updates?

A.

Subscribe the team members to the request.

B.

Ask the team members to add the request to their favorites.

C.

Make the team members all primary contacts on the request.

Full Access
Question # 20

Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?

A.

Status

B.

Condition

C.

Progress Status

Full Access
Question # 21

A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

A.

Visit the Dashboards page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects.

B.

Visit the Projects page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select "Show the Milestone view on the Details tab."

C.

Visit the Reports page and create a Project report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select "Show the Milestone view on the Details tab."

Full Access