Halloween Special Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > CompTIA > Project+ > PK0-004

PK0-004 CompTIA Project + Question and Answers

Question # 4

A project manager wants to determine the percentage of a project's budgeted costs versus expenditures.

Which of the following calculations should the project manager perform?

A.

Burn rate

B.

Critical path analysis

C.

EV

D.

EAC

Full Access
Question # 5

A project coordinator holds a status meeting about a new product line. Some deliverables are behind schedule and need to be completed over the weekend. As a result, extra effort may be needed to adhere to the project timeline. Which of the following project phases is occurring?

A.

Monitoring

B.

Initiating

C.

Planning

D.

Closing

Full Access
Question # 6

Project team members are getting frustrated, questioning their goals, and taking it out on their project manager. In which of the following stages is the team?

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Full Access
Question # 7

A project to implement Voice over Internet Protocol for a contact center has been expanded to include the entire organization.

Which of the following BEST describes the constraints involved?

A.

Deliverables, schedule, and resources

B.

Stakeholders, scope, and schedule

C.

Schedule, quality, and deliverables

D.

Resources, requirements, and scope

Full Access
Question # 8

A vendor who is scheduled to arrive in two days encounters a delay and needs to reschedule the visit. The project manager needs a timely response from the project sponsor regarding the delay; however, the sponsor is in an all-day meeting and is not responding to email.

Which of the following is the BEST method to get the sponsor’s attention?

A.

Schedule an urgent meeting, overbooking one of the meetings.

B.

Delegate to the project coordinator.

C.

Text the sponsor asking for advice.

D.

Interrupt one of the meetings to speak to the sponsor.

Full Access
Question # 9

Two highly skilled resources, who are currently working on other projects, are assigned to a project manager. Personality conflicts between the two resources have adversely affected project completion. The project

manager has asked a manager with direct authority over the resources to provide input to resolve the issue, but the project manager does not have the level of authority required to resolve the personality conflict.

Which of the following structure types is this an example of?

A.

Strong matrix

B.

Balanced matrix

C.

Functional

D.

Weak matrix

E.

Projectized

Full Access
Question # 10

A project manager keeps a running log of all action items for a project and publishes the log on the intranet site. Despite being accessible by the entire project team, action items are not updated as completed.

Based on the above action item log. which of the following is the MOST likely reason for this behavior?

A.

The project team members do not know who is responsible for working the actions

B.

The project team members do not know how to access the action log on the intranet site.

C.

The project manager has not followed up to ensure the tasks are completed.

D.

The project team members have not been trained on closing action items.

Full Access
Question # 11

Which of the following project team members would MOST likely be tasked with maintaining project documents?

A.

Project coordinator

B.

Project manager

C.

Project scheduler

D.

Project sponsor

E.

Project champion

Full Access
Question # 12

Which of the following is the BEST indicator of project failure?

A.

Product deficiencies revealed during the monitor and control phase

B.

Project team members disagreeing on milestones

C.

Project deliverables completed behind schedule

D.

Several changes being made to the project

Full Access
Question # 13

Everyone on the team agrees with a change request, and the team proceeds with the implementation. Which of the following steps is missing from the identified process?

A.

Impact justification

B.

Formal approval

C.

Quality check

D.

Identify and document

Full Access
Question # 14

The Chief Executive Officer (CEO) informs the project manager that a project must be completed six months earlier than previously scheduled. Which of the following is the BEST way for the project manager to respond?

A.

Increase the quality parameters.

B.

Transfer more productive resources to the project.

C.

Recommend a reduction of the deliverables.

D.

Update the project scope.

Full Access
Question # 15

Which of the following will MOST likely result in changes to the project plan?

A.

Departure of the project manager

B.

Departure of the sponsor

C.

Milestone realization

D.

Incident occurrence

Full Access
Question # 16

Which of the following should receive regular communication during the planning phase of a project? (Choose two.)

A.

Collaboration site

B.

Change control board

C.

Subject matter experts

D.

Sponsor

E.

Human resources

Full Access
Question # 17

A new project manager is taking over a project that is already in the execution phase, and is conducting a review of all meetings to identify usefulness and content. Team members have complained of an overabundance of meetings. Which of the following would be useful to identify who should be required to attend?

A.

Compare participation to the list of attendees in the meeting minutes.

B.

Review the communication plan.

C.

Review the meeting minutes for appropriate subject material

D.

Compare scheduled duration to actual duration.

Full Access
Question # 18

A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager do NEXT?

A.

Ask the resource manager to deallocate the resource from the second project.

B.

Ask the resource manager to assign a new resource with 40% of allocation.

C.

Keep the resource 100% allocated in the project, as per the initial plan.

D.

Change the resource to 60% of allocation and review the mitigation plan.

Full Access
Question # 19

Which of the following are the components of a RACI matrix?

A.

Responsibility, authority, support, inform

B.

Responsible, accountable, consulted, informed

C.

Reliability, accountability, support, inform

D.

Responsibility, acquired, consulted, informed

Full Access
Question # 20

Two team members are discussing the lessons learned from the last testing release. Many quality defects were not reported, and the progress report is not accurate. Which of the following phases/activities are being executed?

A.

Planning/governance

B.

Monitoring/performance measuring

C.

Closing/gathering lessons learned

D.

Executing/performing project team

Full Access
Question # 21

A PM is interested in outsourcing a project deliverable but is uncertain of the company's offerings. Which of the following documents would be most appropriate for the PM to send to the company to acquire more details?

A.

RFP

B.

MOU

C.

RFI

D.

SOW

Full Access
Question # 22

During a weekly meeting, a project manager mentioned a decision was made on June 17 to include future state workflows in onboard training.

Which of the following communication methods should be used?

A.

Project communications plan

B.

Project dashboard

C.

Project schedule

D.

Project status report

Full Access
Question # 23

A new project manager is assigned in the middle of a seven-month project. The project is behind schedule, and there is only historical weekly cost data available.

Which of the following best practices should the project manager perform to assess project costs?

A.

Review the SPI.

B.

Create a burndown chart.

C.

Ask the project sponsor for additional funding.

D.

Perform a cost benefit analysis.

Full Access
Question # 24

A project manager notices a lack of meeting attendance from the project team. Which of the following actions might the project manager take to BEST improve the level of attendance?

A.

Schedule the meeting directly on the attendees’ calendars.

B.

Publish an agenda prior to the meeting.

C.

Increase the number of email invitations for the upcoming meeting.

D.

Send the meeting invitation by email with a read receipt.

Full Access
Question # 25

While planning a project, the project team estimates known expenses but also applies a margin of error for

unknown expenses. Which of the following is the project team trying to determine?

A.

Cost of quality

B.

Expenditures

C.

Total project cost

D.

Burn rate

Full Access
Question # 26

A small company has a successful proof of concept for an innovative new service but lacks the necessary expertise to deploy it. Which of the following is the BEST course of action to address this deficiency?

A.

Internal reorganization

B.

Business merger/acquisition

C.

Business process change

D.

Outsourcing

Full Access
Question # 27

Which of the following is the BEST source for identifying the defect tolerance of a project?

A.

SOW

B.

SWOT

C.

KPP

D.

SLA

Full Access
Question # 28

A project manager has updated the project schedule but cannot analyze the schedule performance. Which of the following steps did the project manager miss?

A.

Lock the schedule

B.

Approve the schedule

C.

Baseline the schedule

D.

Fast track the schedule

Full Access
Question # 29

An American publisher is participating in a workshop in Hong Kong with the purpose of updating a new book that will be launched in Japan next year. During the workshop, a deep and intense discussion occurs with other local publishers regarding the references the book may contain. Which of the following BEST describes the situation?

A.

Language barrier

B.

Personal preference

C.

Technological factor

D.

Cultural difference

Full Access
Question # 30

A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.

Which of the following terms describe this requirement?

A.

Outsourcing

B.

Business acquisition

C.

Business process change

D.

Internal reorganization

Full Access
Question # 31

A project manager is creating the monthly report for top management. The project manager has collected the information below:

AC = 100

PV = 80

EV = 120

Based on this information, the CPI reflects which of the following about the project?

A.

It is under budget.

B.

It is over budget.

C.

It is ahead of schedule.

D.

It is behind schedule.

Full Access
Question # 32

The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project.

Which of the following schedule compression techniques should be used by the project manager?

A.

Rescheduling

B.

Crashing

C.

Rebaselining

D.

Control scope

Full Access
Question # 33

A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Select TWO).

A.

Using the WBS will help prevent work from slipping or being forgotten.

B.

TheWBS will be required on very large projects.

C.

TheWBS will be required if the project manager has the time available to complete it.

D.

TheWBS will aid in determining which resources are required for the project.

E.

The WBS is the best way to determine risks of the project.

Full Access
Question # 34

A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.

Which of the following is the MOST likely reason?

A.

Established communication plan

B.

Scope creep

C.

Resource constraints

D.

Iterative approach

Full Access
Question # 35

A project’s key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)

A.

Cost performance parameter

B.

Project schedule

C.

KPI

D.

Corrective action plan

E.

WBS

Full Access
Question # 36

Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.

Which of the following techniques is the project manager using?

A.

Compromising

B.

Smoothing

C.

Withdrawing

D.

Accepting

Full Access
Question # 37

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project’s resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.

Which of the following documents should the project team reference to fast-track the project? (Choose two.)

A.

Scope management plan

B.

Configuration management plan

C.

Network diagram

D.

Project schedule

E.

Project plan

Full Access
Question # 38

A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?

A.

Reduced quality

B.

Reduced scope

C.

Reduced risk

D.

Reduced timeline

Full Access
Question # 39

A project in the execution phase is over budget, and tasks on the critical path are on schedule.

Which of the following should the project manager do NEXT?

A.

Update the project management plan.

B.

Issue a change request.

C.

Revise the project charter.

D.

Evaluate the impact to the baseline.

Full Access
Question # 40

Which of the following documents should be used to provide high-level reporting to key stakeholders?

A.

Dashboard

B.

Communication plan

C.

Statement of work

D.

Project charter

Full Access
Question # 41

A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility.

Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?

A.

Email

B.

Social media

C.

Text messaging

D.

Face-to-face

Full Access
Question # 42

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?

A.

Pareto chart

B.

Fishbone diagram

C.

Process diagram

D.

Run chart

Full Access
Question # 43

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.

This type of analysis is an example of which of the following?

A.

Cost performance index

B.

Risk mitigation

C.

Schedule variance

D.

Cost variance

Full Access
Question # 44

Which of the following is a characteristics of a matrix organization?

A.

Authority lies solely with the project manager.

B.

Authority is directed by the project architect.

C.

Authority is shared between the project manager and project coordinator.

D.

Authority is shared between functional and project managers.

Full Access
Question # 45

A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.

Which of the following techniques is MOST likely to be used to complete the project on time?

A.

Throttling

B.

Crashing

C.

Resource leveling

D.

Resource smoothing

Full Access
Question # 46

Which of the following risk strategies is represented by the purchase of insurance?

A.

Mitigate

B.

Accept

C.

Transfer

D.

Avoid

Full Access
Question # 47

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

A.

SCRUM retrospective

B.

Kickoff meeting

C.

Budget baseline

D.

Risk review

Full Access
Question # 48

Which of the following are characteristics of a project? (Choose two.)

A.

A project is a temporary endeavor.

B.

A project provides a unique product, service, or result.

C.

A project is an ongoing endeavor.

D.

A project involves scheduled maintenance.

E.

A project includes life-cycle cost management.

Full Access
Question # 49

In which of the following organizational structures would a project manager have the MOST authority?

A.

Projectized

B.

Strong matrix

C.

Balanced matrix

D.

Functional

Full Access
Question # 50

A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?

A.

Transfer

B.

Share

C.

Mitigate

D.

Avoid

Full Access
Question # 51

A project manager is justifying a required change with the associated impact on the project.

Which of the following is the NEXT step?

A.

Implementation

B.

Approval

C.

Validation

D.

Auditing

Full Access
Question # 52

In a project with a ВАС of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?

A.

The project is under budget and ahead of schedule.

B.

The project is over budget and ahead of schedule.

C.

The project is under budget and behind schedule.

D.

The project is over budget and behind schedule.

Full Access
Question # 53

Which of the following characteristics would stakeholders MOST likely have?

A.

Provide input, vested interest, affected by project

B.

No vested interest, funding control, expertise

C.

Project steering, funding control, vested interest

D.

Expertise, provide input, good at controlling

Full Access
Question # 54

A project manager detects low performance from a team member who previously demonstrated to be a highly

skilled asset. The team member explains that being part of two teams is too time consuming. This is a disadvantage of having:

A.

dedicated resources.

B.

interproject dependencies.

C.

resource overallocation.

D.

shared resources.

Full Access
Question # 55

Which of the following includes setting governance gates as well as predecessors and dependencies?

A.

Project communication

B.

Project constraints

C.

Project change control

D.

Project scheduling

Full Access
Question # 56

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.

The project manager should:

A.

follow the change process flow and notify the legal department after the change is implemented.

B.

extend a formal invitation to the legal department representative to join the CCB.

C.

hold a separate meeting with the legal department representative and ask for approval.

D.

notify the legal department representative in the event of an upcoming audit.

Full Access
Question # 57

The executive sponsor asks a project manager to summarize the following for a project:

1. Final capital expenditures.

2. Anticipated cost of new employee resources to support the solution.

3. Maintenance estimates.

Which of the following information should the project manager provide?

A.

Cost baseline

B.

Burn rate

C.

Cost variance report

D.

Total project cost

Full Access
Question # 58

Which of the following is described as placing responsibility for addressing the potential effects of an uncertain future event on an entity outside the organization?

A.

Risk avoidance:e

B.

Risk transfer

C.

Risk exploitation

D.

Risk mitigation

Full Access
Question # 59

Using Scrum, which of the following are discussed in a daily standup meeting?

A.

What was done yesterday, what is planned for today, and what roadblocks need to be removed

B.

What was done yesterday, what is planned for the week, and what issues were resolved

C.

What was done yesterday, what is planned for today, and what deliverables were completed

D.

What was done yesterday, what is planned for this week, and what items from the backlog are priority

Full Access
Question # 60

A project team on a four-year project has a shortage of workspace within an office. Which of the following is the MOST viable solution for the project team while ensuring work hours are not wasted?

A.

Secure a new facility, permit remote work, and reduce staff.

B.

Reduce staff, implement BYOD, and permit remote work.

C.

Implement BYOD, secure a new facility, and utilize shared workspaces.

D.

Permit remote work, utilize shared workspaces, and implement BYOD.

Full Access
Question # 61

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

A.

Sales clerk

B.

Marketing representative

C.

Team lead

D.

Product item

Full Access
Question # 62

Which of the following project documents should be used to record the occurrence of an unplanned event?

A.

Action log

B.

Risk log

C.

Change log

D.

Issue log

Full Access
Question # 63

A project manager has identified a minor skills gap in the operational team that will end up supporting the project solution.

Which of the following is the BEST risk mitigation strategy that the project manager should use?

A.

Organize adequate training and have one of the operational staff as part of the project team.

B.

Raise a risk in the risk register, identify the likelihood and the consequence of the risk occurring.

C.

Have the project adequately document the solution and ensure a transition is in place.

D.

Escalate this as an issue to the project control board and ensure that there is adequate discussion.

Full Access
Question # 64

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:

  • Coordinate project schedule
  • Manage to the triple constraint
  • Provide performance feedback to team members’ managers

Which of the following types of organizational structures did the new project manager MOST likely join?

A.

Balanced matrix

B.

Strong matrix

C.

Functional

D.

Projectized

Full Access
Question # 65

A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.

Which of the following calculations accurately shows the critical path?

A.

20 days

B.

39 days

C.

49 days

D.

52 days

Full Access
Question # 66

A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?

A.

Issue log

B.

Action items

C.

Dashboard information

D.

Communication plan

Full Access
Question # 67

A risk with a high probability and medium consequence to a project has been identified. In response, the project manager has purchased an insurance plan with the intent to provide additional funds if the risk is realized. There is no risk to the schedule or scope. Which of the following types of risk strategies is this an example of?

A.

Accept risk

B.

Transfer risk

C.

Mitigate risk

D.

Exploit risk

E.

Avoid risk

Full Access
Question # 68

A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference.

Which of the following is MOST likely to be the main challenge the influences this decision?

A.

Geographical factors

B.

Language barriers

C.

Cultural differences

D.

Technology factors

Full Access
Question # 69

A project team is comprised of a mix of in-house and virtual team members.

When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?

A.

Composing a project team email with the details of the announcement is the best method. It gives the project manager the opportunity to explain but not be overcome with questions from the team.

B.

Using text messaging to make the announcement is the best method. It allows the project manager to reach the project team members wherever they are located.

C.

Sending a fax is the best method. It gives the project manager the opportunity to explain the announcement and come up with questions and answers the team may have.

D.

Hosting a web conference meeting is the best method. It gives the project manager the opportunity to explain the announcement and answer any questions from the team.

Full Access
Question # 70

A project team is spread between two countries on different continents. Which of the following factors are MOST likely to influence communication methods selected for the communication plan? (Select TWO).

A.

Interorganizational constraints

B.

Personal preferences

C.

Language barriers

D.

Cultural differences

E.

Confidentiality constraints

Full Access
Question # 71

A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?

A.

Update

B.

Scheduling

C.

Kickoff

D.

Review

Full Access
Question # 72

Which of the following is a key aspect of the Agile project management methodology?

A.

Test-driven

B.

Daily standup meetings

C.

Short project durations

D.

Defined list of requirements

Full Access
Question # 73

A senior developer abruptly resigned without notice. Because of the senior developer’s expertise, the active task workload was substantial.

This would MOST likely impact the project’s: (Choose two.)

A.

environment

B.

scheduling

C.

requirements

D.

effectiveness

E.

scope

F.

budget

Full Access
Question # 74

A project sponsor wants to replace the current PM with a more experienced PM. However, removing the current PM might have a negative impact on the team's morale and motivation in a critical stage of the project. After talking to the main stakeholder, the sponsor decides to provide the PM with training according to the need instead of removing the PM. Which of the following risk management strategies was used in this scenario?

A.

Avoid

B.

Exploit

C.

Transfer

D.

Mitigate

Full Access
Question # 75

A program manager asks for a visual representation of tasks, including the start and end dates. Which of the following tools should the project manager provide?

A.

Run chart

B.

Gantt chart

C.

Process diagram

D.

Histogram

Full Access
Question # 76

A vendor is not meeting the agreed-upon quality of deliverables. To try to renegotiate the contract with the vendor, which of the following documents should the project manager use to highlight the areas that need improvement?

A.

RFI

B.

SLA

C.

MOU

D.

LOI

Full Access
Question # 77

A project manager, who previously worked at a construction firm, has just joined an IT organization and has been assigned to handle a security project. Which of the following roles can provide technical direction during the course of the project?

A.

Security SME

B.

Business analyst

C.

Project scheduler

D.

Project sponsor

Full Access
Question # 78

Joe, a stakeholder, threatens to withdraw from a project that is not going according to his wishes. The president talks to the project manager regarding options for a response to the stakeholder, and they decide the

project will move forward as originally planned.

Which of the following risk strategies was used?

A.

Accept

B.

Mitigate

C.

Avoid

D.

Transfer

Full Access
Question # 79

A project sponsor asks if a construction project can be accelerated to meet a new timeline. The project manager analyzes the schedule and finds insufficient float to accommodate the new delivery date.

If more resources are provided, which of the following strategies would BEST help to achieve the new date?

A.

Fast track

B.

Burn

C.

Crash

D.

Reduce durations

Full Access
Question # 80

Management announces the PMO will assume all research and development efforts.

Which of the following BEST describes this scenario?

A.

Process change

B.

Business merger

C.

Outsourcing

D.

Relocation

Full Access
Question # 81

Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3.

Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a

duration of one day. Which of the following represents the critical path?

A.

Five days

B.

Six days

C.

Seven days

D.

Eight days

Full Access
Question # 82

A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days.

Which of the following characteristics classifies this as a project?

A.

Repetitive

B.

Ongoing

C.

Iterative

D.

Temporary

Full Access
Question # 83

When an action is taken on a risk, which of the following is being done and which document needs to be updated?

A.

Mitigating risk, and the risk register should be updated

B.

Accepting risk, and the risk review document should be updated

C.

Avoiding risk, and the risk review document should be updated

D.

Exploiting risk, and the risk register should be updated.

Full Access
Question # 84

A daily standup Scrum meeting is BEST accomplished in a:

A.

telephone conference.

B.

group email.

C.

face-to-face meeting.

D.

video conference.

Full Access
Question # 85

The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following factors is MOST likely to influence communication methods across the project?

A.

Personal preferences and message content

B.

Level of message/report detail and confidentiality constraints

C.

Time zones and language barriers

D.

Technological and criticality factors

Full Access
Question # 86

Which of the following statements are correct regarding project management? (Select two.)

A.

A project can be part of an organization’s program management.

B.

An organization’s portfolio will include programs.

C.

A program has a defined start and finish.

D.

An organization’s portfolio is a temporary and unique endeavor.

E.

A project portfolio will be managed under program management.

Full Access
Question # 87

Which of the following is a characteristic of a project?

A.

It solves a business problem.

B.

It created a unique service.

C.

It has a definite beginning and end.

D.

It adheres to a formal framework.

Full Access
Question # 88

A project manager has been experiencing resistance from a group of stakeholders.

With which of the following should the project manager consult to reduce friction going forward?

A.

Project scheduler

B.

Project coordinator

C.

Project sponsor

D.

Project management office

Full Access
Question # 89

The project's network map has a loop with multiple project outcomes.

This is the result of which of the following scheduling tools?

A.

Establishing project schedule baselines

B.

Critical Path Analysis

C.

Critical Chain Method

D.

Graphical evaluation and review technique

Full Access
Question # 90

Which of the following represents the order of the team development stages?

A.

Forming, storming, norming, performing

B.

Forming, performing, storming, norming

C.

Forming, norming, storming, performing

D.

Forming, norming, performing, storming

Full Access
Question # 91

A new project manager is working in an environment where resources report to another supervisor. The

project manager is having difficulty with a particular member and wants to escalate the issue. Which of the

following documents should the project manager consult?

A.

Issue log

B.

RACI chart

C.

Risk management plan

D.

Organizational chart

Full Access
Question # 92

Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project.

Which of the following MOST likely explains this issue?

A.

Risks were not identified.

B.

Risks were not mitigated.

C.

Risks were not exploited.

D.

Risks were not communicated.

Full Access
Question # 93

A project has activities on the critical path that must be completed before other activities can start:

Task A is dependent on Task C before Task D can be completed.

Task A requires Task B to start.

Task B takes twice as long to complete as Task C.

Which of the following is the appropriate ordering of the critical path?

A.

B, A, D

B.

C, B, D, A

C.

D, A, C

D.

B, C, A, D

Full Access
Question # 94

A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it.

Which of the following steps of the control was missed?

A.

Communicate the change

B.

Quality check

C.

Implementation

D.

Evaluate impact and justification

Full Access
Question # 95

Which of the following network scheduling techniques is focused mainly on the duration and stack of each

activity?

A.

Program evaluation review technique

B.

Precedence diagramming method

C.

Arrow diagramming method

D.

Critical path method

Full Access
Question # 96

A project team is working on a project with high public visibility and excitement. The project sponsor is

concerned the public may lose interest due to the long delivery timeline. Which of the following is the BEST

way to keep the external stakeholders informed and engaged throughout the project?

A.

Video conferencing

B.

Instant messaging

C.

Social media

D.

Email

Full Access
Question # 97

Which of the following describes a project’s budget overrun?

A.

The project spends only half of the funds.

B.

The project spends only the allocated funds.

C.

The project spends none of the funds.

D.

The project spends in excess of the funds.

Full Access
Question # 98

Three IT companies have agreed to summarize their efforts as a common organization to generate new businesses in the IT cloud computing industry. Which of the following is the type of organizational change described?

A.

Expansion

B.

Rightsizing

C.

Merger

D.

Onboarding

Full Access
Question # 99

A client has requested a project be completed ahead of schedule. The client understands the triple constraints

and agrees to expand the defect tolerance.

Which of the following should the PM do NEXT?

A.

Crash the schedule.

B.

Notify the project team.

C.

Initiate a change request.

D.

Accept the risk.

Full Access
Question # 100

The final project report should contain which of the following?

A.

Minutes of all the project meetings

B.

Project design documentation

C.

Detailed breakdown of the schedule

D.

Summary of the project cost

Full Access
Question # 101

Which of the following should be included in an effective SOW?

A.

Lessons learned

B.

Procurement process

C.

Corrective action plan

D.

Project objectives

Full Access
Question # 102

A new contractor joining the project team is an example of:

A.

offshoring

B.

offboarding

C.

rightsizing

D.

outsourcing

Full Access
Question # 103

A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:

A.

project management plan

B.

scope statements and issue log

C.

project dashboard and status report

D.

action items and meeting minutes

Full Access
Question # 104

Which of the following is the MOST important component against which the project manager can analyze

project performance?

A.

Burn rate

B.

Project baselines

C.

KPIs

D.

Budget

Full Access
Question # 105

A PM has notified the project team of an immediate project relocation. Of which of the following triggers is this

MOST likely a result? (Choose two.)

A.

Business continuity response

B.

Resource changes

C.

Disaster recovery response

D.

Risk response

E.

Gate review

Full Access
Question # 106

A project manager has taken over a project that is already in progress. The project manager notices the

functional manager of one team is unaware of the current progress. Which of the following should the project

manager do? (Choose two.)

A.

Update the project charter to include the functional manager as a key stakeholder

B.

Publish the project schedule to the functional manager

C.

Review the communications plan to ensure proper involvement

D.

Add the incident to the issue log and seek resolution

E.

Ensure the functional manager is on the status report distribution list

Full Access
Question # 107

Which of the following are mutually binding project documents? (Select two.)

A.

Quotation

B.

Letter of intent

C.

Proposal

D.

Evaluation

E.

Warranty

F.

Charter

Full Access
Question # 108

An active project has a CPI of 0.92. Which of the following can be determined?

A.

The project is currently over budget.

B.

The project has a budget surplus.

C.

The project is ahead of schedule.

D.

The project is behind schedule.

Full Access
Question # 109

A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?

A.

Issues log

B.

Change log

C.

Status report

D.

Meeting minutes

Full Access
Question # 110

Based on the table below:

Which of the following is the total float for the critical path?

A.

0

B.

1

C.

2

D.

3

Full Access
Question # 111

Despite receiving regular updates, a sponsor learns a project recently slipped.

Which of the following documents can the sponsor review to determine the project’s performance? (Select two.)

A.

Status report

B.

Communication plan

C.

Issue log

D.

Project schedule

E.

Action items list

F.

Risk register

Full Access
Question # 112

A client has provided a list of deliverables to include in the project scope. Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?

A.

Requirements traceability matrix

B.

Gantt chart

C.

SWOT analysis

D.

Project charter

Full Access
Question # 113

The project team is moving from high-level risks to detailed risks. Which of the following project phases is the

project team moving between?

A.

Execution to monitor and control

B.

Initiation to planning

C.

Initiation to monitor and control

D.

Planning to execution

Full Access
Question # 114

Which of the following conflict resolution techniques relies on establishing areas of agreement rather than disagreement?

A.

Smoothing

B.

Collaborating

C.

Compromising

D.

Avoiding

Full Access
Question # 115

Based on the table below:

Which of the following is the float of Task B?

A.

-2

B.

0

C.

2

D.

5

Full Access
Question # 116

During the planning phase, the project manager meets with the project team to determine the tasks team to determine the task and their relationship.

Which of the following should the project manager receive from the team members? (Select two.)

A.

Durations

B.

Start/finish dates

C.

Dependencies

D.

Resources

E.

Baseline

Full Access
Question # 117

A project manager is required to maintain various documents and procedures.

Which of the following require ongoing attention and periodic updates?

A.

Project charter

B.

Change requests

C.

Project management plan

D.

Communication plan

E.

Project SOW

Full Access
Question # 118

Given the information in the table below, which of the following is the total project cost?

A.

$40,000

B.

$70,000

C.

$95,000

D.

$120,000

Full Access
Question # 119

A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?

A.

Incident response

B.

Quality control

C.

Resource changes

D.

Business continuity response

Full Access