What are the typical activities of the Strategy to Portfolio Value Stream?
Strategy, Service Portfolio, Demand, Selection
Strategy, Enterprise Architecture, Portfolio, Release
Strategy, Finance, Service Level Management, Investment Portfolio
Strategy, Release, Change, Investment Policy
Which key data object associated with the Change Control functional component records the data required to manage the change lifecycle?
The Change Control data object
The RFC data object
The Problem, Known Error data object
The Interaction data object
What is a purpose of the Test functional component?
To create Defect data objects that are consumed by the Defect functional component
To maintain traceability of each Requirement to the original source
To monitor and report on the results of each integration build
To keep track of all Defects by registering Defects of all types, including security-related Defects